Site work and new construction of a municipal facility in Milwaukee, Wisconsin. Working plans call for the construction of a 374,000-square-foot, 10-story above grade municipal facility; and for site work for a municipal facility.
As of March 25, 2026, an architect and construction manager team has been chosen for this project. Demolition is expected to begin in 2028 and construction is expected to be completed in 2032. *Previous solicitation listed below for reference:* Contract Description: This project will confirm and challenge the findings of the previous phases and incorporate additional County initiatives which were identified after the completion of Phase III and through the completion of Phase IV. This project will confirm and challenge the findings of the previous phases and incorporate additional County initiatives which were identified after the completion of Phase III and through the completion of Phase IV. While most of the planning to-date has assumed construction of a new courthouse in the same footprint of the existing Public Safety Building, that also presents a significant challenge and cost in relocating staff and functions out of the Public Safety Building to a temporary location while the Public Safety Building is razed, and the new courthouse is constructed. County staff have investigated alternate locations for the new courthouse that would eliminate the need for temporary relocation and razing of the Public Safety Building. The site recommendation will be led by the Design Consultant with input from the project team, concluding the selected Construction Manager. Seven total site alternatives on six sites are currently planned to be evaluated, including the sites below and any additional sites identified by the County RFP-Scoring and shortlist 12/6/2024 RFP-Interviews 12/18/2024 RFP-Selection 1/7/2025 RFP-Award, Execution, and Notice to Proceed 2/4/2025 Conceptual design of new courthouse on PSB site: 374,000 square foot building, 10 story tower for 26 courtrooms and associated spaces, adjacent 4-story building for administrative space. Design meets program requirements including State Supreme Court standards: o Total project cost estimate in 2019 was $300-350M Escalated to 2025 construction $440-490M
Pre-Construction/Negotiated
Municipal
$490,000,000.00
Public - County
New Construction, Site Work
Documents for this project are exclusively Specifications. If Plans become available, we will add them here.
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
November 13, 2024
March 1, 2028
901 N 9th St, Milwaukee, WI
Related To This Project
Milwaukee, WI
--
Milwaukee, WI
Bid Date: Dec 03 2024
Milwaukee, WI
Bid Date: Dec 17 2025
Milwaukee, WI
Bid Date: Jan 14 2025
Milwaukee, WI
Bid Date: Apr 01 2025
Milwaukee, WI
Bid Date: Dec 04 2024
Milwaukee, WI
Bid Date: Dec 02 2024
Milwaukee, WI
--
Milwaukee, WI
Bid Date: Nov 22 2024
Milwaukee, WI
Bid Date: Nov 22 2024
Milwaukee, WI
Bid Date: Nov 26 2024
Milwaukee, WI
Bid Date: May 21 2021
Milwaukee, WI
Bid Date: Nov 12 2024
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.