Site work and renovation of a water / sewer project in Brewer, Maine. Completed plans call for the renovation of a water / sewer project; and for site work for a water / sewer project.
**As of March 18, 2020, this project has not yet been awarded. Anticipated award date is end of April 2020. Work under this project includes, but is not limited to, all labor, materials, expenses, and incidentals for the upgrade of the aeration system at the City of Brewer's wastewater treatment plant and miscellaneous building modifications and concrete repairs including all general conditions and mobilization, demolition and site clearing, structural and trench excavation, backfilling, dewatering, and compaction, earthwork, erosion control, paving, underdrain, site restoration, concrete, masonry, metals, railings and gratings, rough and finish carpentry, panel work, insulation, siding, flashing, sealants, doors and windows, painting, installation of Owner prepurchased aeration blowers and silencers, fine bubble diffused aerators, piping, valves, gates, expansion joints, pipe hangers and supports, seals, electrical wiring and installation, conduit, control panels, HVAC equipment and all incidentals needed for a complete working project. . 5. Bid Bond a Certified Check or Bank Draft Payable to the Owner or a Satisfactory Bid Bond Executed by the Bidder and Surety Company in an Amount Equal to Five Percent (5%) of the Bid Shall Be Submitted With Each Bid. No Bid May Be Withdrawn for at Least 90 Days After Receipt of Bids Unless Released by Owner. 6. Qualifications of Bidder in Order to Be Considered as a Responsive Bidder, Each General Contractor Must Be on the Engineer's Bidding Register by Purchasing at Least One Set of Bidding Documents Directly From the Engineer's Office. The Owner Reserves the Right to Reject Any Bid if the Evidence Submitted by, or Investigation of, Such Bidder Fails to Satisfy the Owner That Such Bidder is Properly Qualified to Carry Out the Obligations of the Contract and to Complete the Work Contemplated Therein. The Successful Bidder Shall Be Required to Provide Both a Performance and a Payment Bond, Each Representing 100% of the Contract Value, at the Time of Contract Execution. 7. Non Discrimination in Employment and Labor Standards Bidders on This Work Will Be Required to Comply With the President's Executive Order No. 11246 and Amendments or Supplements to That Order. The Requirements for Bidders and Contractors Under This Order Are Explained in the Notice to Contractors. 8. Federal Requirements the Contractor Must Comply With All Safety and Health Regulations (Cfr29 Part 1926 and All Subsequent Amendments) as Promulgated by the Us Department of Labor on June 24, 1974, the Department of Labor Regulations Relating to Copeland "Anti-kickback Act (18 U.s.c. 874) as Supplemented by 29 Cfr Part 3, Contract Work Hours and Safety Standards Act (40 U.s.c: 327-330) as Supplemented by 29 Cfr Part 5, and Occupational Safety and Health Standards (Osha) (29 Cfr Part 1910). The Contractor Must Comply With All Applicable Standards, Orders, or Requirements Issued Under Section 306 of the Clean Air Act (42 U.s.c. 1857(H)), Section 508 of the Clean Water Act (33 U.s.c. 1368), and Executive Order 11738. 9. American Iron & Steel Section 746 of Title Vii of the Consolidated Appropriations Act of 2017 (Division a - Agriculture, Rural Development, Food and Drug Administration, and Related Agencies Appropriations Act, 2017) Applies an American Iron and Steel Requirement to This Project. All Iron and Steel Products Used in This Project Must Be Produced in the United States. The Term "Iron and Steel Products" Means the Following Products Made Primarily of Iron or Steel: Such as, but Not Limited to, Lined or Unlined Pipes and Fittings, Manhole Covers and Other Municipal Castings, Hydrants, Tanks, Flanges, Pipe Clamps and Restraints, Valves, Structural Steel, Reinforced Precast Concrete, and Construction Materials. The Deminimus and Minor Components Waivers Apply to This Contract. 10. Award of Contract the Owner Reserves the Right to Reject Any or All Bids, to Accept Any Bid That It Deems to Be in Its Best Interests, and to Waive Any Irregularities in Bidding.
Bid Results
Water / Sewer
$2,603,200.00
Public - City
Renovation, Site Work
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
Sign-up for Instant Access.
Provide your information to unlock 5 active projects and companies from our commercial construction database. Free.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.
January 17, 2020
February 17, 2020
December 13, 2020
To Be Determined, Brewer, ME
Related To This Project
Brewer, ME
Bid Date: Mar 28 2022
Brewer, ME
Bid Date: Jan 08 2024
Brewer, ME
--
Brewer, ME
Bid Date: Feb 21 2024
Brewer, ME
Bid Date: Apr 05 2024
Brewer, ME
Bid Date: Mar 22 2024
Brewer, ME
Bid Date: Mar 27 2024
Brewer, ME
Bid Date: Oct 22 2021
Brewer, ME
Bid Date: Jun 17 2020
Brewer, ME
Bid Date: Oct 04 2019
Brewer, ME
Bid Date: Feb 11 2022
Brewer, ME
Bid Date: Dec 08 2021
Brewer, ME
Bid Date: Aug 31 2023
Brewer, ME
Bid Date: Aug 16 2023
Recently Viewed
--
--
--
--
--
--
--
--
--
--