BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Site work for a water / sewer project in Richmond, California. Completed plans call for site work for a water / sewer project.

The City of Richmond's sanitary sewer collection system is periodically CCTVd by Veolia Operation and Maintenance staff. This information has been assessed by Veolia and V.W. Housen and Associates, which has identified several pipe segments, which are currently inaccessible due to obstruction, line collapse, joint defect and other such defects that are in need of repairs and/or replacement. Online Q&A Yes Q&A Deadline 04/09/2024 11:00 AM (PDT) Estimated Project Cost - The construction cost for this project is estimated to be approximately $2,500,000. Veolia Water West Operating Services, Inc. operates and maintains the City of Richmond's Wastewater Treatment Facility (WWTF) and the associated sewer collection system. The work will include pipe segment replacement of deteriorated sewer pipe segments within the collection system using pipe bursting, open cut, or pipe reaming as discussed further below. The work shall include manhole installation and/or replacement and/or full interior surface (e.g. chimney, cone, wall, bench, and channel) rehabilitation when the adjacent pipeline is replaced, and manhole frames and covers as necessary. For pipe replacement work, pipe bursting is the preferred method, followed by open cut and then pipe reaming. The pipe segments to be replaced for this project are identified in Scope of Work Attachment A. The line segments identified may be modified from time-to-time during the project. The selected Contractor shall conduct a pre-CCTV of each line segment to the greatest extent possible to mark and locate the defects prior to commencement of the Work. A complete NASSCO graded post-construction CCTV survey of the entire line segment (manhole to manhole) shall be completed upon completion of the work (no later than one week after the repair or replacement) and provided to Veolia. If following the repair, the line remains inaccessible, the contractor shall provide a supplemental repair cost proposal with the CCTV video for consideration. The project scope includes, but is not limited to the following: 1. Contracting with a local Civil Professional Engineer to provide review and approval of each line segment installation, and preliminary engineering and design for the lines which have utility conflicts, or other constructability issues. The Engineer of Record shall submit an initial plan showing the lines that will receive preliminary engineering for review and concurrence, followed by 30 percent design drawings clearly showing all conflicting utilities, structures, and other field constraints and the contractor's approach to addressing these constraints as needed to complete the work . The contractor shall be responsible for addressing all field conditions, whether included or not included in the 30 percent design package, and whether shown or not shown on the submitted design. The initial plan and the 30 percent designs shall be approved in concept by the Owner. Separate designs may be provided for individual line segments in order to expedite the work. 2. Submit final as-built drawings and any intermediate design and modifications for all pipelines, including those that did not receive 30 percent design, to the Owner for approval. 3. Contractor shall provide a construction project schedule, including weekly schedules with crew information and locations as reasonably required by Veolia. 4. Contractor shall provide bi-weekly updates for progress of pipe replacement/repair work 5. Sheeting, shoring and bracing. 6. Trenching width shall be (Pipe OD + 24" MIN) or (Pipe OD + 36" MAX). 7. Potholing existing utilities based on mandatory USA markings. 8. All USA markings shall be removed from the pavement after work is complete. 9. Traffic control, as necessary per City of Richmond requirements. 10. Pipe replacement by pipe bursting, unless inadvisable or infeasible with authorization by Veolia and the City of Richmond. 11. Open Cut techniques permitted only if pipe bursting is not feasible and with authorization by Veolia and the City of Richmond. 12. Reconnection and/or extension of existing service laterals to new sewer main, as necessary. 13. Extending sewer laterals from the closest point of abandoned sewer mains to new sewer mains. Open cut or hand-digging may be required. 14. Removal of existing manholes or cleanouts and construction of new manholes, complete, as needed. 15. Rehabilitation of Manholes whenever the adjacent pipeline is replaced, per attached specifications. Vacuum testing of rehabilitated brick manholes is not required. 16. Post Construction cleaning of sewer pipe line segments that were replaced. 17. Post replacement NASSCO graded CCTV of the entire line segment. 18. Post construction NASSCO graded CCTV information shall be submitted no later than one week following the line segment replacement. 19. Restoration and repair of existing pavement systems shall be T-cut, and the Contractor shall be responsible for restoring surface improvements affected by the Work and incidentals for complete and usable sewer system. 20. If the Contractor encounters defective private sewer lateral connecting to the mainline, the Contractor shall replace up to 6 feet of the private sewer lateral from the mainline. 21. Replace striping with thermoplastic, traffic loops, and fire hydrant markers. 22. Handling and disposal of contaminated material if authorized by the Project Manager and the City of Richmond. 23. Dewatering and obtain appropriate permits, as necessary. 24. Construction shall be Monday thru Friday from 7am to 4pm. Contractor's request for weekend, offhours and holiday work may be considered on a case-by-case basis by Veolia Project Manager. Substantial Completion of this project by October 1, 2024 ; final completion- 30 calendar days after Substantial Completion.

Bid Results

Water / Sewer

$1,690,800.00

Public - City

Site Work

Documents for this project are exclusively Specifications. If Plans become available, we will add them here.

10

Subscribe For Documents

37 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
354
Active Projects
173
Bidding Soon
3,366
All Active Projects
1,366
Updated Recently

One Low Price

  • One license and one market
  • Details and key contacts on all bidding projects
  • Organize your pipeline with a digital bid board
  • Automatically match opportunities to your profile
  • Saved searches deliver daily project leads to your email inbox

Market Pricing Around

  • All Starter Product functionality
  • Access to all documents (plans, specifications, and addenda)
  • Access to planning projects
  • Access to contact information
  • Ability to Export

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

Sign-up for Instant Access.

Get Started Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

April 16, 2024

June 17, 2024

October 1, 2024

img_map_placeholder

601 Canal Blvd, Richmond, CA


Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.