Demolition, site work, paving, new construction and addition to a bridge / tunnel in Liberty Township, Ohio. Completed plans call for the addition of a bridge / tunnel; for the construction of a bridge / tunnel; for site work for a bridge / tunnel; for paving for a bridge / tunnel; and for the demolition of a bridge / tunnel.
KYLES STATION ROAD BRIDGE 4 SCOPE OF WORK 104.01 Intent of the Contract Documents. The intent of the Contract Documents is to provide for the design, construction, and completion ofthe Work. Perform the Work according to the Contract Documents. 104.011 Design ofthe Project. The Designer and subconsultants will provide all necessary services to design all permanent and temporary portions of the Project in accordance with the Contract Documents, not necessarily including Work incorporated in the preparation of Working Drawings or Engineered Drawings. All work shall conform to current LPA, FHWA and AASHTO standards, practices, policies, guidelines and specifications. Unless otherwise noted in the Contract Documents, the LPA's standards, practices, policies, guidelines and specifications shall control in case of a conflict. The standard of care for all such services performed or furnished pursuant to the Contract will be the care and skill ordinarily exercised by members ofthe engineering profession practicing under similar conditions at the same time and locality. The DBT shall require the Designer to assign only qualified engineers and surveyors, professionally registered in the State of Ohio, in direct responsible charge of engineering and surveying endeavors. When services required are predominantly oriented toward other disciplines such as environmental, landscaping, transportation planning, or architectural applications, the Designer shall assign other professionally competent personnel registered in Ohio or certified as required by law, to be in charge ofthe work. Electronic plans will be developed by the Designer in accordance with the Location and Design Manual. The Designer shall perform all necessary services to design all permanent and temporary portions ofthe Project, not including Work incorporated in the preparation of Working Drawings or Engineered Drawings, in accordance with the Contract Documents including the following: A. Consult with LPA to understand the requirements for the Project and review available data. B. Advise the LPA as to the necessity ofproviding or obtaining from others additional reports, data or services ofthe types provided in paragraph 104.012 and assist the LPA in obtaining such reports, data, or services. C. Develop maintenance of traffic plans in accordance with the current Standard Construction Drawings, Location and Design Manual, OMUTCD and the Scope of Services. D. Maintain and make available to LPA, at LPA's request, a Project Record which includes a history of significant events (changes, comments, etc.) which influenced the development ofthe project. E. Perform any surveys (see LPA Survey Manual) required for this project. F. Perform hydraulic analysis as set forth in the Scope of Services document. The results ofthe analyses must show no harmful interference to adjacent riparian vegetation (along streams). Results must be certified by the Designer. The certification must state that the proposed structure will have an equal to or greater hydraulic capacity and that a deletion of existing auxiliary openings and overflow areas is not planned. G. Perform any additional needed soils surveys, soils borings, and geotechnical investigations, with appropriate analysis to produce the proposed design. H. Reference the appropriate Construction and Materials Specifications in the Plans for all construction work to be performed and all materials to be furnished. I. Provide Plans, specifications and supporting documents for review by LPA at the several stages of plan development review required by the Scope of Services. J. Provide written concurrence on DBT accepted Shop Drawing(s). Written concurrence shall be provided with the submission to the LPA. K. Provide concurrence on acceptability ofdeveloped Engineered drawings identified in 501.05.A 1, 501.05A 2, 501.05.A 3, 501,05B 3, & 501.05B 6. Written concurrence shall be provided with the submission to the LPA. L. Provide concurrence on acceptability of Corrective Work Plan (CWP) as described in 501.05.C. Written concurrence shall be provided with the submission to the LPA. , M. Perform the additional duties and requirements as explained in "Specifications for Consulting Services". Design services that require prequalification may only be performed by firms that are prequalified forthose services at the time ofperformance ofthe services. The Designer and subconsultants that will perform design work must be listed in the appropriate prequalification category on the following website: http://www.dot.state.oh.us/Divisions/Engineering/Consultant/Pages/default.aspx The Designer and all subconsultant names and addresses must be the same as those on file with the LPA. All engineering services must comply with Section 4733.16 ofthe Ohio Revised Code. Interpret all references to guidelines, recommendations and considerations within applicable design manuals as minimum requirements except when specifically excluded within the Scope of Services. Perform recommended evaluations ifnot provided by the LPA. Perform an analysis and submit to the LPA for review and concurrence if a recommendation in any design manual cannot be met. This analysis shall indicate the reasons for a deviation from a design recommendation and shall propose an acceptable solution. Cost or an incorrect bid assumption shall not be a reason for a deviation. A deviation from a design recommendation shall not be included in the design without the LPA Design Project Manager’s concurrence.
Award
Bridges / Tunnels
$2,700,000.00
Public - County
Addition, Demolition, New Construction, Paving, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
May 8, 2025
June 16, 2025
Kyles Station Rd, Liberty Township, OH
Related To This Project
Liberty Township, OH
Bid Date: Jul 16 2025
Liberty Township, OH
Bid Date: May 21 2025
Liberty Township, OH
Bid Date: May 28 2025
Liberty Township, OH
--
Liberty Township, OH
--
Liberty Township, OH
Bid Date: Nov 24 2025
Liberty Township, OH
Bid Date: Apr 02 2025
Liberty Township, OH
Bid Date: Mar 06 2025
Liberty Township, OH
Bid Date: Feb 20 2025
Liberty Township, OH
Bid Date: Jun 18 2025
Liberty Township, OH
--
Liberty Township, OH
Bid Date: Jun 26 2025
Liberty Township, OH
--
Liberty Township, OH
Bid Date: Dec 04 2025
Liberty Township, OH
Bid Date: Aug 09 2024
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.