Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Published June 3, 2025 at 8:00 PM
Updated June 4, 2025
Site work and paving for a civil project in Laguna Beach, California. Completed plans call for site work for a road / highway; for paving for a road / highway; and water / sewer project.
**As of June 3 ,2025, project was awarded, to GMZ Engineering, Inc. ,with an awarded amount of $5,311,250 start date 6/23/25** Question Deadline 03/27/2025 at 5:00 PM PT All communications relative to this project shall be directed to Ulises Escalona, Senior Project Manager at uescalona@lagunabeachcity.net. In general, the WORK of this Contract will consist of relocating the existing 70kW emergency natural gas generator to a new location, installed in a new below grade CIP concrete vault, and an above grade electrical/control building, installation of a new below ground submersible style sewer lift station and valve vault, demolition of the existing lift station and site features, and rehabilitation/reconstruction of the Anita Street beach access stairs, including ALL general civil site improvements within the City of Laguna Beach. In accordance with the provisions of Sections 1773.2 of the California Labour Code, copies of the general prevailing rate of per diem wages as determined by the State Director of Industrial Relations are available on the Internet at the World Wide Web site of the State Department of Industrial Relations at under Statistics and Research. It shall be mandatory upon the contractor to whom the contract is awarded and upon any subcontractor under him to pay not less than said specified rates to all workers employed by them in the execution of the contract. All parties to the contract shall be governed by all provisions of the California Labour Code relating to prevailing wage rates; Sections 1770-1781 inclusive. If required in the Notice Inviting Bids, bids shall be accompanied by a certified or cashier's check or an acceptable corporate bid bond on the form furnished by the City for an amount not less than ten percent (10%) of the bid, made payable to the order of the City of Laguna Beach. The Contractor will be required to post a payment bond guaranteeing the payment to subcontractors and other persons furnishing labour, materials and/or equipment with respect to the project in an amount equal to one hundred percent (100%) of the estimated Contract price. The City reserves the right after opening bids to reject any or all bids, to waive any informality (non-responsiveness) in a bid, or to make award to the lowest responsive, responsible bidder and reject all other bids, as it may best serve the interest of the City. (b) As a condition of award, the successful bidder will be required to submit payment and performance bonds and insurance. The Contractor shall possess a valid Class A, General Engineering, Contractor License at the time of submitting bids, in accordance with provisions of Chapter 9, Division III of the California Business and Professions Code. Contractor shall be in good state licensing standing Specifically, the WORK will include but will not be limited to the following major items: 1. Following and coordinating with the City on the project identified Inventory of Mitigation Measures for: Biological Resources, Cultural Resources, Geology and Soils, Noise, and Tribal Cultural Resources. Refer to Appendix B of Technical Specifications. 2. General site clearing, grubbing, demolition, and excavation for new constructed structures. 3. Installation of site stormwater features and equipment. 4. Installation of a new below ground concrete generator vault and associated infrastructure for the relocation of an existing 70kW natural gas standby emergency generator. 5. Installation of a new SoCal Gas natural gas service meter and service for the relocated generator. 6. Installation of a new Southern California Edison electrical service meter (480V power). 7. Civil grading improvements as part of the rehabilitation/reconstruction of the existing Anita Street beach access stairs. 8. Installation of a new submersible pump-style, below ground, sewer pump station and valve vault; installation of a new above ground electrical building. 9. Installation of new City-approved landscaping and potable water irrigation system. New electrical, controls, instrumentation, and programming of the proposed
Award
Water / Sewer
$3,724,286.00
Public - City
Paving, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
April 8, 2025
June 23, 2025
Anita St, Laguna Beach, CA
Related To This Project
Laguna Beach, CA
Bid Date: Oct 03 2023
Laguna Beach, CA
Bid Date: Dec 16 2021
Laguna Beach, CA
Bid Date: Nov 16 2021
Laguna Beach, CA
--
Laguna Beach, CA
Bid Date: Jan 13 2022
Laguna Beach, CA
Bid Date: Jan 17 2022
Laguna Beach, CA
--
Laguna Beach, CA
--
Laguna Beach, CA
--
Laguna Beach, CA
--
Laguna Beach, CA
--
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.