Demolition, site work, paving and new construction of a bridge / tunnel in Highland Park, Illinois. Completed plans call for site work for a bridge / tunnel; for paving for a bridge / tunnel; for the demolition of a bridge / tunnel; and for the construction of a bridge / tunnel.

Replace the bridge carrying Park Avenue West over a Ditch of the Skokie River in Highland Park. Region 1 District 1 Federal Project # 05QI(933) County(s) Lake Key Route(s) FAU 1255 Marked Route(s) PARK AVENUE WEST Section(s) 13-00122-00-BR (HIGHLAND PARK) State Job #(s) C-91-375-14 PPS #(s) 1-21532-0000 Completion Date: July 19, 2024 Plus 15 Working Days Questions not accepted as of November 08, 2022 04:30 PM. Questions directed to: IDOT Contracts Office Harry R. Hanley Building Room 326 2300 South Dirksen Parkway Springfield, IL 62764 (217) 782-7806 Fax: (217) 785-1141 TDD: (217) 524-4875 DOT.DE-Contracts@illinois.gov Unless otherwise indicated, a proposal guaranty is required by bid bonds, cashier's check or properly certified check for not less than 5 (five) percent of the bid amount. If the proposal is accepted and the bidder is declared "not responsive," it is hereby agreed that the amount of the proposal guaranty will become the property of the State of Illinois and shall be considered as payment of damages due to the delay and other causes suffered by the State because of the failure to adhere to the procedures required. Otherwise, the bid bond will become void or the proposal guaranty check will be returned to the bidder. Contractors who desire to become prequalified or to renew their prequalification for this letting must file with the Department of Transportation, Bureau of Construction, Room 322, 2300 South Dirksen Parkway, Springfield, Illinois 62764, a Contractor's Statement of Experience and Financial Condition no later than 4:30 PM prevailing local time, October 28, 2022. A contractor will not be prequalified for this letting unless the statement is received before the time and day established. The Department reserves the right to reject any and all bids, to waive minor or immaterial irregularities, informalities or technicalities, to advertise for new bids, or to request confirmation or clarification from any bidder regarding a bid. ILDOT - 083 - Replace the Bridge Carrying Park Avenue West The Work consists of furnishing all labor, materials, equipment, and other incidentals necessary for the complete removal of the existing reinforced concrete deck structure on single span steel beams, constructing a new single span steel beam structure on semi-integral abutments, earth excavation, rock excavation, channel excavation, furnished excavation, porous granular embankment, trench backfill, topsoil furnish and place, sodding, stone riprap, aggregate subgrade improvement, HMA and PCC surface removals, HMA binder and surface courses, PCC driveway placement, pavement removals, combination curb and gutter removal and replacement, sidewalk removal and replacement, curb ramp removal and replacement, concrete barrier removal, pavement patching, removal of existing structures, protective shield, structure excavation, cofferdams, concrete structures, concrete superstructure, bridge deck grooving, form liner textured surface, concretes superstructure (approach slab), furnishing and erecting structural steel, reinforcement bars, bicycle railing, parapet railing, furnishing and driving piles, temporary soil retention system, pipe underdrains, steel plate beam guardrail and terminals, non-special waste disposal, mobilization, pavement markings, temporary concrete barrier, sign panels, underground conduits, handholes, full-actuated controller and cabinet, electric cable, traffic signal posts, mast arm assemblies and poles, traffic and pedestrian signal heads, temporary traffic signal installation, remove existing traffic signal equipment, relocate existing electrical system, erosion control, temporary access, detectable warnings, staining concrete structures, water main removal and reconstruction, sanitary sewer removal and reconstruction, manholes, adjustments to drainage structures, traffic control and protection, paint traffic signal equipment, accessible pedestrian signals, video detection, backflow preventers, warm mix asphalt surface course, construction layout, temporary information signing, re-optimize traffic signal system, temporary traffic signal timing, pressure connection, water mainline stop, as-built drawings as well as all other incidental and miscellaneous items of work in accordance with the Plans, Standard Specifications, and these Special Provisions.

Bid Results

Bridges / Tunnels

$5,067,778.00

Public - State/Provincial

Demolition, New Construction, Paving, Site Work

147

5

7

4

Subscribe For Documents

16 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
186
Active Projects
100
Bidding Soon
1,965
All Active Projects
849
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

November 18, 2022

April 1, 2023

img_map_placeholder

Park Ave W, Highland Park, IL

Related To This Project


The data you need to build the relationships you want. Try it free.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.