Site work for a water / sewer project in Manor, Texas. Completed plans call for site work for a water / sewer project.
Project No. SP-2023-0360D 4,200 feet of 36-inch wastewater interceptor from E. U.S. 290 north along Gilleland Creek to Hill Lane, 4,450 feet of 30-inch wastewater interceptor from the 36-inch wastewater interceptor west along Hill Lane to N. SH 130, and 4,720 feet of 24-inch wastewater interceptor from the 30-inch wastewater interceptor west across N. SH 130 and then north along Gilleland Creek to E. Howard Lane. The Work shall include furnishing all tools, labor, materials, equipment, and miscellaneous items necessary for the complete construction of approximately 4,200 linear feet of 36-inch wastewater interceptor, 4,100 feet of 30-inch wastewater interceptor, and 3,625 feet of 24- inch wastewater interceptor. Bidder must manage and follow two distinct Milestones, with each Milestone having its own separate set of guidelines. It is assumed that the Bidder will advance the schedule for Milestone 2 to run concurrently with Milestone 1 in order to meet the Contract Time described in Section 9 below. All Bids shall be accompanied by an acceptable Bid guaranty in an amount of not less than five percent (5%) of the total Bid, as specified in Section 00100, Instructions to Bidders. Performance and payment bonds when required shall be executed on forms furnished by OWNER. Each bond shall be issued in an amount of one hundred percent (100%) of the Contract Amount by a solvent corporate surety company authorized to do business in the State of Texas, and shall meet any other requirements established by law or by OWNER pursuant to applicable law. Minimum insurance requirements are specified in Section 00810, Supplemental General Conditions. The Contract Time for Milestone 1 is of the essence and all work shall be substantially completed within one hundred and fifty (150) Working Days after the date specified in the Notice to Proceed, in accordance with the Bid Form, Section 00300. Final Completion shall be achieved within thirty (30) Working Days after substantial completion. Liquidated damages apply for Milestone 1 up to final completion. Liquidated damages are Five Hundred ($500) per Working Day for failure to achieve final completion within thirty (30) Working Days after substantial completion of Milestone 1, in accordance with the Bid Form, Section 00300. The Contract Time for Milestone 2 is of the essence and all work shall be substantially completed within one hundred and ten (110) Working Days after the date specified in the Notice to Proceed, in accordance with the Bid Form, Section 00300. Final Completion shall be achieved within thirty (30) Working Days after substantial completion. Liquidated damages apply for Milestone 2 up to final completion. Liquidated damages are Five Hundred ($500) per Working Day for failure to achieve final completion within thirty (30) Working Days after substantial completion of Milestone 2, in accordance with the Bid Form, Section 00300. WBE 2.36%. Event pre bid meeting description : For those calling in, please send an email to Steven.Cocke@austintexas.gov with the subject line CLMC1086, indicate in the body of the email your name, the firm you are representing, your contact information and whether you are a prime firm or subcontractor. Attendance is not mandatory unless otherwise stated. Bidders must attend any mandatory Pre-Bid Conference and are encouraged to attend any non-mandatory Pre-Bid Conference to ensure their understanding of OWNER's bidding and contracting requirements, particularly MBE/WBE or DBE Procurement Program requirements. If the Pre-Bid Conference is mandatory the Bidder must arrive and sign-in within fifteen (15) minutes of the scheduled start time of the meeting, otherwise the Bidder will not be allowed to submit a Bid for the project. OWNER reserves the right to reject any or all Bids and to waive any minor informality in any Bid or solicitation procedure (a minor informality is one that does not affect the competitiveness of the Bid). Question Deadline 12/30/2025 Prospective Bidders desiring further information or interpretation of Project Manual or Drawings must make a written request for such information to OWNER addressed to the Authorized Contact Person listed in Section 00020 no later than seven (7) Working Days before Bid opening Project No. 0124-045
Bid Results
Water / Sewer
$14,399,601.00
Public - City
Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
January 22, 2026
March 23, 2026
13512 Gregg Manor Rd, Manor, TX
Related To This Project
Manor, TX
Bid Date: Dec 22 2025
Manor, TX
Bid Date: Dec 30 2025
Manor, TX
--
Manor, TX
Bid Date: Jan 28 2026
Manor, TX
--
Manor, TX
--
Manor, TX
Bid Date: Aug 31 2020
Manor, TX
--
Manor, TX
--
Manor, TX
Bid Date: Oct 15 2025
Manor, TX
Bid Date: Oct 24 2025
Manor, TX
Bid Date: Dec 16 2025
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.