BLOCK PAGE!!!

Get Full Details

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Published July 31, 2026 at 8:00 PM

Updated August 2, 2026

Site work for a transportation facility in Southbank, British Columbia. Completed plans call for site work for a transportation facility.

The Track Package includes Scope A which is the Main Line Track from Ramsay Inglewood Station in the north to the end of the project limits, as well as Scope B the Maintenance Storage Facility (MSF) track. Scope C includes both scopes. For scope delineation, this RFP is divided as follows: Scope A: Main Line Track Scope B: Maintenance & Storage Facility (“MSF”) Track Scope C: Combined Track Package (Scopes A and B) in its entirety. Scope A Main Line Track Ballasted Track: from the Top of Rail (TOR) to the top of the sub-ballast. Test track works Special trackwork (e.g., turnouts, crossovers) Track-related ROW equipment, crossings, and appurtenances Ducting, cable containment, and associated infrastructure Boundary limit south of the MSF turnaround (see Scope B figure below) Design and implementation of all Temporary Works. Field review, monitoring, and reporting for Temporary Works. Support of excavation. Laydown areas and traffic management. Construction noise and vibration mitigation. Environmental mitigation protection measures. Provide all: Labour, supervision, and management Materials, plant and equipment Survey, quality control, and environmental control Documentation and testing support Interface coordination Scope B MSF Track MSF trackwork supply and installation including: Direct Fixation (DF) Track: from the Top of Rail (TOR) to the bottom of the plinths (second-pour concrete). Ballasted Track: from the Top of Rail (TOR) to the top of the sub-ballast. MSF trackwork (yard and shop) supply and installation Test track works Special trackwork (e.g., turnouts, crossovers) Track-related ROW equipment, crossings, and appurtenances Ducting, cable containment, and associated infrastructure Boundary limit north of the MSF turnaround (see Scope B figure above) Design and implementation of all Temporary Works. Field review, monitoring, and reporting for Temporary Works. Support of excavation. Laydown areas and traffic management. Construction noise and vibration mitigation. Environmental mitigation protection measures. Provide all: Labour, supervision, and management Materials, plant and equipment Survey, quality control, and environmental control Documentation and testing support Interface coordination Scope C Combined Track Package (Scopes A and B) Main Line trackwork supply and installation including: Direct Fixation (DF) Track: from the Top of Rail (TOR) to the bottom of the plinths (second-pour concrete). Ballasted Track: from the Top of Rail (TOR) to the top of the sub-ballast. MSF trackwork supply and installation including: Direct Fixation (DF) Track: from the Top of Rail (TOR) to the bottom of the plinths (second-pour concrete). Ballasted Track: from the Top of Rail (TOR) to the top of the sub-ballast. MSF trackwork (yard and shop) supply and installation Test track works Special trackwork (e.g., turnouts, crossovers) Track-related ROW equipment, crossings, and appurtenances Ducting, cable containment, and associated infrastructure Design and implementation of all Temporary Works. Field review, monitoring, and reporting for Temporary Works. Support of excavation. Laydown areas and traffic management. Construction noise and vibration mitigation. Environmental mitigation protection measures. Provide all: Labour, supervision, and management Materials, plant and equipment Survey, quality control, and environmental control Documentation and testing support Interface coordination The following provisions and items are applicable to all respective trackwork scopes, comprising but not limited to the following: General Provisions Deliver a complete, coordinated, safe, maintainable, and commissionable LRT track system for the respective trackwork scope. The scope split matrix provided in Schedule 9 Construction Contract Form, with the Proponent taking primary responsibility for trackwork. Applies across design, procurement, construction, testing, commissioning, handover, and warranty. Track equipment, including the supply, fabrication, delivery, installation, adjustment, inspection, and acceptance of: Running rail Jordan rail Ties Ballast Direct fixation assemblies Embedded track components All required fittings and fixations Guard rails Restraining rails Insulated joints Expansion joints Rail anchors Rail lubricators End-of-track protection devices Special trackwork Switch clearance devices Switch heater equipment Level crossings Track drainage interfaces Cable containment Track troughs Concrete plinths (second pour) System assurance for the scope of trackwork, including all applicable inspection, testing, and commissioning activities required for the respective trackwork scopes, including: Factory Acceptance Testing (FAT) Factory Integration Testing (FIT) Pre-Installation Check-Out (PICO) Site Acceptance Testing (SAT) Integrated interface testing Trial running support Closeout evidence Acceptance testing Any other activities applicable to the specific scope of work. Interfaces with other Construction packages Stations, bridges, MSF building Public roads and pedestrian crossings Utility zones and embedded track areas Transition slabs and systems equipment locations Temporary tie-ins for staged construction Communications & Traction Power Systems (wayside) Signaling & Train Control Systems Documents can be obtained from https://tinyurl.com/5bn76dyw

GC Bidding

$200,000,000.00

Public - City

We’ve obtained documents for this project and are currently processing them.

Subscribe For Documents

No Data

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
14
Active Projects
4
Bidding Soon
28
All Active Projects
0
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

October 29, 2026

December 1, 2026

Project location map

Multiple Locations, Southbank, BC

Related To This Project


Recently Viewed

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.