Renovation of a water / sewer project in Cookson, Oklahoma. Completed plans call for the renovation of a wastewater treatment plant.
Quantity Unit Description 1 L.S. Follow unloading instructions for the unloading of the CMF unit from shipping container (will require coordination with shipping company and having handling equipment with minimum 10,000-lb lifting capacity at water treatment plant (WTP) to unload CMF unit once it arrives) and placement inside WTP. Unloading of Electrical & Pneumatic Control Panels and other loose shipped items. Installation of four concrete equipment pads inside WTP for CMF unit (must be installed before unit arrives, anticipated arrival of unit is end of May). Installation of support leg extensions onto equipment pads. Installation of CMF unit onto leg extensions. Installation of block (4) & bleed valves (4) to CMF unit (will require field electrical wiring and pneumatic tubing to be supplied and installed). Installation of Unit Process & B/Wash Feed (AV3), Unit CIP Inlet/Drain (AV9), Unit Manifold Filtrate Exhaust (AV15), Unit TURB Sample Isolation (MV3), and Unit Filtrate Turbidimeter Sample (SV1) loose shipped valves. Installation of Turbidimeter panel. Installation of Unit Electrical and Pneumatic Control Panels on CMF unit with external field wiring (landing of wires and pneumatic tubing inside each control panel will be done by Memcor representative). 1 L.S. Piping and Appurtenances. All interconnect piping/expansion joints, flange hardware, tubing, fittings and installation required to connect new CMF unit to raw water feed and filtered water piping, existing ancillary equipment (Backwash Tank, Process Air Receiver, To/From CIP System, To CIP System) Piping materials and service lines must conform with table on Sheet 4 of the Memcor P&IDs. 1 L.S. Electrical and Controls. Upgrade WTP master control panel PLC, I/O modules, power supply and communication card to match/provide compatibility with PLC in new CMF unit. Upgrade existing CMF unit PLC, I/O modules, power supply and communication card to match/provide compatibility to upgraded master control panel and new CMF unit. Install/Supply Ethernet wiring between existing Page 2 master control panel and new CMF unit control panel. Provide field wiring and air supply (as required) for Block & Bleed Valves, and all loose shipped vales as required by Memcor Installation Instructions/P&ID Sheets (included in Specifications). Provide external field wiring for power and air supply hook up for new CMF unit. 1 L.S. Upgrade and configure SCADA system for compatibility with new CMF unit and upgraded PLC for master control panel and existing CMF unit. Upgrade and configure new control software.
Post-Bid
Water / Sewer
$500,000.00
Public - County
Renovation
Trades Specified
Division 00 - Lorem Ipsum
Division 01 - General Requirements
Division 02 - Existing Conditions
Division 03 - Concrete
Division 04 - Masonry
Division 05 - Metals
Division 07 - Thermal and Moisture Protection
Division 08 - Openings
Division 09 - Finishes
Division 10 - Specialties
Division 11 - Equipment
Division 12 - Furnishings
Division 22 - Plumbing
Division 23 - Heating Ventilating and Air Conditioning
Division 26 - Electrical
Division 28 - Electronic Safety and Security
Division 31 - Earthwork
Division 32 - Exterior Improvements
Division 33 - Utilities
Division 34 - Transportation
Division 35 - Waterways and Marine Construction
Division 40 - Process Interconnections
Division 41 - Material Processing and Handling Equipment
Division 44 - Pollution Control Equipment
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
April 17, 2025
May 19, 2025
Multiple Locations, Cookson, OK
Related To This Project
Cookson, OK
Bid Date: Feb 27 2025
Cookson, OK
--
Cookson, OK
Bid Date: Dec 17 2024
Cookson, OK
Bid Date: Oct 10 2024
Cookson, OK
Bid Date: May 29 2024
Cookson, OK
Bid Date: Jan 21 2022
Cookson, OK
Bid Date: Jan 24 2022
Cookson, OK
--
Cookson, OK
--
Cookson, OK
Bid Date: Jun 13 2024
Cookson, OK
Bid Date: Jun 13 2024
Cookson, OK
--
Cookson, OK
Bid Date: May 12 2022
Cookson, OK
Bid Date: Feb 21 2022
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Unlock Efficiency: The Future of Commercial Construction is Data-Driven
Sign up now to get free company and project data. No payment required.
.webp)
Get the right
data with Project Intelligence
Share with your network.
Water System Improvements Installation of New CMF Unit and System Upgrades
Project Shared
with
example@example.com
.webp)
Upgrade now for industry‑leading commercial construction data.
You've reached the free-view limit.
Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.