Site work, renovation and addition to an educational facility in Laurel, Montana. Completed plans call for the addition of a 85,500-square-foot educational facility; for site work for a educational facility; and for the renovation of a educational facility.

Phased construction began March 2024, with entire project completion slated for August 2025. All subcontractor trades have been closed. Planned work generally includes the construction of approximately 68,000 square feet at the new Mogan Elementary, 17,500 square feet addition to the existing West Elementary School, along with additional remodel area on West Elementary. Payment and performance bonds may be required at the discretion of the Construction Manager and Owner. The amendment would include construction services through completion of the Project. Alternatively, Langlas may, at its sole discretion, choose not to continue the Contract beyond the completion of preconstruction activities and solicit bids from qualified contractors for the construction of the Project, in accordance with provisions set forth in the complete Bid Package document. This Bid/RFP shall not commit Langlas to enter into any agreement, to pay any expenses incurred in preparation of any response to this request, or to procure or contract for any supplies, goods or services. Langlas reserves the right to accept or reject any and all responses received as a result of this Request if it is in the Project's best interest to do so. Estimate = total project construction cost estimate ALL QUESTIONS AND CONTACTS REGARDING THIS RFP MUST BE SUBMITTED IN WRITING TO: Jason Hubbard, Sr. Project Manager jhub@langlas.com Office: 406-656-0629 Cell: 406-860-1870 The Laurel Elementary School Projects will consist of two elementary schools. West Elementary School has 30,000 sf of additions and a partial remodel of the existing that will be located in Laurel at 502 8th Ave. This building additions will be a 2-story steel and concrete structure as a classroom addition and a masonry and steel structure for a gym addition. Mogan Elementary will be a 66,600 sf new ground up elementary school. The new school with a 3-story steel and concrete structure. These projects will start in early spring of 2024 and be completed August of 2025. Addendum #1 has been issued as of 11-30-2023.

Under Construction

Educational

$50,000,000.00

Public - City

Addition, Renovation, Site Work

376

13

2

2

Subscribe For Documents

7 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
1
Active Projects
0
Bidding Soon
33
All Active Projects
13
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

December 7, 2023

March 4, 2024

img_map_placeholder

Multiple Locations, Laurel, MT


Get the most reliable construction project data instantly.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.