Site work and paving for a mixed-use development in Red Oak, Iowa. Completed plans call for site work for a sidewalk / parking lot; for paving for a sidewalk / parking lot; and water / sewer project.

The project consists of replacement of an existing 6" water main with approximately 675 LF 6" PVC trenchless water main, new services up to the curb stop, removal and replacement curb and gutter, driveway, and sidewalk, and miscellaneous associated work. Project is located on Oakwood Avenue between 2nd Street and 4th Street, Red Oak, IA 51566. Each bidder shall accompany its bid with bid security as defined in Iowa Code Section 26.8, and in the amount of 10% of the total amount of the bid as security that the successful bidder will enter into a contract for the work bid upon and will furnish after the award of contract a corporate surety bond, in a form acceptable to the Jurisdiction, for the faithful performance of the contract, in an amount equal to 100% of the amount of the contract. The bidder's security shall be in the amount fixed in the Instruction to Bidders and shall be in the form of a cashier's check or a certified check drawn on an FDIC insured bank in Iowa or on an FDIC insured bank chartered under the laws of the United States; or a certified share draft drawn on a credit union in Iowa or chartered under the laws of the United States; or a bid bond on the form provided in the contract documents with corporate surety satisfactory to the Jurisdiction. The bid shall contain no condition except as provided in the specifications. Each successful bidder will be required to furnish a corporate surety bond in an amount equal to 100% of its contract price. Said bond shall be issued by a responsible surety approved by City of Red Oak, IA and shall guarantee the faithful performance of the contract and the terms and conditions therein contained and shall guarantee the prompt payment of all material and labor, and protect and save harmless City of Red Oak, IA from claims and damages of any kind caused by the operations of the contract and shall also guarantee the maintenance of the improvement caused by failures in materials and construction for a period of two years from and after acceptance of the contract. The guaranteed maintenance period for new paving shall be four years. Contractor shall fully complete the project in 25 working days. Should the contractor fail to complete the work in this timeframe, liquidated damages of $1,000.00 per working day will be assessed for work not completed within the designated contract term. The late start date shall be April 1, 2026. Pre-Bid Meeting Info: A pre-bid meeting is not scheduled for this project. The City of Red Oak, IA does hereby reserve the right to reject any or all bids, to waive informalities, and to enter into such contract, or contracts, as it shall deem to be in the best interest of the jurisdiction

Award

Water / Sewer

$140,793.00

Public - City

Paving, Site Work

5

6

5

Subscribe For Documents

27 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
140
Active Projects
102
Bidding Soon
1,004
All Active Projects
0
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

July 31, 2025

April 1, 2026

Project location map

Oakwood Ave, Red Oak, IA

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.