BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Site work for a water / sewer project in Savannah, Georgia. Completed plans call for site work for a water / sewer project.

This SOLICITATION is for the FY23 Savannah Inner Harbor Maintenance Dredging. This acquisition is being offered as an unrestricted competitive solicitation and will result in a Firm Fixed Price Contract Award. The magnitude of this requirement per DFARS 236.204(ii) is between $25,000,000.00 and $100,000,000. Project Location: The work is located in the deep draft Savannah Harbor navigation project in Georgia. The Savannah Habor project is located on the border of Georgia (GA) and South Carolina (SC) in Chatham and Jasper Counties. Project Description: The Savannah Inner Harbor Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a hydraulic cutterhead dredge, and the duration is expected to be one year from Notice to Proceed. Up to four million cubic yards of maintenance material is expected to be removed from the inner harbor. The work is located in the deep draft Savannah Harbor navigation project in Georgia in the vicinity of Chatham County, Georgia (GA) and Jasper County, South Carolina (SC). The Savannah Inner Harbor channel is 47 ft. deep MLLW and 500 ft. wide to the upper end of Kings Island Turning Basin: 36 ft. deep MLLW and 400 ft. wide to the upper end of Argyle Island Turning Basin; and 30 ft. deep MLLW and 200 ft. wide to the upper limit of the project. Savannah Harbor s Kings Island Turning Basin (KITB) is the primary turning basin for large civilian and military ships, lying adjacent to the Georgia Ports Authority docks. KITB requires dredging twice a year to allow the loaded ships to freely turn when using the port. Up to 1.6 million cubic yards of maintenance material is removed from the KITB annually. Other contractor(s) may be working for the Savannah District on the Savannah Harbor, to include confined upland dredged material containment areas and designated staging areas. If such work occurs, the contractors shall coordinate activities under the direction of the Contracting Officer. A majority of the material dredged from the Savannah Inner Harbor must be placed in upland confined disposal areas adjacent to the Savannah River. Savannah confined upland disposal areas DMCAs 12A, 13A, 13B and Jones Oysterbed Island are owned by local sponsor Georgia Department of Transportation. Disposal areas DMCAs 14A and 14B are owned by the Joint Project Office of the Georgia and South Carolina Port Authorities. Portions of DMCAs 2A and Jones/Oysterbed are owned by the Georgia Department of Transportation and the US Fish and Wildlife Service. DMCA 1N is owned entirely by the US Fish and Wildlife Service. The Federal Government holds existing easements on all confined upland disposal areas in the Savannah Harbor except DMCA 1N which has a Memorandum of Understanding. Environmental windows limit the timing of dredging in the Savannah Inner Harbor. The environmental windows in Savannah include a Striped Bass spawning window (2 weeks between approximate dates 1 April through 15 May timeframe) which limits the amount and timing of dredging above station 63+360 (River Mile 12), and a dissolved oxygen window (approximately July 1 through September 30). To protect sturgeon aggregation areas in the upper river, no dredging is allowed above STA105+500 1 May through 31 October. Certain reaches of O and M sediments may contain cadmium (Cd) in levels significant enough to harm foraging avian species in the DMCAs. Therefore, O and M sediments in those reaches will be tested by the Government prior to dredging. If Cd is found in those sediments equal to or greater than 14 mg/kg, then options will be exercised that include disposal of the sediments in specific DMCAs under special handling conditions. Obstructions are objects or materials in the required side slope cross sections or in the existing ground surface which are unknown at the time of encounter by the dredge or identified by pre and post hydrographic surveys, and monthly condition surveys. Obstructions are objects which cannot be removed by a hydraulic pipeline dredge. The Contractor may encounter obstructions during dredging operations and must remove the objects or materials to provide the required section as shown on the cross-section plates. If the Contractor is performing maintenance dredging with a pipeline dredge, the dredge must act as a probe for obstructions. The object removed will be the property of the Contractor unless it has been determined to be culturally significant. The base contract will include mobilization/demobilization, maintenance dredging, moves, dive team diving, and equipment rental for obstruction removal. Contract options include Cd dredging with placement to the backside of DA 14B and maintenance dredging as cap material placed on top of the Cd dredged material. Title of Project: FY 23 Savannah Inner Harbor Maintenance Dredging Bidder Inquiry Key: ZFYQQU-5JGVZ2 *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document.

Bid Results

Water / Sewer

$20,825,200.00

Public - Federal

Site Work

99

20

24

8

Subscribe For Documents

7 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
54
Active Projects
23
Bidding Soon
500
All Active Projects
204
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

May 18, 2023

June 12, 2023

img_map_placeholder

To Be Determined, Savannah, GA

The data you need to build the relationships you want. Try it free.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.