Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Published November 26, 2025 at 7:00 PM
Updated November 27, 2025
Site work and new construction of a laboratory facility in Harrisburg, Pennsylvania. Completed plans call for the construction of a 300,000-square-foot laboratory facility; and for site work for a laboratory facility.
As of August 28, 2025, an award is still pending. Pennsylvania Joint Laboratory Facility DGS C-1050-0001.1 Phase 1 General Construction DGS C-1050-0001.2 Phase 1 HVAC Construction The Department of General Services Capital Programs and the Bureau of Diversity, Inclusion and Small Business Opportunities (BDISBO) identified this procurement as eligible for the setting of Small Diverse Business (SDB) and/or Veteran Business Enterprise (VBE) participation goals. However, BDISBO did not set SDB and/or VBE participation goals for those procurements that are less than the $600,000 threshold required to set either goal. In addition, there will be no points allocated toward SDB/SB participation for this procurement. This is a significant programmatic change from the SDB and SB Participation program contained in prior Projects issued by Capital Programs. Bidders now must agree to meet the SDB and VBE Participation Goals in full or demonstrate that they have made Good Faith Efforts to meet the Goals. Refer to the Instructions to Bidders section regarding Small Diverse Business and Veteran Business Enterprise Participation for further information. ESTIMATED RANGE:.1A Site Work - $19,000,000 - $20,000,000 .1B Interiors - $3,000,000 - $4,000,000 .2A Sheet Metal - $18,000,000 - $19,000,000 .3 Plumbing - $24,000,000 - $25,000,000 .4 Electrical - $45,000,000 - $46,000,000 .4A Site Electrical - $9,000,000 - $10,000,000 .5 Fire Protection - $3,000,000 - $4,000,000 LIQUIDATED DAMAGES = (.1A) $6,000.00 per day, (.1B) $2,000.00 per day, (.2A) $6,000.00 per day & (.3) $7,000.00 per day. (.4) $12,000.00 per day, (.4A) $4,000.00 per day, (.5) $2,000.00 per day, This PROJECT IS A STANDARD LOW BID PROJECT and includes GENERAL, HVAC, PLUMBING AND ELECTRICAL CONSTRUCTION. Duration: 1084 Calendar Days from date of Initial Job Conference ESTIMATED RANGE:.1A Site Work - $19,000,000 - $20,000,000 .1B Interiors - $3,000,000 - $4,000,000 .2A Sheet Metal - $18,000,000 - $19,000,000 .3 Plumbing - $24,000,000 - $25,000,000 .4 Electrical - $45,000,000 - $46,000,000 .4A Site Electrical - $9,000,000 - $10,000,000 .5 Fire Protection - $3,000,000 - $4,000,000 LIQUIDATED DAMAGES = (.1A) $6,000.00 per day, (.1B) $2,000.00 per day, (.2A) $6,000.00 per day & (.3) $7,000.00 per day. (.4) $12,000.00 per day, (.4A) $4,000.00 per day, (.5) $2,000.00 per day, There is no Bid Guaranty required for this Project. The Department of General Services Capital Programs and the Bureau of Diversity, Inclusion and Small Business Opportunities (BDISBO) identified this procurement as eligible for the setting of Small Diverse Business (SDB) and/or Veteran Business Enterprise (VBE) participation goals. However, BDISBO did not set SDB and/or VBE participation goals for those procurements that are less than the $600,000 threshold required to set either goal. In addition, there will be no points allocated toward SDB/SB participation for this procurement. This is a significant programmatic change from the SDB and SB Participation program contained in prior Projects issued by Capital Programs. Bidders now must agree to meet the SDB and VBE Participation Goals in full or demonstrate that they have made Good Faith Efforts to meet the Goals. Refer to the Instructions to Bidders section regarding Small Diverse Business and Veteran Business Enterprise Participation for further information. The Goals for each Prime Contract is as follows: SDB AND VBE GOALS .1A Site Work - ALL BASE BIDS (#1) SDB = 16% VBE = 3% .1B Interiors - ALL BASE BIDS (#1) SDB = 18% VBE = 3% .2A Sheet Metal - ALL BASE BIDS (#1) SDB = 10% VBE = 3% .3 Plumbing Construction - ALL BASE BIDS (#1) SDB = 15% VBE = 3% .4 Electrical Construction ALL BASE BIDS (1) SDB = 18% VBE = 3% .4A Site Electrical - ALL BASE BIDS (#1) SDB = 16% VBE = 3% .5 Fire Protection - ALL BASE BIDS (#1) SDB = 16% VBE = 3% All Proposers are required to create a user profile within e-Builder. Please click on discipline below to create a user profile and view the bid package: Site Work Construction Interiors Construction Sheet Metal Construction Plumbing Construction Electrical Construction Site Electrical Construction Fire Protection Construction There is no Bid Guaranty required for this Project. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. The scope of work encompassed under this RFP consists of the prime contract(s) (i.e., General and Mechanical/HVAC) for the construction work identified on the cover sheet of this RFP and in the Notice to Proposers. The complete scope of work for this Project is further described by the Plans and Specifications (provided as Appendices to this RFP), which shall take precedence over this general description. For purposes of this solicitation, the Contract Work shall encompass all work set forth in Article I (The Contract Documents) and Article II (The Work) of the Standard Construction Contract included as an Appendix to this RFP. Deadline to Submit Questions April 30, 2025 Bid Result DGS C-1050-0001 P1.1A - Vollers Excavating & Construction, Inc. - 21,775,155 DGS C-1050-0001 P1.1B - Wohlsen Construction - 11,335,354 DGS C-1050-0001 P1.2A - Matchline Mechanical - 27,969,000 DGS C-1050-0001 P1.3 - Ainsworth - 22,948,000 DGS C-1050-0001 P1.4 - JOYCE ELECTRICAL INC. - 49,363,000 DGS C-1050-0001 P1.4A - Manada Electric - 4,629,955 DGS C-1050-0001 P1.5 - Triangle Fire Protection, Inc. - 2,889,790
Bid Results
Laboratories
$140,910,254.00
Public - State/Provincial
New Construction, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
June 3, 2025
January 12, 2026
20 Azalea Dr, Harrisburg, PA
Related To This Project
Harrisburg, PA
Bid Date: Apr 17 2025
Harrisburg, PA
Bid Date: Aug 08 2025
Harrisburg, PA
Bid Date: Aug 08 2025
Harrisburg, PA
--
Harrisburg, PA
Bid Date: Apr 22 2025
Harrisburg, PA
Bid Date: Apr 30 2025
Harrisburg, PA
Bid Date: Apr 23 2025
Harrisburg, PA
Bid Date: Jul 10 2025
Harrisburg, PA
Bid Date: Apr 22 2025
Harrisburg, PA
Bid Date: Apr 15 2025
Harrisburg, PA
Bid Date: Apr 17 2025
Harrisburg, PA
Bid Date: May 01 2025
Harrisburg, PA
Bid Date: Apr 03 2025
Harrisburg, PA
Bid Date: May 13 2025
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.