Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
New construction of a fire / police facility in Fayetteville, North Carolina. Completed plans call for the construction of a fire / police facility; and one-story above grade fire / police facility.
The furnishing of labor, material, and equipment entering into the construction of: Swift Water Rescue Building The New Swift Water Rescue Building will be located on the current Fire and Rescue Training Center which is located at 775 Tom Starling Road, Fayetteville NC. The new stand-alone building will be approximately 14,000 square feet. The building will house a large simulation tank use to train emergency service personal on swift water rescues. The building will contain an open space for the housing of the simulation tank, classrooms, restroom and locker rooms and storage area. This building is a single-story steel framed type IIB construction, non-sprinklered, with combination brick and formed metal panel cladding. Bids will be received for single prime contractors. All proposals shall be lump sum. Each proposal shall be accompanied by a cash deposit or a certified check drawn on some bank or trust company, insured by the Federal Deposit Insurance Corporation, of an amount equal to not less than five percent (5%) of the proposal, or in lieu thereof a bidder may offer a bid bond of five percent (5%) of the bid executed by a surety company licensed under the laws of North Carolina to execute the contract in accordance with the bid bond. Said deposit shall be retained by the owner as liquidated damages in event of failure of the successful bidder to execute the contract within ten days after the award or to give satisfactory surety as required by law. A performance bond and a payment bond will be required for one hundred percent (100%) of the contract price. Payment will be made based on ninety five percent (95%) of monthly estimates and final payment made upon completion and acceptance of work. No bid may be withdrawn after the scheduled closing time for the receipt of bids for a period of 30 days. Liquidated damages, as stated in the contract documents [, is an amount reasonably estimated in advance to cover the consequential damages associated with the Owner's economic loss in not being able to use the Project for its intended purposes at the end of the contract's completion date as amended by change order, if any, by reason of failure of the contractor(s) to complete the work within the time specified. Liquidated damages does not include the Owner's extended contract administration costs (including but not limited to additional fees for architectural and engineering services, testing services, inspection services, commissioning services, etc.), such other damages directly resulting from delays caused solely by the contractor, or consequential damages that the Owner identified in the bid documents that may be impacted by any delay caused soley by the Contractor (e.g., if a multi-phased project-subsequent phases, delays in start other projects that are dependent on the completion of this Project, extension of leases and/or maintenance agreements for other facilities). The Contractor shall commence work to be performed under this agreement on a date to be specified in a written order form the designer and shall fully complete all work within 155 consecutive calendar days from, and including said date. For each day in excess of the above number of days, the Contractor shall pay to the Owner the sum of $1,500 per day, as liquidated damages reasonably estimated in advance to cover the losses to be incurred by the Owner by reason of failure of said Contractor to complete the work within the time specified, such time being in the essence of this contract and a material consideration thereof Early Completion of Project: The Contractor may attempt to complete the project prior to the Contract Completion Date. However, such planned early completion shall be for the Contractor's convenience only and shall not create any additional rights of the Contractor or obligations of the Owner under this Contract, nor shall it change the Time for Completion or the Contract Completion Date. The Contractor shall not be required to pay liquidated damages to the Owner because of its failure to complete by its planned earlier date. Likewise, the Owner shall not pay the Contractor any additional compensation for early completion nor will the Owner owe the Contractor any compensation should the Owner, its officers, employees, or agents cause the Contractor not to complete earlier than the date required by the Contract Documents. The contractors shall commence work to be performed under this agreement on a date to be specified in a written Notice to Proceed from the designer and shall fully complete all work hereunder within the time of completion stated. Time is of the essence and the contractor acknowledges the Owner will likely suffer financial damage for failure to complete the work within the time of completion. For each day in excess of the above number of days, the contractor(s) shall pay the owner the sum stated as liquidated damages reasonably estimated in advance to cover the losses to be incurred by the owner by reason of failure of said contractor(s) to complete the work within the time specified, such time being in the essence of this contract and a material consideration thereof. In the event of multiple prime contractors, the designer shall be the judge as to the division of responsibility between the contractor(s), based on the construction schedule, weekly reports and job records, and shall apportion the amount of liquidated damages to be paid by each of them, according to delay caused by any or all of them. Occupancy by the owner under this article will in no way relieve the contractor from his contractual requirement to complete the project within the specified time. The contractor will not be relieved of liquidated damages because of beneficial occupancy. The designer may prorate liquidated damages based on the percentage of project occupied. That no liquidated damages (if applicable) shall be assessed after this date. To provide for sufficient contract balance to cover liquidated damages that will be assessed. The owner reserves the right to reject any or all bids and to waive informalities. the last day for questions is 5:00PM on Wednesday June 15th. All questions following 5:00PM on Wednesday June 15th will not be entertained.
Bid Results
Fire / Police
$4,391,026.00
Public - City
New Construction
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
June 23, 2022
September 5, 2022
775 Tom Starling Rd, Fayetteville, NC
Related To This Project
Fayetteville, NC
Bid Date: Aug 10 2022
Fayetteville, NC
Bid Date: Dec 14 2018
Fayetteville, NC
--
Fayetteville, NC
Bid Date: Jan 04 2023
Fayetteville, NC
Bid Date: Aug 01 2022
Fayetteville, NC
Bid Date: Aug 19 2022
Fayetteville, NC
Bid Date: Aug 03 2022
Fayetteville, NC
Bid Date: Mar 16 2022
Fayetteville, NC
Bid Date: Jul 08 2022
Fayetteville, NC
Bid Date: May 17 2022
Fayetteville, NC
Bid Date: Mar 25 2022
Fayetteville, NC
Bid Date: Jun 17 2022
Fayetteville, NC
Bid Date: May 05 2022
Fayetteville, NC
Bid Date: Jun 25 2022
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.