Published April 11, 2024 at 8:00 PM

Updated December 17, 2024

Site work for a civil project in New Hope, Minnesota. Completed plans call for site work for a road / highway.

As of April11, 2024, project was awarded to GMH Asphalt Corporation in the amount of $1,717,005.50. Bid Security in the amount of 5 percent of the amount of the Bid must accompany each Bid in accordance with the Instructions to Bidders. The Owner reserves the right to retain the deposits of the 3 lowest Bidders for a period not to exceed 60 days after the date and time set for the Opening of Bids. No Bids may be withdrawn for a period of 60 days after the date and time set for the Opening of Bids. The Owner reserves the right to reject any and all Bids, to waive irregularities and informalities therein, and further reserves the right to award the Contract to the best interests of the Owner. The furnishing of all labor, materials, and all else necessary for the following: 2024 Infrastructure Improvements Project - City Project No. 1107 In general, Work consists of the replacement of watermain, storm water and street improvements. The Project consists of the following approximate quantities for the Base Bid: 5,000 LF Remove and Replace Concrete Curb and Gutter 12,600 SY Reclaim and Shape Bituminous Pavement 49,300 SY Mill Bituminous Pavement (depth 2") 15 EA Remove and Replace Sanitary Sewer Frame and Rings With HDPE Rings and Frames 20 EA Remove and Replace Storm Sewer Adjustment Rings, Savage Casting Assembly 365 LF 6" NonPerforated Collection Pipe 200 LF Remove CIP Water Main (6" - 12") 3 EA 12" Gate Valve and Box 5,350 TN Type SP 9.5 Wearing Course Mixture 3,150 TN Type SP12.5 Wearing Course Mixture 4,500 LF 4" Double Solid Line Multi-Component Ground In 1,950 LF 4" Double Solid Line Paint Along with miscellaneous utility improvements, removals, restoration, and correlated appurtenances. Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information for such questions provided in the Advertisement for Bids Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date

Award

Water / Sewer

$1,717,006.00

Public - City

Site Work

66

22

10

4

Subscribe For Documents

16 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet
Division 01 - General Requirements

Division 01 - General Requirements

Price and Payment Procedures, Contract Modification Procedures, Payment Procedures, Schedule of Values, Administrative Requirements, Submittal Procedures, Certificates, Quality Requirements, References, Definitions, Temporary Facilities and Controls, Vehicular Access and Parking, Traffic Control, Temporary Barriers and Enclosures, Execution and Closeout Requirements, Examination and Preparation, Execution, Application, Closeout Submittals, Warranties, Facility Operation, Facility Operation Procedures, Facility Maintenance Procedures
Division 02 - Existing Conditions

Division 02 - Existing Conditions

Demolition, Selective Site Demolition
Division 03 - Concrete

Division 03 - Concrete

Cast-in-Place Concrete, Concrete Curing, Precast Concrete
Division 04 - Masonry

Division 04 - Masonry

Unit Masonry, Clay Unit Masonry
Division 07 - Thermal and Moisture Protection

Division 07 - Thermal and Moisture Protection

Dampproofing and Waterproofing, Steep Slope Roofing, Shingles and Shakes, Asphalt Shingles
Division 09 - Finishes

Division 09 - Finishes

Tiling, Painting and Coating
Division 10 - Specialties

Division 10 - Specialties

Information Specialties, Signage
Division 31 - Earthwork

Division 31 - Earthwork

Earthwork, Common Work Results for Earthwork, Soils for Earthwork, Aggregates for Earthwork, Earth Moving, Grading, Finish Grading, Excavation and Fill, Subgrade Preparation, Excavation, Dewatering, Fill, Backfill, Compaction, Embankments, Erosion and Sedimentation Controls
Division 32 - Exterior Improvements

Division 32 - Exterior Improvements

Exterior Improvements, Operation and Maintenance of Exterior Improvements, Watering, Schedules for Exterior Improvements, Bases, Ballasts, and Paving, Base Courses, Aggregate Base Courses, Curbs and Gutters, Concrete Curbs and Gutters, Paving Specialties, Pavement Markings, Planting, Planting Preparation, Soil Preparation, Turf and Grasses, Seeding, Sodding
Division 33 - Utilities

Division 33 - Utilities

Utilities, Common Work Results for Utilities
Division 34 - Transportation

Division 34 - Transportation

Transportation
Division 40 - Process Interconnections

Division 40 - Process Interconnections

Process Integration, Common Work Results for Process Integration
Division 41 - Material Processing and Handling Equipment

Division 41 - Material Processing and Handling Equipment

Manufacturing Equipment, Machining Equipment, Grinding Equipment, Finishing Equipment, Grinding Equipment
Division 44 - Pollution Control Equipment

Division 44 - Pollution Control Equipment

Water Treatment Equipment

Find More Local Projects

Within 75 Miles of This Project
81
Active Projects
40
Bidding Soon
852
All Active Projects
353
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

March 14, 2024

April 15, 2024

img_map_placeholder

Multiple Locations, New Hope, MN

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.