Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Published June 12, 2025 at 8:00 PM
Updated June 13, 2025
Site work for a water / sewer project in Sioux City, Iowa. Conceptual plans call for site work for a water / sewer project.
Update:Due to the recent identification of special flood hazard zones in the Hoeven Valley, the need to identify mitigation alternatives for the individual areas is necessary. An evaluation of the area was completed, and options are under consideration. A portion of the work plan was identified out of the Floyd River Flood Reduction Study completed by HR Green in August 2013. This identified project work to include berm modifications & additional culverts which will reduce the extent of the flood zone and accommodate a recreational trail. Additionally, in July 2015 HR Green completed the Leeds Area Interior Drainage Study which built upon the data collected in the 2013 study and identified in greater detail the existing conveyance network and ponding scenarios associated with many storm events. In 2018 HR Green started working towards 30% plans to submit a Conditional Letter of Map Revision (CLOMR) application to FEMA. Pending FEMA's acceptance of the modeling results, storm infrastructure upgrades, estimated at a cost of $2.6 million in FY 2013, will be completed to prevent flooding resulting from a 100-year rain event for properties in the Leeds area. These improvements include an excavated channel, approximately 500' of new 48" pipe, approximately 525' of new 60" pipe, and approximately 125' of upgraded pipe from 36" to 48". This option would still allow some ponding in the street right-of-way but remove the clear majority of the 133 properties from Zone AH. No properties would be affected by flooding of one foot or greater; however, 7 of the 133 properties would be impacted by flood depths smaller than one foot. The flooding would be limited to water slightly crossing the property line of 5 residential and 2 businesses along Floyd Boulevard and Fillmore Street. Similar work has been required for the Perry Creek area, which has lessened the flood hazard area. The City feels that when implemented this project will lead to fewer residents and businesses being impacted by interior ponding. The result of these projects will be to open development area and reduce the flood insurance requirements for individuals and businesses. Adjustments within the project budget and available cash balance will be used to cover costs of property acquisition needed for underground storage and an excavated channel Project is included in City of Sioux City Fiscal Year 2025-2030 ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Due to the recent identification of special flood hazard zones in the Hoeven Valley, the need to identify mitigation alternatives for the individual areas is necessary. An evaluation of the area was completed, and options are under consideration. A portion of the work plan was identified out of the Floyd River Flood Reduction Study completed by HR Green in August 2013. This identified project work to include berm modifications & additional culverts which will reduce the extent of the flood zone and accommodate a recreational trail. Additionally, in July 2015 HR Green completed the Leeds Area Interior Drainage Study which built upon the data collected in the 2013 study and identified in greater detail the existing conveyance network and ponding scenarios associated with many storm events. In 2018 HR Green started working towards 30% plans to submit a Conditional Letter of Map Revision (CLOMR) application to FEMA. Pending FEMA's acceptance of the modeling results, storm infrastructure upgrades, estimated at a cost of $2.6 million in FY 2013, will be completed to prevent flooding resulting from a 100-year rain event for properties in the Leeds area. These improvements include an excavated channel, approximately 500' of new 48" pipe, approximately 525' of new 60" pipe, and approximately 125' of upgraded pipe from 36" to 48". This option would still allow some ponding in the street right-of-way but remove the clear majority of the 133 properties from Zone AH. No properties would be affected by flooding of one foot or greater; however, 7 of the 133 properties would be impacted by flood depths smaller than one foot. The flooding would be limited to water slightly crossing the property line of 5 residential and 2 businesses along Floyd Boulevard and Fillmore Street. Similar work has been required for the Perry Creek area, which has lessened the flood hazard area. The City feels that when implemented this project will lead to fewer residents and businesses being impacted by interior ponding. The result of these projects will be to open development area and reduce the flood insurance requirements for individuals and businesses. Adjustments within the project budget and available cash balance will be used to cover costs of property acquisition needed for underground storage and an excavated channel This project is included in the city's fy 2025-2029 Capital Improvement Program. As of March 6, 2025, further details regarding construction and completion timelines have not been identified. *Project information has been obtained through a public capital improvement plan (CIP). A CIP is a financial schedule for short- and long-range projects which is updated regularly. Information listed in the CIP often evolves based on funding availability and the project details, including timeline and value, are subject to change. The content management team will continue to pursue additional details as they become available.
Conceptual
Water / Sewer
$4,540,000.00
Public - City
Site Work
Plans and Specifications are not available for this project. If that changes, they will be made available here.
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
July 1, 2026
Outer Dr N, Sioux City, IA
Related To This Project
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
--
Sioux City, IA
Bid Date: Jun 13 2023
Sioux City, IA
--
Unlock Efficiency: The Future of Commercial Construction is Data-Driven
Sign up now to get free company and project data. No payment required.
