Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Published June 10, 2026 at 8:00 PM
Updated June 10, 2026
Renovation of an educational facility in South Gate, California. Completed plans call for the renovation of a educational facility.
Roofing Replacement Project Location- INDEPENDENCE ELEMENTARY SCHOOL - The furnishing of all labor, materials, equipment, services, and incidentals necessary for Work of the Independence ES - Roofing, at Independence Elementary School located at 8435 Victoria Ave., South Gate, California 90280, as set forth in the Construction Documents which include, but are not limited to, the Drawings, Addenda and Specifications. Buildings: 002CAX MULTI-PURPOSE BUILDING, 45807 LUNCH PAVILION, 001CDX CLASSROOM BUILDING, X3528Y, X3529Y, X3530Y, X3531Y, X3532Y, 45806 ARCADE #1, 45913 BUILDING #2. The District's contract bond estimate is $1,389,351. The Contract Time is 230 days (25%) for Small Business Enterprises (SBE) and five percent (5%) for all Veteran Business Enterprises (VBE) A. The presence of asbestos-containing roofing materials and lead-based paint on affected components have been determined or are assumed to exist on one or more of the buildings referred to in the scope of work. See the asbestos and lead reports for locations of these materials. CONTRACTOR shall include as part of this contract asbestos and lead abatement and lead related construction work, as required. All such work shall be performed by a subcontractor included on the current list of approved abatement contractors. The CONTRACTOR shall coordinate abatement and lead related construction of all asbestos-containing materials (ACM) and building components with lead-based paint (LBP) surfaces to be impacted by the project through the environmental consultant. This shall be done prior to any roof replacement work to ensure that no ACM and/or LBP are inadvertently disturbed. All ACM and/or LBP to be impacted by the project and requiring abatement or lead related construction work shall be clearly identified and marked by the CONTRACTOR with the assistance of the Environmental Consultant. The abatement or lead related construction work shall not commence without the approval of the Environmental Consultant. All ACM and/or LBP work shall be monitored by the Environmental Consultant. B. CONTRACTOR shall not proceed with any roof replacement work until notification is received from the Environmental Consultant that all ACM and LBP to be impacted by the project have been abated or managed, as required, and the work area is clear for normal access in accordance with the specifications. Unless otherwise noted: all roof removal and/or Asbestos/Lead abatement work shall be performed during non-school hours. C. Where the OWNER calls for reuse of existing materials, the CONTRACTOR may, at their option, remove and replace with new at no additional cost to the OWNER. D. Unless otherwise noted, eyebrows, eaves, and overhangs attached to a building listed in Section 1.01A are included in the scope of work. E. Unless otherwise noted all work on arcades, cafeterias, lunch shelters, children centers, early education centers, special education classrooms, and kindergartens are to be performed during non-school hours. F. Temporary barricades utilizing temporary chain link fence panels a minimum of 6' high and set a minimum of 10' from buildings and arcades, utilizing a double fence set up on all arcades spaced out 10 feet of each other. Stands shall be set at maximum of 12' on center. All staging areas, regardless of day or time, shall be completely enclosed with temporary chain link fencing with a minimum height of eight (6) feet. Orange snow fencing is not allowed as a barrier system. G. When removal of roofing is required for roofs higher than fifteen (15) feet, a completely enclosed trash chute is required. H. All bins, dumpsters and storage units shall be set on 2' x 2' x 3/4 " plywood minimum and care shall be taken in delivery and pick up as to not create any damage to grounds. CONTRACTOR to bear all expenses of repairs to damaged grounds. I. The contractor and all employees of the contractor shall wear photo identification while on District property. The ID shall include employee's name, contractor's name, and job classification. J. Remove and replace ALL equipment platform covers with new 22-gauge galvanized sheet metal covers matching existing in size and configuration. K. Remove and replace all insulation matching existing thickness with new polyisocyanurate with a minimum value of R7 per inch. L. Install pressure release vents on all concrete substrates per manufacturers recommendations. M. Install PVC walk pads from roof hatch to and around serviceable equipment. N. Site Wide - Install dura-blocks attached to 80-mil textured PVC, install 2" round stanchion supports in place where the support curbs were removed/angle iron (must be in the same location and brace underneath if required. O. Install "Black" stenciled school address to main building per the specifications for PVC roofing. P. Contractor shall use scheduling software such as Microsoft Project to provide a baseline schedule, monthly updates, and recovery schedules for the project. Contractor shall incorporate milestones found in the Phasing of the Work specification into the project schedule. 1. Demolition & Abatement: The Contractor shall be responsible for the complete removal and abatement of all existing roofing materials down to the substrate. This includes, but is not limited to, the following components: pipe flashings, mechanical sleepers, counter flashing, mechanical-curb flashing, conduit supports, gutters, downspouts, scuppers, mechanical curb covers, pitch pockets including all filler material, and coping. a. All standing seam metal roofs are exempt and are to remain in place as is. All work at metal roof to low-slope transitions shall be installed per manufactures installation guide. b. All skylights are exempt and are to remain in place as is. All work at roof to curb/flashing transitions shall be installed per manufacturers installation guide. 2. New Roof System Installation: o The Contractor shall install a new roofing system comprising the following components: Minimum 60 mil thermoplastic roof membrane composed of polyvinyl-chloride (PVC) including new mechanical curb caps, counter flashing, duct-curb flashing, electric conduit and gas pipe supports (using durablocking), gutter, downspouts, vinyl-clad edge metal, and scuppers. Recondition all primary and condensation roof drains. Replace any missing drain assembly components. 3. Installation Standards & Compliance: All installation work and materials used shall follow the approved details, the Los Angeles Unified School District (LAUSD) Specifications 07 5413 Mechanically Attached and 07 5419 Fully Adhered PolyvinylChloride Roofing for the applicable substrate, all related LAUSD specification sections, and the manufacturer's installation guide. 4. Ponding Mitigation: The Contractor is solely responsible for mitigating ponding areas on the roofing system. Contractor shall install crickets at all areas showing visible signs of ponding water. The Contractor is responsible for ensuring that ponding mitigation measures effectively eliminate standing water on the roof surface. 5. HVAC & Platform Securement: The Contractor shall secure all HVAC units and platform covers per LAUSD detail drawing in appendix or contractor provided approved detail. 6. Stucco & Wood Repair: The Contractor shall be responsible for the repair or replacement of any stucco and/or painted wood members that are damaged during the process of replacing the existing roofing system.
Sub-Bidding
Educational
$1,389,351.00
Public - County
Renovation
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
July 15, 2026
September 14, 2026
8435 Victoria Ave, South Gate, CA
Related To This Project
South Gate, CA
--
South Gate, CA
--
South Gate, CA
Bid Date: Nov 21 2019
South Gate, CA
Bid Date: Jun 09 2026
South Gate, CA
Bid Date: May 21 2026
South Gate, CA
--
South Gate, CA
Bid Date: Jun 16 2026
South Gate, CA
Bid Date: May 22 2026
South Gate, CA
Bid Date: May 26 2026
South Gate, CA
Bid Date: Mar 26 2026
South Gate, CA
Bid Date: Apr 16 2026
South Gate, CA
Bid Date: Apr 16 2026
South Gate, CA
Bid Date: Apr 20 2026
South Gate, CA
Bid Date: Apr 16 2026
South Gate, CA
Bid Date: Mar 25 2026
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.
