BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Site work for a road / highway in Toledo, Ohio. Completed plans call for site work for a road / highway.

Construction of Section 4, Phase 1 disposal cell at the Hoffman Road Landfill. Includes mass excavation, soil liner construction, geosynthetics procurement/deployment, leachate management system and ancillary, related infrastructure. Project Type Bid Response Types Line Items Bid Bond Project Paperwork (required) Signed Contract (required) Child Support Affidavit (required) Certificate of Insurance (required) Bureau Workers Compensation Cert (required) Tax Exemption Cert (required) Preliminary Project Schedule (required) Additional Upload Area, if needed Additional Upload Area, if needed Type of Award Lump Sum Preferences MBE - Minority-Owned Business Enterprise WBE - Woman-Owned Business Enterprise Local - Local Business Bid Valid 60 Days Liquidated Damages $950 / Day Start/Delivery Date Upon issued PO Project Duration 8-10 Months Bid Bond 5.00% Payment Bond 0.00% Performance Bond 100.00% Online Q&A Yes Q&A Deadline 12/07/2022 5:00 PM (EST) Questions must be submitted thru electronically. In order to be responsive, all bids must have the following with submittal: Construction Project Paperwork* Line Items Bid Guaranty (bid bond or certified check / cashier's check on a solvent bank) Signed Contract by the Vendor* Child Support Affidavit* Bureau of Worker's Compensation Certificate Tax Exemption Certificate* Insurance Certificate, naming the City of Toledo as an additional insured Project Specific Submissions: Preliminary Project Schedule Unit Rates for Labor & Equipment References for Similar Projects (3 total) Expected Project Personnel (Project Manager, Superintendent, Contract Manager) Major Subcontractors & Suppliers This is a prevailing wage project. The design of this project was completed by the owner's in-house design professional. The Work to be performed under this Contract includes the construction of the 5.3-acre Section 4 Phase 1 Cell. Contractor activities include: stripping, containment berm construction, access road improvements, material excavation and hauling, RSL placement and compaction, providing and installing the leachate drainage layer, installing general fill, access roads and surface water control berms and culverts, and seeding/mulching disturbed areas. Site preparation activities include: -Stripping and clearing materials, and removing designated items from within the proposed limits of construction and designated soil stockpile area; -Construction of a perimeter containment berm for stockpiling of excavated materials; - Mass excavation lacustrine soils overlying glacial till soils for placement in the soil stockpile area; - Access Road construction from the existing Hoffman Road to: o Section 4, Phase 1 Cell; and, o Section 3 disposal area, including stripping, drainage culverts, and placement of General Fill for the protection of existing interim cover. The 5.3-acre composite liner system consists of the following from the bottom to top: - 3-foot thick Recompacted Soil Layer; - 60mil HDPE Geomembrane; - 1-foot thick Leachate Drainage Layer; - Non-Woven Geotextile Fabric; - General Fill for Termination Berms and Access Road improvements; and, - Temporary stormwater diversion berms and drainage culverts. All Work must be carried out and maintained in accordance with the Construction Drawings and Technical Specifications. Materials found to be outside the tolerances identified in the Construction Drawings and Technical Specifications must be reworked or removed and replaced to the approval of the CQA Consultant and at no additional cost to the Owner. Contractor will be responsible for any damage their operations cause to any portion of the Work or existing structures, regardless of the circumstances, and will repair this damage to the approval of the CQA Consultant and at no additional cost to the Owner. Contractor will be responsible for all dewatering and repairs required due to rain or freezing; associated costs are to be included in unit prices. The Contractor will also be responsible for dust control and maintaining all required haul roads during construction.

Award

Roads / Highways

$99,961.00

Public - City

Site Work

12

21

51

8

Subscribe For Documents

61 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
149
Active Projects
78
Bidding Soon
1,330
All Active Projects
601
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

December 20, 2022

January 12, 2023

img_map_placeholder

3962 Hoffman Rd, Toledo, OH

The data you need to build the relationships you want. Try it free.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.