Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Published April 8, 2026 at 8:00 PM
Updated May 20, 2026
Renovation of an educational facility in Rancho Cucamonga, California. Working plans call for the renovation of a 68,082-square-foot educational facility.
As of April 8, 2026, a LLB Contractor has been selected. A timeline for construction has yet to be announced. However, the project is estimated to take between 32-36 months to complete. *The closed solicitation has been included below for reference: Request for Qualifications and Proposals for Lease-leaseback Pre-construction and Construction Services Cucamonga School District ("District") is seeking proposals from pre-qualified firms for Lease-Leaseback Construction Services ( LLB ) including, but not limited to, pre-construction services including design review, constructability review, and value engineering, as well as construction services for the District s proposed Los Amigos Elementary School Renovation Project and Cucamonga Elementary School Renovation Project (each a Project ). Proposals shall be valid for at least ninety (90) calendar days after the due date. No proposer may withdraw its proposal for a period ninety (90) calendar days after the due date. Proposers and any mechanical, electrical, and plumbing subcontractors must be Prequalified. The District uses PQ Bids electronic Prequalification system. The link to PQ Bids electronic Prequalification system is at the link given in the RFP document. The proposer must submit its contact information and register with the District by September 5, 2025. The last day to submit Prequalification information is September 9, 2025. All questions must be submitted by September 10, 2025. The successful proposer for each Project will be required to furnish the District with a Performance Bond and a Payment Bond each equal to 100% of the Guaranteed Maximum Price, prior to the start of construction services. All bonds are to be secured from a surety that meets all of the State of California bonding requirements, as defined in Code of Civil Procedure Section 995.120, and is admitted by the State of California. Each proposer shall be a licensed contractor pursuant to the Business and Professions Code and shall be licensed in the following appropriate classification(s) of contractor s license(s), for the work bid upon, and must maintain the license(s) throughout the duration of the Contract: Class B General Building Contractor. Award of Contracts: The District shall award the Contract for each Project separately, to the proposer submitting the best value proposal for that Project as determined by the District pursuant to the evaluation criteria in the RFP. The District reserves the right to reject any or all proposals and to waive any irregularities or informalities in any proposals or in the proposal process. The address for submission of Proposals is as follows: Cucamonga School District Attn: Michael Chaix, Superintendent RE: Los Amigos/Cucamonga Elementary School Renovation RFQ/RFP 8776 Archibald Avenue Rancho Cucamonga, CA 91730 A contractor may send or deliver its Proposal to the District via: (i) certified, registered, or first-class U.S. Mail; (ii) FedEx, UPS, or other private delivery service; (iii) personal delivery; or (iv) other means as the contractor determines appropriate. However, notwithstanding the foregoing, in no event will the District accept any Proposal sent via facsimile transmission, email, or other electronic means. ProjectLocation 8498 Ninth St. Rancho Cucamonga, CA 91730 8677 Archibald Ave. Rancho Cucamonga, CA 91730 ProjectDescription THE LOS AMIGOS RENOVATION PROJECT INVOLVES THE MODERNIZATION AND EXPANSION OF THE ENTIRE LOS AMIGOS ELEMENTARY SCHOOL CAMPUS , ENCOMPASSING THE FOLLOWING KEY ELEMENTS: BUILDING IMPROVEMENTS: 1, COMPLETE MODERNIZATION OF BUILDING NO. 1. 28,432 SQ, FT, ADMINISTRATION BUILDING: RENOVATION OF ALL INTERIOR FEATURES TO ALIGN WITH UPDATED STANDARDS AND FUNCTIONAL NEEDS. 2. MINOR ALTERATIONS TO THE EXISTING CLASSROOM BUILDING NO.5, INCLUDING EXTERIOR PAINT, NEW INTERIOR PAINT, NEW CARPET, AND UPGRADED FIRE ALARM. THE REMAINDER OF THE BUILDING WILL REMAIN UNCHANGED. 3, COMPLETE DEMOLITION OF THE EXISTING MPR BUILDING, REMOVAL OF THE EXISTING MULTI-PURPOSE ROOM (MPR) STRUCTURE TO MAKE WAY FOR NEW FACILITIES. 4. RELOCATION OF EXISTING RELOCATABLE CLASSROOMS, REPOSITIONING OF EXISTING PORTABLE CLASSROOMS TO ANOTHER SITE, 5, CONSTRUCTION OF A NEW 15,452 SQ.FT. KINDERGARTEN BUILDING NO.3 THAT INCLUDES A 1,472 SQ. FT. SHADE STRUCTURE: DEVELOPMENT OF A KINDERGARTEN FACILITY. 6. NEW 14,250 SQ. FT. MULTI-PURPOSE ROOM (MPR) /FOODSERVICE BUILDING NO.2: INCLUDES A 4,100 SQ. FT. LUNCH SHELTER AND A 2,105 SQ. FT. SERVICE YARD EQUIPPED WITH A TRASH ENCLOSURE, CAN WASH, AND TRANSFORMER YARD FOR UTILITIES. 7. NEW 1,619 SQ. FT. PHYSICAL EDUCATION (PE) BUILDING NO.4, DEDICATED SPACE TO SUPPORT THE PHYSICAL EDUCATION PROGRAM, 8. NEW 652 SQ. FT. ELRT BUILDING NO.6, ENHANCED FACILITIES FOR ENGLISH LANGUAGE READING , AND TRAINING ( ELRT), SITE ENHANCEMENTS: 1, NEW PROTECTED TRANSITIONAL KINDERGARTEN (TK) PLAY ZONE, SAFE AND ENCLOSED PLAY AREA DESIGNED SPECIFICALLY FOR TRANSITIONAL KINDERGARTEN STUDENTS. 2. OUTDOOR ACTIVITY AREAS, UPGRADED OUTDOOR SPACES TO SUPPORT RECREATIONAL AND EDUCATIONAL ACTIVITIES, 3, ENHANCED OUTDOOR COURTYARD, CENTRALIZED, MULTloFUNCTIONAL COURTYARD DESIGNED FOR SOCIAL INTERACTION ANO LEARNING. 4. NEW DROP-OFF AREA, IMPROVED VEHICULAR FLOW WITH,'. DEDICATED DROP-OFF AREA FOR ENHANCED SAFETY AND ACCESSIBILITY. 5, NEW ELECTRIC VEHICLE (EV) CHARGING STATIONS, SUSTAINABLE ADDITIONS TO SUPPORT ENVIRONMENTALLY FRIENDLY TRANSPORTATION, 6. NEW LANDSCAPE AREAS, UPDATED LANDSCAPING TO IMPROVE AESTHETICS, FUNCTIONALITY, AND ENVIRONMENTAL BENEFITS ACROSS THE CAMPUS. Project Information 1. Demolition of existing Administration, Library, MPR with Kitchen, and Classroom and toilet buildings and Portables, as well as existing parking lots, playground and basketball court. 2. Construction of two (2) new buildings to include Administration, Library, MPR, Kitchen, and Classrooms. 3. Construction of new parking lots, basketball courts, playground , and CMU wall. 4. To remain: two (2) PV panels and the existing TK/K Building (A#04-119045). The Project will be constructed in multiple phases on an occupied campus.
Pre-Construction/Negotiated
Educational
$61,401,527.00
Public - City
Renovation
Documents for this project are exclusively Specifications. If Plans become available, we will add them here.
9
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
September 23, 2025
September 28, 2026
Multiple Locations, Rancho Cucamonga, CA
Related To This Project
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
Bid Date: Sep 08 2025
Rancho Cucamonga, CA
Bid Date: Sep 29 2025
Rancho Cucamonga, CA
Bid Date: Oct 06 2025
Rancho Cucamonga, CA
Bid Date: Oct 06 2025
Rancho Cucamonga, CA
Bid Date: Oct 10 2025
Rancho Cucamonga, CA
Bid Date: Oct 13 2025
Rancho Cucamonga, CA
Bid Date: Nov 03 2025
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
Bid Date: Jul 29 2025
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
--
Rancho Cucamonga, CA
Bid Date: Jul 11 2025
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.