Site work and new construction of a water / sewer project in Emmitsburg, Maryland. Completed plans call for the construction of a water / sewer project; and for site work for a water / sewer project.
Water Treatment Plant Clarifier. The Town of Emmitsburg is requesting Bids to construct a Water Clarifier to improve raw water clarity flowing into the plant, reduce damage to the plants equipment and reduce the millions of gallons of lake water wasted through backwashes. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. Project Cost Class D - $1,000,000 to $2,500,000. The Project has an expected duration of 360 days. A Bid must be accompanied by Bid security made payable to Owner in an amount of Five (5) percent of Bidder's maximum Bid price (determined by adding the base bid and all alternates) Bidding Documents and any performance and payment bonds required by the Bidding Documents. Liquidated Damages Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones not achieved within the Contract Times, as duly modified. Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work. Required Bid security in the form of a Bid Bond (EJCDC No. C-430) or Certified Check The Project includes the following Work: Furnishing all labor, materials, equipment and performance of work for construction of the new Water Treatment Plant Clarifier. Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows: A. Via email to Bill Gross, PE at bgross@rkk.com and copy John C. Moore, PE at jmoore@rkk.com; Cathy Willets at cwillets@emmitsburgmd.gov; and Madeline Shaw at mshaw@emmitsburgmd.gov.
Award
Water / Sewer
$2,329,561.00
Public - City
New Construction, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
February 28, 2024
April 29, 2024
8585 Crystal Fountain Rd, Emmitsburg, MD
Related To This Project
Emmitsburg, MD
Bid Date: Feb 12 2024
Emmitsburg, MD
--
Emmitsburg, MD
Bid Date: May 17 2024
Emmitsburg, MD
Bid Date: May 21 2024
Emmitsburg, MD
Bid Date: May 21 2024
Emmitsburg, MD
Bid Date: Jun 04 2024
Emmitsburg, MD
Bid Date: Aug 28 2024
Emmitsburg, MD
Bid Date: Aug 16 2024
Emmitsburg, MD
Bid Date: Feb 09 2024
Emmitsburg, MD
Bid Date: Feb 08 2024
Emmitsburg, MD
Bid Date: Nov 01 2019
Emmitsburg, MD
Bid Date: Dec 13 2023
Emmitsburg, MD
Bid Date: Nov 17 2023
Emmitsburg, MD
Bid Date: Nov 01 2023
Emmitsburg, MD
Bid Date: May 17 2022
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.