Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Renovation of a water / sewer project in Hanover Park, Illinois. Completed plans call for the renovation of a water / sewer project.
A. DIGESTER COMPLEX BUILDING (DCB) 1. Upgrade electrical systems to comply with NFPA 820, including constructing walls to isolate un-classified areas from classified areas and provide access doors for un-classified areas. 2. Remove 480 Volt duct bank in the basement of DCB. Provide new buried duct bank for 480 Volt power feeder cables outside DCB. 3. Remove MCC Nos. 5 and 13 from the DCB. Provide new MCC No. 15, Power Distribution Panel Board No. 15A, No. 15B, No. 15C, and No. 15D in the new East and West Electrical Rooms to feed all existing and new equipment. 4. Remove existing and provide new explosion-proof motors, disconnect switches, pushbutton stations, lighting fixtures, panel boards, instrumentation, telephones, conduit, fittings, wiring, junction boxes and other appurtenances for existing equipment. 5. Modify existing Telephone, Gas Detection System and Fire Alarm System to accommodate new and hazardous locations. 6. Remove exterior face brick veneer, windows, limestone sills, louvers and provide face brick veneer wall mock-up and infill brick veneer. 7. Provide concrete over infill around existing digester adjacent to building addition. 8. Remove hot water piping as shown on Contract Documents. 9. Remove five hot water boilers and modify hot water piping for the sludge heat exchangers. 10. Provide cap cover infill at removed boiler stacks on existing concrete roof. 11. Remove mechanical and electrical equipment and piping for digester gas mixing systems for digester Nos. 3, 5 and 6. 12. Remove air compressor, two effluent water pumps, ductwork, water heater, and water piping, near the Gravity Belt Thickener (GBT) area. 13. Provide wall and roof exhaust fans, unit heaters, and electrical infrared heaters. 14. Modify or provide floor drains at various locations. 15. Provide hot water supply and hot water return lines and connect them to the existing headers and branches for air handling units, unit heaters, eyewash stations, and sludge heating. 16. Remove polymer mixing units and eyewash station and provide new polymer mixing units into new polymer room area including epoxy flooring. 17. Extend stainless steel digester gas piping from DCB to new Central Boiler Facility (CBF). 18. Update the Distributed Control System (DCS) to remove unused signals, add new signals, relocate I/O currently in classified area to a new cabinet in the unclassified area and provide a new cabinet and associated I/O for the Central Boiler Facility. B. PUMP & BLOWER HOUSE NO. 2 (ADMINISTRATION BUILDING) - (PBH2) 1. Remove two hot water boilers and associated pumps, piping, boiler stack, equipment pads, and associated electrical, and control work. 2. Remove hot water tank located on the 2nd floor of the PBH2. 3. Remove two primary filter house and one secondary filter house. 4. Remove louvers on South wall, provide new louver on East Wall and perform other architecture work shown on Contract Documents 5. Provide new exit door on East side of PBH2 exterior and close the exit door on South side of the PBH2 exterior. 6. Connect existing hot water piping with new hot water piping from CBF. 7. Modify existing power feedsin PBH2. 8. Provide new potable piping between DCB and PBH2. C. CENTRAL BOILER FACILITY (CBF) 1. Provide new East Electrical Room and Central Boiler Facility, east of existing DCB, including all excavation, foundation, structural, architectural, and civil work, including site preparations, regrading and all work as detailed in the Contract Documents. 2. Provide five boilers (three co-firing boilers and two natural gas boilers) and associated natural gas, digester gas, water piping, and associated mechanical, electrical, and control equipment. 3. Provide four boiler water re-circulation pumps, two plant heating water re-circulation pumps, three process heating water re-circulation pumps, and associated mechanical piping, supports, electrical and control systems. 4. Provide two plate heat exchangers for plant heating and two plate heat exchangers for process heating. 5. Provide a hot water generator with 120 gallons storage tank. Provide piping, as required, to connect with existing hot water piping in the PBH2. 6. Provide floor drain and underdrain piping and connect with existing associated piping in the PBH2. 7. Provide roof drain piping and connect with storm drain South of CBF. 8. Design and provide fire sprinkler system to meet the Village of Hanover Park building ordinance, including all the permit and inspection costs. 9. Provide weather-tight continuous expansion joint between PBH2 and CBF. 10. Provide epoxy flooring. D. MISCELLENOUS WORK 1. Remove yard piping and provide new yard piping, remove abandoned buried duct bank. 2. Excavate and rebuild existing drainage ditch outside DCB and new CBF. 3. Demolish existing and install new driveways and culverts outside DCB. 4. Remove planter in front of PBH2. 5. Coordinate with Nicor Gas to remove natural gas meter and provide new gas meter at location indicated on the drawings. Provide temporary buried natural gas piping for boilers and flares in DCB during construction of CBF. Install permanent buried natural gas piping as shown on the drawings. 6. Provide temporary electrical power supply, as required, during the electrical duct bank installation and commissioning. 7. Provide temporary hot water piping for building heat and digester sludge heating, as required. 8. Provide fully furnished Prefabricated Engineering Field Office for use by the District Construction Staff, with concrete pad, utility connections and any site improvements specified. 9. Perform any other work as specified in the Specifications and as shown on the Plans. KIRIE WATER RECLAMATION PLANT: A. Remove existing construction trailer and provide fully furnished Prefabricated Engineering Field Office at the same location for use by the District Construction Staff, with utility connections and any site improvements specified. WEBSTER AVENUE AERATION STATION: A. Remove existing roofing, roof structure, roof mounted air intake penthouses, and exhaust fans, and replace in accordance with the Contract Documents, including furnishing and installing new roof structure, roofing system, air intake penthouses, exhaust fans, and other associated work. The site of construction is at Hanover Park Water Reclamation Plant, 1200 East Sycamore Ave, Village of Hanover Park, County of Cook, State of Illinois; the Kirie Water Reclamation Plant, 701 W. Oakton Street, Des Plaines, County of Cook, State of Illinois, and the Webster Avenue Aeration Station located at Webster and Ashland Ave and North Branch of the Chicago River, City of Chicago, County of Cook, State of Illinois. The estimated cost of the work under Contract 19-542-3M, is between $12,083,000.00 and $14,627,000.00. Each proposal must be accompanied by a bid deposit in the form of a bid bond in the amount of SIX HUNDERED THOUSAND DOLLARS ($600,000.00). Each bid bond must be underwritten by a surety licensed to do business in the State of Illinois, listed in the latest copy of the Federal Register and approved by the Director of Procurement and Materials Management. The bid bond must contain signatures from the Bidder and Surety Company. Failure to provide signatures on the bid bond will result in the rejection of the bid. Photographic and/or stamped signatures are acceptable. Any proposal submitted without being accompanied by the required bid deposit, in the aforesaid form, will not be considered and will not be read after it is publicly opened. Prior to award of the contract, the lowest responsible bidder must demonstrate compliance with the MWRDGC Multi-Project Labor Agreement by submitting to the Director of Procurement and Materials Management a signed Certification of Compliance with Multi-Project Labor Agreement. The Agreement and Certificate of Compliance are contained in the Contract Documents. The bid money value of all materials purchased directly by the Contractor, together with the bid money value of all work performed by personnel and facilities provided directly by the Contractor, shall not be less than 25% of the money value of all work performed under this Contract. Any bid money value of work performed by the Subcontractors for work on the job site utilizing Subcontractors' materials, labor and facilities cannot be included in the percent of work to be completed by the Contractor. Bidders on contracts in excess of Ten Thousand Dollars ($10,000.00) will be required to comply with the President's Executive Order No. 11246, as amended to date, regarding NONDISCRIMINATION IN EMPLOYMENT. The requirements for bidders and contractors under this order are explained in Appendix C of the Contract Documents. The provisions of Appendix C also apply to each Subcontractor on contracts in excess of Ten Thousand Dollars ($10,000.00). The Bidder agrees to fulfill the Special Training Provisions for Apprentices as specified in the Appendix K and to provide training opportunities throughout the life of the contract. The requirements of the Special Training Provisions for Apprentices are 1288 minority hours and 460 female hours for the purposes of this contract. The bidder shall submit with the Proposal a signed and completed MBE, WBE, SBE Utilization Plan, which lists the firms intended to be used as MBE, WBE, SBE, the type of work or service each will perform, and the dollar amount to be allocated to each MBE, WBE, SBE. The bidder shall submit with the Proposal a signed and completed MBE, WBE, SBE Utilization Plan, which lists the firms intended to be used as MBE, WBE, SBE, the type of work or service each will perform, and the dollar amount to be allocated to each MBE, WBE, SBE. 1.) Each Bidder must submit with the proposals a signed and completed MBE, WBE, SBE Utilization Plan which lists each business intended to be used as a MBE, WBE, SBE on pages UP-2, UP-3 and UP-4 and supplemental pages as necessary. The Bidder must sign the Signature Section page UP-5. Failure to submit a signed MBE, WBE, SBE Utilization Plan will result in a bid being deemed non-responsive and the bid will be rejected. Also, if a Waiver is sought, the Bidder is required to sign pages UP-5 and UP-6, the Waiver Request Form; failure to do so will be viewed as non-responsive and the bid will be rejected. 2.) Each Bidder must submit with their bid package an original or facsimile copy of MBE, WBE, SBE Subcontractor's Letter of Intent, Page UP-7 for each subcontractor listed on their MBE, WBE, SBE Utilization Plan. The submitted MBE, WBE, SBE Subcontractor's Letter of Intent must be completed and signed by the subcontractor and accompanied with a copy of the subcontractor's current Letter of Certification from a state, local government or agency or documentation demonstrating that the subcontractor is a MBE, WBE, or SBE within the meaning of the Affirmative Action Ordinance, Revised Appendix D. Failure to submit the MBE, WBE, SBE Utilization Plan signed by the Bidder at the time of the bid opening and the MBE, WBE, SBE Subcontractor's Letter of Intent signed by each MBE, WBE, SBE will be viewed as non-responsive and the bid will be rejected. 3.) If the Bidder exceeds the allowable Supplier Utilization amount which is stated in the bid documents, the bid will be viewed as non-responsive. Therefore, the Bidder may not exceed the use of a MBE, WBE, SBE supplier for more than 25% of each of the respective MBE, WBE, SBE goal, unless the Director of Procurement and Material Management has authorized a Supplier's Exception notated on page AU-1. 4.) Each Bidder must submit with their proposals a completed VBE Commitment Form which lists each business to be used as a VBE. The Bidder must make a "Good Faith Effort" to identify eligible Veteran Owned Business by completing the VBE Commitment Form. If the Bidder is unable to identify qualified VBE subcontractors capable of providing goods or services required by the contract, the Bidder must write "no participation" on the VBE Commitment Form. Where a Bidder has failed to meet the VBE participation goal, the Administrator shall require the Contractor to submit a Veteran's Business Enterprise Good Faith Efforts Documentation Form and provide additional documentation of its good faith efforts in attempting to fulfill the VBE goal. The Utilization Plan MUST be signed by the bidder, even if the bidder requests a waiver and/or offers itself to meet any of the Affirmative Action Ordinance Revised Appendix D goals. If the bidder offersitself to satisfy any of the Affirmative Action Ordinance Revised Appendix D goals, then its name shall be shown in the appropriate space(s) on the Utilization Plan. Where a bidder is a business owned and controlled by a minority woman (M/WBE) or where the bidder utilizes a M/WBE in a joint venture or as a subcontractor, the bidder may count the M/WBE participation either toward the achievement of its MBE or WBE goal, but not both. If a waiver from the Affirmative Action Ordinance Revised Appendix D requirements is sought, the bidder should include with the bid package documentation of good-faith efforts to meet the Affirmative Action Ordinance Revised Appendix D utilization goals. Subsequent to bid opening and if it is determined by the Affirmative Action Administrator that a Contractor's Information Form is required from the apparent low bidder, the bidder must complete and submit the form within three (3) days of receiving the written request. The work under this Contract is classified as "Mechanical" for the MBE, WBE, SBE Utilization Goals contained in the Affirmative Action Ordinance Revised Appendix D. The associated goals are 20% Minority-owned Business Enterprises (MBE), 9% Women-owned Business Enterprises (WBE), 10% Small Business Enterprises (SBE), and 3% Veteran Business Enterprises (VBE). Should you have any questions, please contact the Diversity Office at 312-751-4035. The MBE, WBE, SBE utilization goals do not apply to the portion of the work assigned to the DCS manufacturer Emerson (COST PROPOSAL B). The bidder to whom the contract is awarded must be prepared to comply with the requirements of the Affirmative Action Ordinance Revised Appendix D during the life of the contract. Any contract or contracts awarded under this invitation for bids are expected to be funded in part by a loan from the Illinois Environmental Protection Agenc y (IEPA). Neither the State of Illinois nor any of its departments, agencies, or employees is or will be a party to this invitation for bids or any resulting contract. The procurement will be subject to regulations contained in the Procedures for issuing Loans from the Water Pollution Control Loan Program (35 IAC Part 365), the Davis-Bacon Act (40 USC 276a through 276a-5) as defined by the United States Department of Labor, the Employment of Illinois Workers on Public Works Act (30 ILCS 570), and the "Use of American Iron and Steel" requirements as contained in Section 436 of H.R. 3547, The Consolidated Appropriations Act, 2014. This procurement is also subject to the District's policy regarding the increased use of small, minority, women, and veteran's business enterprises. The District's policy requires all bidders to undertake specified affirmative efforts at least fifteen (15) days prior to the day of the bid opening. The policy is contained in the specifications. Bidders are also required to comply with the President's Executive Order No. 11246, as amended. The requirements for bidders and contractors under this order are explained in 41 CFR 60-4. Federal Regulations regarding labor standards, the Copeland Anti-Kickback Act, equal employment opportunity and access to work shall be in effect. These regulations appear in Appendices B and I in the Contract Documents and form a part thereof. The Bidder must execute Grant Forms Nos. 1, 2, 3, 4 and 5 in the appropriate place in Appendix B as part of the Proposal. Any Proposal submitted without being accompanied by the executed Grant Forms Nos. 1, 2, 3, 4 and 5 will be rejected as non-responsive. The Bidder shall specifically take note of Section 7, "Certification," of Appendix I regarding non-collusion requirements, and shall comply with same. The District does not guarantee the timeliness of responses provided online, nor does the District guarantee that such responses will be provided in adequate time to affect the submission of bids. The District shall provide responses online ONLY if the responses do not interpret or otherwise change the bidding documents. The District's responses online are NOT official responses and, therefore, are not binding to the bidding documents. Any official interpretation or change to the bidding documents will be made only by addenda duly e-mailed to all plan holders on record by the Director of Procurement and Materials Management. The District will only respond to questions received online UP TO ONE WEEK prior to the bid opening date of the bidding documents. The District will not respond to questions received after this date. The Project Manager for this contract is Mr. Chris Nam. This Project Manager will provide online responses to online inquiries. The Contact person for site visit is Mr. Sanjay Goel at (708) 714-4080/ (847)714-4080 or GoelS@mwrd.org All Contracts for the Construction of Public Works are subject to the Illinois Prevailing Wage Act (820 ILCS 130/.01 et.seq.) The contract will be awarded to the lowest responsible, responsive bidder, unless all bids are rejected. The Metropolitan Water Reclamation District of Greater Chicago reserves the right to reject any or all proposals
Bid Results
Water / Sewer
$13,760,000.00
Public - County
Renovation
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
October 5, 2021
December 6, 2021
1200 Sycamore Ave, Hanover Park, IL
Related To This Project
Hanover Park, IL
Bid Date: Jul 20 2023
Hanover Park, IL
Bid Date: Aug 01 2023
Hanover Park, IL
Bid Date: Aug 11 2023
Hanover Park, IL
Bid Date: Aug 24 2023
Hanover Park, IL
Bid Date: Sep 14 2023
Hanover Park, IL
Bid Date: Nov 18 2021
Hanover Park, IL
Bid Date: Dec 22 2021
Hanover Park, IL
Bid Date: Jul 27 2023
Hanover Park, IL
Bid Date: Jul 27 2023
Hanover Park, IL
Bid Date: Jun 27 2023
Hanover Park, IL
Bid Date: May 18 2023
Hanover Park, IL
Bid Date: Nov 07 2019
Hanover Park, IL
Bid Date: May 02 2023
Hanover Park, IL
Bid Date: Apr 20 2023
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.