Renovation of a water / sewer project in Bradenton, Florida. Design plans call for the renovation of a water / sewer project.
This project will demolish the existing four million gallons per day (MGD) flow equalization storage tank and replace with two 2.5 MGD storage tanks including mixing systems to keep solids in suspension. Replace the existing return pump station with a new station including a permanent hoist for removing pumps. Provide new odor control and chemical storage/feed facility. Supervisory Control and Data Acquisition (SCADA) programming shall be included; and appurtenances for ventilation/odor control shall be provided. A new transformer and motor control center(MCC) will power existing and new equalization loads along with any loads remaining on Substation Nos. 5 & 6/MCC B1-B4, which shall be removed. Replace existing vertical turbine pumps in the Filter Bypass pump station (four total) to provide 12 MGD capacity. The Flow Equalization (FEQ) tank receives and stores raw influent during the day and returns it to the plant at night to equalize the incoming flow. There is only a single tank and Southwest Water Reclamation Facility (SWWRF) staff cannot take it out of service for cleaning and maintenance, so two tanks would provide flexibility for cleaning, maintenance and flow equalization. The existing FEQ return pump station needs numerous upgrades and replacements. The Filter Bypass pump station needs to be upsized and will provide flow equalization while the existing FEQ tank is being demolished and the new tanks constructed. The project is included in the county's 2022-2027 Capital Improvement Program (CIP). As of August 9, 2022, the project is in the design phase. Information regarding the contractor selection has not been disclosed. A firm timeline for construction has not been established. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available.
Design
Water / Sewer
$17,915,500.00
Public - County
Renovation
Plans and Specifications are not available for this project. If that changes, they will be made available here.
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
January 2, 2023
5101 65th St W, Bradenton, FL
Related To This Project
Bradenton, FL
--
Bradenton, FL
--
Bradenton, FL
Bid Date: Mar 08 2022
Bradenton, FL
Bid Date: Sep 30 2021
Bradenton, FL
--
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.