Site work and paving for a road / highway in Winston Salem, North Carolina. Design plans call for site work for a road / highway; and for paving for a road / highway.
As of July 28, 2025, this project is in the design phase. It is expected to be let for construction in September of 2026. *Previous solicitation listed below for reference:* This RFLOI is to solicit responses (LETTERS of INTEREST, or LOIs) from qualified firms to provide professional consulting services to design the extension of Piedmont Regional Greenway in Winston-Salem, North Carolina along Kerners Mill Creek from Linville Road to Hastings Hill Road. Summary: In 2013, the City of Winston-Salem entered into an agreement with NCDOT for the acceptance of STP-DA funding for the construction of 6,500 linear feet of greenway along Kerners Mill Creek from Linville Road to Hastings Hill Road, including a pedestrian culvert under Hastings Hill Road and boardwalks. Some preliminary environmental and flood studies have been performed. This work will include but not limited to hydraulic design, location surveys, erosion control plans and permitting, preparation of construction contract proposal and estimates, and utility coordination. All applicants should be familiar with these processes and provide examples in Section III - "Project Understanding and Similar Projects". This project is approximately at 50% design completion. The selected firm will need to take the existing design and complete drainage, erosion control, erosion control permit; and finalize plans, quantities, and contract special provisions per Federal/NCDOT standards. The construction contractor will provide culvert and pedestrian boardwalk plans. Piedmont Regional Greenway is being partially funded with Federal Funds which pass through the North Carolina Department of Transportation (NCDOT). Experience and thorough understanding of the FHWA and NCDOT requirements is essential. This project must adhere to all Federal and State of North Carolina standards. All technical or other questions concerning this request for Letters of Interest should be submitted in writing only by 5:00 PM, August 20, 2024 to Wes Kimbrell at: wesleyki@cityofws.org. The firm must have the financial ability to undertake the work and assume the liability. The selected firm(s) will be required to furnish proof of Professional Liability insurance coverage in the minimum amount of $1,000,000.00. The firm(s) must have an adequate accounting system to identify costs chargeable to the project. SCOPE OF WORK The City of Winston-Salem is soliciting proposals for the services of a firm/team for the following contract scope of work: 1. Designing approximately 6,500 linear feet of greenway along Kerners Mill Creek from Linville Road to Hastings Hill Road. 2. This work will include, but not limited to, hydraulic design, location surveys, construction plans, and erosion control plans and permitting, and utility coordination. 3. Provide special contract provisions. 4. Preparation of construction plans, including Engineer's Opinion of Probable Cost with proposed quantities and unit costs. PROPOSED CONTRACT TIME: From Notice To Proceed until project completion, anticipated completion date of December 31, 2025. PROPOSED CONTRACT PAYMENT TYPE: Proposed Contract Payment Type - i.e. LUMP SUM; NOT TO EXCEED negotiated price, to be invoiced no more than once every 30 days.
Design
Roads / Highways
$2,120,000.00
Public - City
Paving, Site Work
Documents for this project are exclusively Specifications. If Plans become available, we will add them here.
3
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
November 2, 2026
Mill Creek Rd, Winston Salem, NC
Related To This Project
Winston Salem, NC
Bid Date: Apr 11 2024
Winston Salem, NC
Bid Date: Mar 22 2024
Winston Salem, NC
Bid Date: Apr 10 2024
Winston Salem, NC
--
Winston Salem, NC
--
Winston Salem, NC
Bid Date: Apr 23 2024
Winston Salem, NC
Bid Date: Apr 25 2024
Winston Salem, NC
Bid Date: May 07 2024
Winston Salem, NC
--
Winston Salem, NC
--
Winston Salem, NC
--
Winston Salem, NC
Bid Date: Oct 23 2024
Winston Salem, NC
--
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.