BLOCK PAGE!!!

Subscribe For Access

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Saving Project...

Demolition, site work, paving, asbestos abatement and new construction of a mixed-use development in Edinburg, Texas. Completed plans call for the demolition of a municipal facility; for the construction of a municipal facility; for asbestos abatement for a municipal facility; for site work for a sidewalk / parking lot; and for paving for a sidewalk / parking lot.

https://riograndeguardian.com/cortez-pandemic-impacted-construction-of-new-county-courthouse/ Cortez: Pandemic impacted construction of new county courthouse Hidalgo County Judge Richard Cortez says he and his Commissioners Court colleagues want the best new courthouse possible. But he and the commissioners do not want anybody using it until it is properly completed. Everyday someone asks me the status of the (Hidalgo County) courthouse. And, as you know, the courthouse was contracted out before I became county judge. It was a process of going out for bids, designing it, etcetera. A contractor was selected and there’s a contract. So, when you have already selected the contractor and you already have a contract, then that’s what I inherited. That’s what I heard. That’s what we inherited the present (county) commission. And as we went through the process, we also hired a project manager. So, here we had a designer that designed the courthouse. We have a contractor to build the courthouse. We had a project manager to make sure that the contractor was doing what he was supposed to be doing based on the design. So, we had all of those precautions. We had all those things in place to hopefully get us a good courthouse. And if there was any violation of any duties, we had a legal contract that said, hey, here’s the duties that each one has. So, that’s what we have to deal with. So, when a contractor hasn’t fulfilled properly its duty to finish the courthouse, then our only recourse is what are the legal rights within the contract. So, that’s what we have been doing. That’s what we have been doing and so far, the issues that have occurred, we’ve been trying to resolve them. And we have what we call life and safety issues. These are the serious issues, and then we have other cosmetic types of issues. We’re pretty well down… that we’ve eliminated most of our life and safety issues. And we’re dealing with what we would call cosmetic, which is basically the stucco issue. But here we are, during the process of constructing this courthouse, we went through a pandemic, a 100-year pandemic. One thing that happens once in 100 years that had an interruption, and that construction had an interruption in our ability to be able to put people to construct it and our ability to get supplies. Then as we kept going through the through the process, other issues surfaced. So, yes, it’s taken longer than we wanted it to. But we want the best courthouse that is (well) designed. We want it to be right. We want it to be correct. We don’t want to have anybody in there unless it’s the way it should be. And right now, it’s not. So, we want to make sure that we don’t move in there until it is perfect control, it is right. And, and we’re getting there. But again, we have limitations as to what the agreement between us and the contractor says, and that’s taken a little longer than what we would like it to be. As county judge, I have a duty to get it done, to get it right for our people as soon as possible. We are working right now as efficiently as we can to do just that. When you start a journey… and certainly the first explorers who were going east to west, they didn’t know where to go. So, you have to adjust as you go. That’s where we are right now. We trying to find that model that works. And the best thing that I can tell the people of the Rio Grande Valley is that we have a lot of people that are very talented, very experienced wanting to find that solution and we’re all working together. Editor’s Note: The above commentary was provided by Hidalgo County Judge Richard Cortez to the Rio Grande Guardian during a video interview held at his office in Edinburg. Cortez discussed two or three issues. The above commentary is what he said about the new Hidalgo County Courthouse. -------------------------------------------------------------------- Hidalgo County is in the process of completing its new county courthouse located at 100 N. Closner Blvd. in Edinburg, Texas. The construction of the new courthouse was awarded as an independent contract and is considered Phase I of the courthouse project. Phase I work will be completed before Phase II construction commences. The existing courthouse, constructed in 1950 with a floor expansion in the 1980s, will undergo a transformation in Phase II. Phase II will involve asbestos abatement, demolition of the current courthouse, the creation of a new parking lot, and the construction of a meander. Question Submission Deadline: July 15, 2024, 5:00pm Question Response Deadline: July 17, 2024, 12:00am A Bid Bond for 5% of the project will be required. Pre-bid meeting info : Dial by your location o +1 346 248 7799 US (Houston) o +1 669 900 6833 US (San Jose) o +1 929 205 6099 US (New York) o +1 312 626 6799 US (Chicago) o 833 548 0282 US Toll-free o 877 853 5247 US Toll-free o 888 788 0099 US Toll-free o 833 548 0276 US Toll-free Meeting ID: 863 5743 4899 Passcode: 584130 Join by SIP o 86357434899@zoomcrc.com --- Join by H.323 o 162.255.37.11 (US West) Meeting ID: 863 5743 4899 Passcode: 584130 The CONTRACTOR hereby agrees to commence work under this contract on or after a date to be specified in written "Notice to Proceed" of the OWNER and to fully complete the project within ninety (90) working calendar days thereafter. The CONTRACTOR further agrees to pay, as liquidated damages, the sum of $500.00 for each consecutive calendar day thereafter.

Post-Bid

Municipal

$9,100,000.00

Public - County

Asbestos Abatement, Demolition, New Construction, Paving, Site Work

Documents for this project are exclusively Specifications. If Plans become available, we will add them here.

7

Subscribe For Documents

4 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
42
Active Projects
27
Bidding Soon
431
All Active Projects
172
Updated Recently

One Low Price

  • One license and one market
  • Details and key contacts on all bidding projects
  • Organize your pipeline with a digital bid board
  • Automatically match opportunities to your profile
  • Saved searches deliver daily project leads to your email inbox

Market Pricing Around

  • All Starter Product functionality
  • Access to all documents (plans, specifications, and addenda)
  • Access to planning projects
  • Access to contact information
  • Ability to Export

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

Sign-up for Instant Access.

Get Started Now

Get the right
data with Project Intelligence

Share with your network.

Project Shared

with

example@example.com

Upgrade now for industry‑leading commercial construction data.

You've reached the free-view limit.

Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.

Get Access Now

Choose what you would like to do.

Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.

August 2, 2024

October 1, 2024

March 31, 2025

img_map_placeholder

100 N Closner Blvd, Edinburg, TX

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.