Site work for a water / sewer project in Burton, Michigan. Completed plans call for site work for a water / sewer project.

**As of April 20, 2022, D.V.M. Utilities, Inc. has been awarded the contract in the amount of $2,223,950.50. For SRF Wastewater Improvements - Segment 3 SRF Project Work under this Contract consists of the open cut replacement of approximately 733 feet of 8-inch to 12-inch sanitary sewer, the lining of approximately 29,887 feet of 8-inch to 21-inch sanitary sewer with cured-in-place pipe, and associated sanitary manhole rehabilitation. This project will be funded by a Clean Water State Revolving Fund Loan (CWSRF), all applicable rules and requirements will apply. Any questions regarding the project shall be brought to the attention of Spencer Cain, PE at Stantec Consulting Michigan Inc., in writing by email at spencer.cain@stantec.com. Questions by telephone call are prohibited. Questions will not be accepted if received less than nine (9) calendar days before the bids are due. All bids shall be submitted in a sealed envelope and shall contain, as a minimum, all of the following: Bidder's Qualification and Experience Statement (QES-1-4), Proposal (P1-5), Designation of Major Subcontractors and Suppliers (MS-1), Legal Status of Bidder (LS-1), Bid Certification (BC-1). Each Proposal shall be accompanied by a cashier's check, certified check, money order or bid bond, payable to the OWNER, in an amount not less than five percent (5%) of the amount of the Proposal, as a Bid Security. The Bid Security of the Bidders under consideration will be returned after approval of the Contract by the OWNER. All others will be returned after the Proposal opening. The successful Bidder will be required to furnish a satisfactory Performance Bond and Labor and Material Bond, each in the amount of One Hundred Percent (100%) of the Contract. Withdrawal of any Proposal is prohibited for a period of 90 days after the actual date of the opening thereof The OWNER reserves the right to accept any Proposal, to reject any or all Proposals, and to waive any irregularities in any Proposal, in the interest of the OWNER. The following requirements shall apply to the Contract for the work of this project and to all subcontracts thereunder: 1) State of Michigan Revolving Fund Requirements; 2) Project Wage Determination (under the Davis-Bacon Act, as amended, and related statutes); 3) Equal Opportunity Clause (Executive Order 11246); 4) Debarment Certification. The successful bidder shall fully comply with all of these special provisions and shall be responsible to ensure compliance with same by all of his subcontractors. Bids not incompliance with the contract requirement will risk forfeit of bid security bond. This project requires compliance with the Davis Bacon Act and adherence to the current U.S. Department of Labor Wage Decision. Document requests shall indicate whether request is by: Prospective Bidder, Prospective Subcontractor, Prospective Supplier, or other.

Award

Water / Sewer

$2,223,951.00

Public - City

Site Work

41

12

10

3

Subscribe For Documents

20 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet
Division 01 - General Requirements

Division 01 - General Requirements

Summary, Summary of Work, Work by Owner, Price and Payment Procedures, Contract Modification Procedures, Payment Procedures, Schedule of Values, Quality Requirements, Regulatory Requirements, Temporary Facilities and Controls, Vehicular Access and Parking, Traffic Control, Execution and Closeout Requirements, Examination and Preparation, Execution, Application, Cleaning and Waste Management, Closeout Procedures, Closeout Submittals, Maintenance Data, Bonds, Warranties, Spare Parts, Facility Operation, Facility Operation Procedures, Facility Maintenance Procedures
Division 02 - Existing Conditions

Division 02 - Existing Conditions

Site Remediation, Chemical Decontamination
Division 03 - Concrete

Division 03 - Concrete

Concrete Forming and Accessories, Concrete Forming, Structural Cast-in-Place Concrete Forming, Concrete Reinforcing, Precast Concrete
Division 04 - Masonry

Division 04 - Masonry

Unit Masonry, Clay Unit Masonry
Division 09 - Finishes

Division 09 - Finishes

Painting and Coating
Division 11 - Equipment

Division 11 - Equipment

Entertainment Equipment, Musical Equipment, Bells
Division 22 - Plumbing

Division 22 - Plumbing

Plumbing, Common Work Results for Plumbing, General-Duty Valves for Plumbing Piping
Division 23 - Heating Ventilating and Air Conditioning

Division 23 - Heating Ventilating and Air Conditioning

Heating, Ventilating, and Air Conditioning (HVAC), Common Work Results for HVAC, General-Duty Valves for HVAC Piping, HVAC Piping and Pumps, Hydronic Piping and Pumps, Hydronic Pumps
Division 26 - Electrical

Division 26 - Electrical

Medium-Voltage Electrical Distribution, Medium-Voltage Transformers, Low-Voltage Electrical Distribution, Low-Voltage Transformers, Facility Electrical Power Generating and Storing Equipment
Division 31 - Earthwork

Division 31 - Earthwork

Earthwork, Common Work Results for Earthwork, Aggregates for Earthwork, Earth Moving, Excavation and Fill, Excavation, Dewatering, Backfill, Compaction, Shoring and Underpinning, Shoring, Sheet Piling, Special Foundations and Load-Bearing Elements, Foundation Anchors
Division 32 - Exterior Improvements

Division 32 - Exterior Improvements

Bases, Ballasts, and Paving, Curbs and Gutters, Planting, Plants, Trees
Division 33 - Utilities

Division 33 - Utilities

Utilities, Common Work Results for Utilities, Water Utilities, Water Utility Distribution Piping
Division 34 - Transportation

Division 34 - Transportation

Transportation
Division 41 - Material Processing and Handling Equipment

Division 41 - Material Processing and Handling Equipment

Manufacturing Equipment, Machining Equipment, Drilling Equipment
Division 43 - Process Gas and Liquid Handling, Purification and Storage Equipment

Division 43 - Process Gas and Liquid Handling, Purification and Storage Equipment

Gas Handling Equipment, Gas Compressors
Division 44 - Pollution Control Equipment

Division 44 - Pollution Control Equipment

Water Treatment Equipment

Find More Local Projects

Within 75 Miles of This Project
160
Active Projects
102
Bidding Soon
1,407
All Active Projects
625
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

March 10, 2023

May 9, 2023

img_map_placeholder

Multiple Locations, Burton, MI

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.