Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Renovation of an educational facility in Pueblo, Colorado. Completed plans call for the renovation of a educational facility.
As of September 13, 2022, a design build firm was awarded and construction is underway. *The closed solicitation has been included below for reference: Pueblo School District 60 is seeking competitive proposals from qualified, reliable vendors to replace the electrical distribution system at Central High School. Please see RFP document for full details. Bonding Requirements - Performance Bond 100 % - Payment Bond 100 % Question Acceptance Deadline 02/16/2021 06:00 PM EST Questions are submitted online No Pueblo School District 60 is seeking competitive proposals for the design, engineering, purchase, delivery, and installation of a new electrical distribution system, inclusive of all wiring, main panels, sub-panels and expand electrical capability, if possible. The electrical distribution system is defined as all electrical system components from the main distribution panel to all sub-panels to all termination points (outlets, switches, etc.). The Contractor will also be responsible for the removal and disposal of the existing electrical system, and identifying any hazardous materials remediation/abatement required by the Owner, as required. 1. Contractors will conduct a pre-bid site visit and gather information for the development of a Work Plan. As part of the Work Plan and construction activities the Contractor will identify and comply with all applicable federal, state and local statutes. The Contractor will also comply with applicable terms and conditions of the contract. All submittals shall be approved by the Contractors engineer and State regulatory agencies. 2. The finalized Work Plan and interval construction schedule will be submitted to the District's Project Manager for review and approval prior to the start of construction. The Project Manager will provide to the Contractor any existing drawings/specifications relating to the project. 3. All work must be performed during regular non-school hours and days. 4. The Contractor will mobilize construction forces necessary to begin the project within ten (10) business days after approval of the Work Plan and construction schedule by the District. 5. The Contractor will arrange for the following as needed: a. A secure staging area for storing equipment, materials, tools, and supplies, as the Contractor shall have sole liability for said items, and b. Access to and provision of utilities as needed for design and construction. 6. The following documents, plans, and reports will be provided to the Project Manager: a. Work Schedule and short interval schedule to include daily and weekly activities b. As-built drawings at the end of the project, and c. Inspection Reports as completed. 7. The Contractor will immediately notify the Project Manager of any and all issues that may result in a project delay and/or impact work quality or safety. 8. The Project Manager must be informed of and approve all work done by subcontractors; however, the District will deal only with the Contractor regarding work done and costs incurred by subcontractors. 9. The Contractor will provide all labor, materials, equipment, accessories, etc., required for the design, purchase, delivery, and installation of new electrical distribution system components. All materials and equipment furnished for this job shall be in current production and shall be of quality material. Used, shopworn, demonstrator, prototype, reconditioned, or discontinued equipment or materials are not acceptable. 10. All work will be performed in accordance with current applicable building, plumbing, electrical, and HVAC codes. The Contractors engineer shall perform periodic and final inspections of the work performed, in addition to any State/Local required inspections. The Contractor will be responsible for obtaining all necessary permits and scheduling inspections. 11. The Contractor will provide information and assistance with incentives (green initiatives) and/or rebates and credits that may be offered by manufacturers, utility companies, state and/or federal agencies. 12. The Contractor is responsible for the removal and disposal of the existing electrical system in accordance with local, state and federal regulations, and the Contractor will provide all the necessary equipment, labor, and materials to safely accomplish said removal and disposal. 13. All goods and/or services shall comply with applicable OSHA regulations in effect at the time goods are shipped and/or the service is performed. Safety Data Sheets (SDS) are required in accordance with applicable regulations. SDS must be left on site immediately after goods and/or services have been provided. 14. All installations will be in accordance with manufacturer's recommendations. 15. The Contractor is responsible for removing all construction and packing debris from the work site and keeping a clean, safe work area at all times. Clean up of the work area shall be at no additional cost to the District. If hazardous materials are encountered during execution of the contract, the Contractor will be responsible for notifying the Owner of any said materials for the remediation in accordance with federal, state and local statutes and codes. 16. Safety signs, barricades, and/or other materials will be erected by the Contractor to warn patrons and staff away from work areas. Safety of public, district staff and contractor's employees shall be a priority and shall be the responsibility of the Contractor. 17. All work shall be performed as to not disrupt any school functions, including scheduling for nights, weekends, and non-school days for work to be performed. The Contractor must notify the Project Manager in advance of work that may be disruptive to the normal school operations and parking lot traffic flow. Any shutdown of service and/or utilities must be approved and scheduled with the Project Manager. 18. The Contractor is responsible for providing written documentation to the Project Manager for any work that may affect the District's warranties or existing equipment (for example: roof penetrations). The written documentation must be provided and approved prior to the commencement of work. 19. The Contractor will be held liable for the cost of repair or replacement of structures, utility systems and any other parts of the facility damaged by the Contractor's acts of negligence or lack of full adherence to the requirements of the Scope contained herein. The Contractor will be held liable for the cost of repair or replacement of building components and/or vehicle(s) damaged by falling/flying equipment and/or debris. 20. Warranties for materials, labor, and equipment will be issued in accordance with industry practice. Extended warranties may be requested by the Project Manager as cost and budget allow. 21. The Contractor will respond to inquiries within twenty-four (24) hours and will service any non-working units on the day of the call during the warranty period. The District will not be responsible for any additional costs to repair or replace new equipment or parts that are still under warranty; the Contractor is responsible for all liability. 22. Unless otherwise specified, the Contractor shall unconditionally guarantee the labor and the materials used in performance of this contract within the specified guidelines and recommendations of the manufacturer's warranty. If any defects or signs of deterioration are noted which in the District's opinion are due to faulty workmanship or materials, the Contractor shall be notified and shall make the necessary repairs to correct any deficiency in the system at the Contractor's expense.
Under Construction
Educational
$5,987,010.00
Public - City
Renovation
Documents for this project are exclusively Specifications. If Plans become available, we will add them here.
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
March 1, 2021
July 1, 2021
216 E Orman Ave, Pueblo, CO
Related To This Project
Pueblo, CO
Bid Date: Dec 19 2019
Pueblo, CO
Bid Date: Aug 29 2022
Pueblo, CO
Bid Date: Aug 30 2022
Pueblo, CO
Bid Date: Aug 30 2022
Pueblo, CO
Bid Date: Sep 15 2022
Pueblo, CO
Bid Date: Mar 29 2023
Pueblo, CO
Bid Date: Oct 27 2020
Pueblo, CO
Bid Date: Mar 09 2021
Pueblo, CO
Bid Date: Jul 16 2020
Pueblo, CO
Bid Date: Aug 07 2020
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.