BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Site work for a water / sewer project in Stoughton, Massachusetts. Completed plans call for site work for a water / sewer project.

Sewer System Infiltration Rehabilitation. The approximate scope of work includes furnishment and installation of: 26,000 linear feet (lf) of structural CIPP, 6 lateral liners, open cut repairs in 11 locations, replacement of 3 wye connections, one manhole (MH), 575 vertical feet of MH cementitious lining, 25 MH inflow dishes, 30 MH benches and inverts, structural repairs in 16 MHs, 82 MH frames and covers, raise 11 MH frames & covers to grade, reset 1 MH frame and cover, 4,000lf of cleaning, inspecting, testing and sealing of sewers, 12lf of structural short liners, testing/grouting of service connections, cutting intruding service connections, cleaning and TV inspection of 10,000lf of sewers. Estimated Cost $1,750,000 6,715 linear feet of cured-in-place structural pipe; install two cured-in-place lateral liners; open cut point repairs at four locations; replacement of three wye connections; installation of one sewer manhole; 575 vertical feet of cementitious lining of sewer manholes; furnish and install 23 manhole inflow dishes; build bench and invert in 27 sewer manholes; manhole structural repairs in 16 manholes; raise 11 manhole frames and covers to grade; reset one manhole frame and cover; replace 29 manhole frames and covers. The required Base Bid contract completion period is 100 consecutive calendar days. The Contractor shall complete re-test inspection within 21 consecutive calendar days of commencement of re-test inspection. The approximate scope of work for Alternate Bid No. 1 includes the following rehabilitation work and approximate quantities: 5,855 linear feet of cured-in-place structural pipe; install four cured-in-place lateral liners; open cut point repairs at four locations; replace three wye connections; cut one intruding service connection. The contract duration of the Base Bid plus Alternate Bid No. 1 is 140 consecutive calendar days. The contractor shall complete re-test inspection within 21 consecutive calendar days of commencement or re-test inspection. The approximate scope of work for Alternate Bid No. 2 includes the following rehabilitation work and approximate quantities: 3,895 linear feet of cleaning, inspecting, testing and sealing of sewers; 13,695 linear feet of curedin-place structural pipe; open cut point repairs at three locations; replace one wye connection; installation of 12 linear feet of structural short liners at three locations; testing and grouting of 21 service connections. The contract duration of the Base Bid plus Alternate Bid No. 2 is 150 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The approximate scope of work for Alternate Bid No. 3 includes the following rehabilitation work and approximate quantities: 3,700 linear feet of light cleaning and television inspection of sewers; 5,500 linear feet of heavy cleaning and television inspection of sewers. The contract duration of the Base Bid plus Alternate Bid No. 3 is 100 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The approximate scope of work for Alternate Bid No. 4 includes the following rehabilitation work and approximate quantities: Replace 53 manhole frames and covers. The contract duration of the Base Bid plus Alternate Bid No. 4 is 125 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 1 and Alternate Bid No. 2 duration is 190 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 1 and Alternate Bid No. 3 duration is 140 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 1 and Alternate Bid No. 4 duration is 165 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 2 and Alternate Bid No. 3 duration is 150 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 2 and Alternate Bid No. 4 duration is 175 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection. The Base Bid plus Alternate Bid No. 3 and Alternate Bid No. 4 duration is 125 consecutive calendar days. The Contractor shall complete re-test inspection and final paving within 21 consecutive calendar days of commencement of re-test inspection Question Deadline 04/22/2024 Every request for such interpretation should be in writing (typed, not handwritten) addressed to Weston & Sampson Engineers, Inc., 55 Walkers Brook Drive, Reading, Massachusetts 01867 Attention: CSD, or sent via email to Mahoney.Carolyn@wseinc.com and to be given consideration must be received at least ten working days prior to the date fixed for the opening of bids.

Bid Results

Water / Sewer

$761,000.00

Public - City

Site Work

23

8

4

4

Subscribe For Documents

16 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
288
Active Projects
156
Bidding Soon
2,665
All Active Projects
1,126
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

May 9, 2024

July 8, 2024

img_map_placeholder

Multiple Locations, Stoughton, MA


The data you need to build the relationships you want. Try it free.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.