BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Make some green this Black Friday.

Subscribe for the Commercial Construction data you need to get and stay ahead of the competition.

Site work and renovation of a water / sewer project in Punta Gorda, Florida. Completed plans call for the renovation of a water / sewer project; and for site work for a water / sewer project.

Wharton-Smith is the Construction Manager at Risk who is soliciting proposals and assuring that MBE and WBE firms are used, when possible, for the City of Punta Gorda Wastewater Treatment Plant Improvements 2022. Project Location: 30999 Bermont Road, Punta Gorda, FL 33982. 1. Site clearing and earthwork activities including but not limited to dewatering, erosion and sedimentation controls, excavations, trenching, backfilling, soils and aggregate, milling/repaving, asphalt surfaces, sidewalks, etc. 2. Demolition and removal of existing screens in the Headworks influent channel and replacement with new mechanical step screens including all supporting structural, electrical and instrumentation work. 3. Installation of new yard piping and force mains. Work includes exterior painting and interior coating and installation of various fittings, valves, etc. 4. Relocation of existing yard piping and force mains including all appurtenant fittings, Valves and miscellaneous work. 5. Installation of new process drain pump station wet well with new submersible pumps and discharge piping, as well as, all associated civil, structural, process mechanical, electrical and instrumentation work. 6. Construction of a new stormwater ponds and associated appurtenant work including but not limited to grading and drainage, conveyance, littoral shelf, pipe culverts, manholes and structures, etc. and all required modifications of the existing stormwater system including but not limited to the existing pond and conveyance system. 7. Geotechnical improvements and foundations for structures, etc. including but not limited to installation and testing of piles and geotechnical instrumentation and monitoring. 8. Installation of new bio-reactor tanks including flow splitter box, anoxic and aerobic tankage, pipes/fittings/valves/gates, etc. 9. Installation of new mechanical equipment in the new bio-reactor tanks including but not limited to, submersible axial flow pumps, davit cranes, submersible mixers, flexible membrane disc diffusers, rotary screw blowers, etc. along with handrails/guard rails, grating, ladder access, stairs, etc., as well as all associated structural, electrical and instrumentation requirements. 10. Installation of new wire and strand wrapped prestressed concrete clarifiers. 11. Installation of all associated circular secondary clarifier equipment/mechanism, including drive unit, rake arms, skimmer, baffles, weirs, support column, influent ring, etc. as well as launder covers, periphery walkway, piping/fittings/valves, etc. 12. Clarifiers include influent and effluent piping, RAS/WAS piping, scum piping and drain piping. 13. Installation of end suction pumps including all associated piping/valving, etc. including pump pad, electrical and instrumentation controls, for the RAS/WAS pump station. 14. Installation of double disk pumps including all associated piping/valving, etc. including pump pad, electrical and instrumentation controls, for the scum pump station. 15. Installation of new elevated walkway along with all necessary support structure, handrails, etc. to connect new bioreactors to existing secondary clarifiers as well as new secondary clarifiers (and between the new secondary clarifiers) with stair access. 16. Replacement of existing filter feed pumps in the existing filter feed pump station with new submersible pumps with discharge piping, valves, fittings, header, etc. 17. Replacement of any necessary floats, level sensors, etc, and related electrical, instrumentation work for manual operation of existing valve for filter feed pump station bypass operation. 18. Installation of rotary screw blowers, coarse bubble diffusers, telescoping valves to replace existing equipment in the digesters. The existing equipment must be removed/demolished. 19. Sequenced removal and replacement of existing effluent pumps with new axially split case pumps and all associated piping, fitting, valving, instrumentation control, electrical, etc. 20. Water utility pipes, fire hydrants, disinfection of water pipes, etc. 21. Flow switches, magnetic flow meters, thermal flow meters, ultrasonic level meters, radar level meters, analyzers, transmitters and miscellaneous instruments, etc. 22. Miscellaneous grading, sub-surface preparation, aggregate base courses, asphalt paving pavement marking, turf and grass, etc. 23. New electrical service and electrical building and all associated electrical equipment including but not limited to MCCs, switchgears, VFDs switchboards, panelboards,control panels, transformers, conduit, cables/wires, ductbanks, raceways, grounding, lightning protection, surge protection, lighting/lighting poles, interior and exterior LED lighting, emergency and exit lighting, etc. 24. The new electrical building also includes various civil, process mechanical, architectural, structural, HVAC and instrumentation related requirements. 25. A new electrical power house with similar requirements as the new electrical building. 26. A new standby power generator with a sound attenuated weather protective enclosure and sub-base diesel fuel tank to provide back up power along with associated structural, electrical and mechanical requirements. 27. Relocation of the existing Florida Power & Light (FPL) overhead power lines in the vicinity of the new Secondary Clarifiers, along with extension of the 3-phase service and single-phase service as required. 28. Structural work includes design of the concrete bioreactor on steel piles, the elevated site walkway structure, the electrical building, and the concrete foundations for the Aeration Blower Canopy, RAS/WAS pump station canopy, Existing Secondary Digester Blower canopy, power house and generator. Structural modifications to the slab for the new blowers in the existing Operations Building are also included, in addition to other miscellaneous items. 29. New PLCs in electrical building, electrical power house, and at the headworks. Replacement and migration of existing PLCs to new PLCs. Integration to vendor control panels. Communication and integration to existing SCADA, programming, fire alarm, racks, panels, enclosures, instrumentation, analyzers, etc. 30. Work includes but is not limited to temporary utilities, structures, facilities etc., concrete work - forming, reinforcing, joints, casting, finishing, curing, grouting - precast hollow core, masonry, metal fabrications, rough carpentry, dampproofing, membrane roofing, sealing, doors and frames, overhead doors, floor door, hardware, glazing, high performance concrete lining, coatings, rain gauge, etc. 31. HVAC work includes equipment, motor, duct, insulation, piping vibration control, registers, grilles, split system air conditioners, drywell, standalone controls, high temperature alarms, etc. 32. Leak tests, hydrostatic tests, pressure testing, equipment operational readiness test, functional demonstration test, manufacturers' checks/certifications, start-up, commissioning, training, operational and maintenance guidance, etc. are also included. 33. Upon completion final cleaning is included. In addition, removal of any excess spoil material, proper disposal of all items/equipment, etc. earmarked for demolition and removal is included. Final grading, turf, sod, pavement repair, cleanup and miscellaneous activities related to closeout are included. 34. This summary of work is not a comprehensive description of the requirements of the project and the project includes other Work indicated in the Contract Documents. MBE 9% WBE 3% Question Cuttoff Date & Time 12/23/2022 01:00:00 PM (ET) Sitework Honc $ 1,822,000.00 Concrete East Coast Concrete $ 6,851,891.00 Mechanical Wharton-Smith $ 15,998,100.00 Electrical Windemuller $ 6,961,368.00 Instrumentation Rocha Controls $ 1,274,828.00 Painting Cypress Coatings $ 355,449.00 HVAC Page Mechanical $ 170,620.00 Doors & Hardware Suncoast Commercial Door & Hardware $ 22,079.00 Metal Building Systems Brevard Constructors, Inc $ 394,178.00 Prestressed Concrete Tank Pre Con $ 7,014,000.00 merg. Generator/Fuel Tank Cummins $ 779,993.00 Stainless Steel Slide Gates Hydro-Gate $ 357,186.00 Rotary Screw Blowers Atlas-Copco $ 563,141.23 Axially Split Case Pumps Hydra Service, Inc. $ 499,885.00 Double Disc Pumps Enviro Sales of Florida 104760.48 Submersible Solids Handling Pumps Xylem - Flygt $ 484,213.84 Submersible Axial Flow Pumps Xylem - Flygt $ 857,017.93 Step Screens TSC Jacobs (Vulcan) $ 354,549.20 Variable-Speed Submersible Mixers Xylem - Flygt $ 1,097,977.39 Secondary Clarifier Equipment MFG Construction & Water $ 337,180.10 Coarse Bubble Diffusers Environmental Dynamics (CVI) $ 155,400.00 Flexible Membrane Disc Diffuser Xylem Sanitaire – Silver Series II. $ 157,641.00

Bid Results

Water / Sewer

$46,613,458.00

Public - City

Renovation, Site Work

Subscribe For Documents

34 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
86
Active Projects
51
Bidding Soon
767
All Active Projects
279
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

January 18, 2023

February 16, 2023

img_map_placeholder

30999 Bermont Rd, Punta Gorda, FL

Related To This Project


The data you need to build the relationships you want. Try it free.

Access Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.