Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Site work and renovation of a civil project in Bellingham, Washington. Completed plans call for the renovation of a water / sewer project; and for site work for a water / sewer project.
The scope of work for this project consists of furnishing all labor, materials, and equipment necessary for the project identified above including the following major work items: Prior to start of construction, prepare and submit for Engineer approval an Excavation and Water Management Plan and Stormwater Pollution Prevention Plan (SWPPP) describing means and methods to accomplish the Work. Maintain site security, limit public access to project site, and conduct Work activities so as to not interfere with pedestrian, bicycle, or vehicle traffic on adjacent public rights-of-way. Conduct a utility locate. Install and maintain temporary erosion and sedimentation control (TESC) best management practices (BMPs) to prevent any off-site stormwater runoff or materials track-out and maintain them in full compliance with the approved SWPPP and applicable laws, regulations, and ordinances throughout construction. Establish lined and bermed stockpile areas for contaminated soil and for inert (uncontaminated) debris and maintain appropriate BMPs for all stockpiles, including capture and treatment of runoff from the stockpile area, throughout the Work. Remove existing asphalt surface. Remove the former warehouse foundation elements comprised of reinforced concrete floor slab, pile caps, other footings, stem walls, retaining walls and all other concrete foundation elements. The wooden timber pilings shall remain in place and, where extending above the excavation subgrade, they shall be cut a minimum of 6 inches below that subgrade. Retain in place the project-north and project-west edges of the warehouse foundation until completion of the Phase 1 excavation of contaminated soil is complete as determined by Engineer. Remove all other aboveground and buried concrete structures (e.g., tank pads). Remove all ancillary metal components associated with the concrete foundations being removed. Remove all remnant structures from a pair of railroad spurs (metal rails, wooden railroad ties, and any underlying concrete). Load, transport, and properly recycle the removed inert debris (concrete, asphalt, and metal) at a facility permitted to recycle it. Dispose of the wooden railroad ties, and any other contaminated debris identified by Engineer, as Subtitle D material. As directed by the Engineer, excavate contaminated soil to depths generally less than 4 feet, but with localized depths as great as 7.5 feet below Existing Grade, and to achieve subgrade elevations where specified. Conduct the excavation of contaminated soil in three designated phases (Phase 1, Phase 2, Phase 3), with prioritization for completing Phase 1 excavation (including Engineer's performance monitoring) as expediently as possible. As directed by the Engineer, segregate the excavated contaminated soil into one of three waste streams: Class 2 soil, Class 3 soil, and Subtitle D soil each with specified requirements for landfill disposal. Contaminated Debris identified by Engineer shall also be disposed of at a Subtitle D landfill. Load, transport, and properly dispose each of the contaminated material waste streams at a landfill permitted to receive the material. Assist the Engineer with soil sampling in Phase 1 excavations and, based on testing results, excavate additional contaminated soils as directed by the Engineer. Remove inactive subsurface utilities to the extent necessary to complete the excavation of contaminated soils or as otherwise directed by Engineer. Cut, plug, remove, and dispose of buried pipes that are encountered during excavation. Throughout excavation, remove groundwater as necessary to allow excavation and handling of unsaturated soil and otherwise perform the Work. The Contractor is responsible for all dewatering efforts including providing and installing sumps, pumps, power source (e.g., electrical generators), treatment equipment, temporary storage, conveyance, and to operate the system without leakage. Treat the extracted groundwater, and any stormwater collecting within the stockpile area, to meet Project Water Quality Performance Standards specific to the water discharge method, and discharge the water by one of two methods: Convey it via water truck and discharge it to the Owner's pump station for the Aerated Stabilization Basin (ASB) located approximately 1,000 feet project-north of the Project Limits in accordance with the Owner's NPDES permit for that facility; or Discharge it to City of Bellingham storm drain via an existing buried stub[1]out near the project-northwest corner of the Project Limits in accordance with a NPDES Construction Stormwater General Permit with Project[1]specific Administrative Order (CSGWP) obtained by Owner. Upon execution of the Contract, the Owner will conduct complete transfer of the CSWGP with Administrative Order to the Contractor who will then become solely responsible for compliance with all of its requirements. Backfill and compact excavations with a combination of imported uncontaminated aggregate and crushed rock, as specified depending on location. Each bid must be accompanied by a cashiers check, money order, or an original signed and stamped surety bid bond in an amount not less than five percent (5%) of the total bid, made payable to the Port of Bellingham. The successful Contractor / Vendor will be required to comply with the bonding requirements of RCW 39.08.010. If a Payment and Performance Bond is used to fulfill this requirement, the successful Contractor / Vendor shall use owner provided Payment and Performance Bond form and shall execute and deliver to the Port of Bellingham the bond or other surety for one hundred percent (100%) of the bid amount for the entire project in compliance with RCW 39.08.010. The Contractor is also responsible for forwarding copies of Payment and Performance Bonds to all sub-contractors, suppliers and all other service providers as requested. The Payment and Performance Bond consists of the Payment and Performance Bond form provided in the Bid Solicitation Documents and a Power of Attorney of the Surety evidencing the authority of the signor of the bond. Both the Payment and Performance Bond and the Power of Attorney shall be submitted in a fully executed, original hard copy document. The Payment and Performance Bond shall have original signatures for the principal and surety and include the original surety seal. The Power of Attorney shall be an original document and include the original corporate seal of surety represented. Submission of copies will not be accepted. The Port of Bellingham reserves the right to reject any or all bids and to waive any irregularities or informalities. To register your company on the Plan Holders list, please contact Brian Wilson, Contracts Administrator by email at brianw@portofbellingham.com. All bids submitted shall be considered as valid offers for a period of forty-five (45) days from the date of the bid opening during which time the Port of Bellingham will make the award or return all bids.
Award
Water / Sewer
$2,628,505.00
Public - City
Renovation, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
August 1, 2022
September 30, 2022
1801 Roeder Ave, Bellingham, WA
Related To This Project
Bellingham, WA
Bid Date: Sep 20 2022
Bellingham, WA
Bid Date: Sep 21 2022
Bellingham, WA
Bid Date: Sep 21 2022
Bellingham, WA
Bid Date: Aug 30 2022
Bellingham, WA
--
Bellingham, WA
--
Bellingham, WA
--
Bellingham, WA
--
Bellingham, WA
Bid Date: May 26 2020
Bellingham, WA
Bid Date: Nov 09 2021
Bellingham, WA
Bid Date: Dec 20 2022
Bellingham, WA
--
Bellingham, WA
Bid Date: Jul 05 2022
Bellingham, WA
Bid Date: Aug 30 2022
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.