BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Site work and paving for a mixed-use development in Champaign, Illinois. Completed plans call for site work for a sidewalk / parking lot; for paving for a sidewalk / parking lot; and water / sewer project.

As of September 13, 2021, this project has not yet been awarded. A timeline for the award has not yet been established. This project will construct a dedicated egress/exit lane to the south of the existing lanes at the current CERL security entrance off of Farber Drive. The existing exit (south) lane will be converted to a second entrance lane. The existing canopy structure will be relocated to straddle the two southernmost lanes. Existing infrastructure will be relocated or extended to fit the new layout. Infrastructure impacted includes but is not limited to pavement, curb and gutter, actuated security gates and security fencing, electrical supply lines and handholes, and all associated structural foundations. The existing guard house will be relocated onsite by the Contractor for disposal by the Owner. A new Owner-provided guard house shall be installed to fit the new configuration. Select portions of existing pavement and sidewalk adjacent to Farber Drive will be replaced. Drainage improvements, including storm sewers and linear storm water detention areas will be added adjacent to the existing entrance. The project also includes new actuated barrier arms and associated foundations and electrical supply infrastructure. Additional storm water detention is included as a Bid Alternate. Located on the west side of Farber Drive, about 800 feet north of Interstate Drive in Champaign, IL The bid documents include, but are not limited to, the Notice to Bidders, bid forms, the project manual (including supplementary conditions, list of drawings, schedules and tables, details, and specifications), drawings, and addenda. Return. If applicable, the above deposit will be refunded upon the return of the bid documents in good condition within ten (10) days after bid opening date. The bid documents shall remain the property of the Owner. They shall not be returned with the bids, but shall be returned under separate cover to the Professional Services Consultant's office. Contract Documents Prepared By: Farnsworth Group, Inc. 7707 N. Knoxville Ave Suite 200 Peoria, IL 61614 IDOL Schedule of Current Prevailing Wage Rates. Pursuant to the Prevailing Wage Act, the most current schedule of prevailing wage rates for all crafts (which includes the hourly basic wages, the hourly overtime rates, and the hourly fringe rates for health and welfare, insurance, vacation, and pension benefits) published by the Illinois Department of Labor for the locality in which the work is to be performed, that was available to the Owner at the time the documents were issued for bidding, is attached at the end of Document 00 90 00 and incorporated herein. If the Illinois Department of Labor revises the prevailing rate of hourly wages to be paid by the Owner, the revised rate shall apply to this contract. The prevailing rate of hourly wages is revised by the Illinois Department of Labor and is available on the Illinois Department of Labor's official. Builder's Risk Insurance, pursuant to General Conditions Article 19, shall be provided by Division 01 - General Work for the entire Project as determined by the Owner. Owner-purchased building materials and supplies, equipment, machinery and fixtures intended to become a permanent part of the project valued at $0.00-- shall be included in this Builders Risk Insurance coverage. Property Insurance (contents including furniture, fixtures, equipment, etc.). Property Insurance is not required for this Project. For Delay in Substantial Completion. The parties acknowledge that the Contractor's failure to achieve Substantial Completion of the Work within the Contract Time provided by the Contract Documents will cause the Owner to incur significant actual damages of types and in amounts which are impossible or extremely difficult to calculate and ascertain with certainty and accuracy. Accordingly, in lieu of actual damages for delay in Substantial Completion that is not caused solely by the Owner (hereinafter "Contractor Delay"), the Contractor agrees that liquidated damages will be assessed and recovered by the Owner against Contractor in the event of Contractor Delay and without the Owner being required to present any evidence of the amount or character of actual damages sustained by reason thereof. To the best of their ability and based on information available to them as of the time of entering into this Contract, Contractor and Owner have estimated that the fairest and best approximation of actual damages that will be incurred for each day of Contractor Delay beyond the Contract Time is Five hundred Dollars ($500.00) per calendar day. Therefore, in lieu of actual damages, Contractor shall pay Owner liquidated damages in the aforesaid amount per day for each calendar day of Contractor Delay. Such liquidated damages are intended to represent estimated actual damages and are not intended as a penalty, and Contractor shall pay them to Owner without limiting Owner's right to terminate this agreement for default as provided elsewhere herein. The U19067: CERL Farber Drive Extension & Reconstruction project impacts University operations such as project management, commissioning and inspection, and contract management that cannot be interrupted beyond the substantial completion date. Additionally, the extension would affect the consultant and staff at the Construction Engineering Research Lab (CERL). The gate and drive must be available to allow deliveries during business hours and employees to exit during and after business hours. When Owner reasonably believes that Substantial Completion will be inexcusably delayed, Owner shall be entitled, but not required, to withhold from any amounts otherwise due Contractor an amount then believed by Owner to be adequate to recover liquidated damages applicable to such delays. If and when Contractor overcomes Contractor Delay for which Owner has withheld payment and Owner reasonably believes that there has been or will be no other event of Contractor Delay for which Owner would be entitled to withhold from amounts otherwise due Contractor, Owner shall promptly release to Contractor those funds withheld, in anticipation of liquidated damages. This project has diversity goals for participation by BEP certified owned businesses as bidders, subcontractors or suppliers in accordance with the Business Enterprise for Minorities, Women, and Persons with Disabilities Act as defined in Document 00 20 00. NOTE: These diversity goals are separate and distinct from workforce projections (Attachment A of Document 00 40 00). Each Bidder shall name the BEP certified firm(s) it intends to use to meet the specified goals set for this project on Attachment B - Business Enterprise Program Utilization Plan of bid form document 00 40 00. Utilization of WMBE certified vendors must designate full participation as either a MBE or WBE when split goals are identified for purposes of meeting diversity goals. WMBE value may not be split between MBE and WBE. The goals for this project are as follows ("N/A" in "Combined Goal" column means split goals are in effect and "N/A" in "Split Goals" column means combined goals are in effect for each specific division of work): Division of Work Combined Goal(s) Split Goal(s) MBE/WBE/PBE % MBE % WBE % PBE% 01 - General Work 20 N/A N/A N/A Bidders are required to use any and all good faith efforts to meet the diversity goal prior to the time of bid submittal. Bid submittals that do not meet the goal in its entirety must include submission of good faith efforts documentation, including bidders pricing for each diverse subcontractor identified, at the time of bid submittal. These efforts should demonstrate that every attempt to negotiate and secure diverse business participation was made prior to the bid. Bids with zero or low levels of participation at the time of bid may be determined to have not demonstrated good faith efforts and may be found non-responsive. Bidders that fall short of meeting the goal and demonstrate acceptable good faith efforts at the time of bid submittal will be considered with the additional efforts achieved within the 10 day cure period. If the goals are not met, the Bidder shall submit within ten (10) calendar days after Owner notifies bidder of the deficiency, documentation of its good faith efforts to achieve the goals (See General Instructions to Bidders, Document 00 20 00). Failure to submit such documentation, or to use good faith efforts, shall result in rejection of the bid.

Bid Results

Sidewalks / Parking Lot

$371,500.00

Public - State/Provincial

Paving, Site Work

Subscribe For Documents

9 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
124
Active Projects
58
Bidding Soon
775
All Active Projects
365
Updated Recently

One Low Price

  • One license and one market
  • Details and key contacts on all bidding projects
  • Organize your pipeline with a digital bid board
  • Automatically match opportunities to your profile
  • Saved searches deliver daily project leads to your email inbox

Market Pricing Around

  • All Starter Product functionality
  • Access to all documents (plans, specifications, and addenda)
  • Access to planning projects
  • Access to contact information
  • Ability to Export

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

Sign-up for Instant Access.

Get Started Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

August 24, 2021

September 24, 2021

January 20, 2022

img_map_placeholder

Farber Dr, Champaign, IL

Related To This Project


Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.