BLOCK PAGE!!!
Get Full Details

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Published October 2, 2025 at 8:00 PM

Updated October 3, 2025

Site work for a water / sewer project in New York, New York. Completed plans call for site work for a water / sewer project.

Design of Ribbed Mussel Beds in both Bergen and Thurston Basins as required under the approved Jamaica Bay CSO LTCP. This Request for Proposal ("RFx) is being released through Passport, New York City's online procurement portal. Responses to this RFx should be submitted via Passport. CSO-GC-SFS-CM-RH3-CP3 The City of New York ("City") and the United States Environmental Protection Agency ("EPA") entered into an Administrative Settlement Agreement and Order for Remedial Design, Removal Action and Cost Recovery ("Settlement Agreement") for the Gowanus Canal Superfund site, effective June 9, 2016. The City of New York was directed to institute combined sewer overflow (CSO) controls by designing and constructing retention tanks to intercept discharges from outfall RH-034 in the Red Hook (RH) Wastewater Resource Recovery Facility (WRRF) drainage area, and the work to construct this facility is divided into three phases. Further, the Administrative Order for Remedial Action, Removal Action and Design (UAO), (CERCLA 02-2021-2019), effective June 30, 2021, includes construction start and completion milestones for CP-3 of July 1, 2026 and March 31, 2029 respectively. Contracts CSO-GC-SFS-RH3-CP1 ("CP-1") and CSO-GC-SFS-RH3-CP1A ("CP-1A") were the first phase and included abatement of regulated materials; demolition of structures to slab and/or grade, disconnection and/or demolition of utilities; and site preparations for turnover of the project site (CP-1) and construction staging area (CP-1A). CSO-GC-SFS-RH3-CP2 ("CP-2") is the second phase and includes construction of the support of excavation; the excavation, stabilization, and disposal of soils; and construction of the foundation for the facility. This work will be completed approximately 6-9 months after the start of the CP-3 contract. Construction Management services for CP-1, CP-1A, and CP-2 are provided under separate contracts. The third construction package ("CP-3") is for the construction of the CSO facility superstructure, reconstruction/abandonment of impacted conveyance, and construction of public amenities above the below ground portions of the tank. Although the CP-3 UAO construction start milestone date is July 1, 2026, commencement of CP-3 work is dependent on CP-2 construction progress. The scope of CP-3 also includes installation of all CSO Facility components and conveyance including mechanical equipment, electrical conduits and equipment, Heating, Ventilation, and Air Conditioning components, architectural features, and Con Ed network protection structure installation. Contamination may be encountered along the conveyance route, and the appropriate contaminated soil handling operations will be required. Instead of utilizing space on the site, the stabilization activities will likely occur in the street near the excavation. Odor control and groundwater treatment will be considered and included in the contract documents depending on the characteristics of the contaminants identified in the pre design investigation (PDI). Contaminated groundwater may either be treated at the location using smaller mobile treatment system and discharged to the sewer, or it could be trucked to a larger system located at the site for discharge to the sewer or the Gowanus Canal. This work will occur on two properties located at Block 411, Lot 24 and Block 418, Lot 1, bounded by the Gowanus Canal on the west side and Nevins Street on the east side, between Butler Street and Degraw Street in Brooklyn, NY. Additionally, Block 425, Lot 1 will be used by the contractor as the construction staging area. B. Detailed Scope of Services The following is a description of work under this Contract, and shall not be construed as a complete description of the work to be performed. Proposers must self-perform at least 51% of the work. Please see the Scope of Services document for a general scope of services for this type of project. The CM Consultant shall provide the construction management services to: 1. Erect the building above the existing CSO retention tank constructed under the CP-2 Contract. Influent/drain channel personnel access; 2. Install support of excavations, piles and foundations; 3. Access opening covers within the building; 4. Construct New Regulator R-24, Replacement of Outfall RH-038, Modification of Regulator RH-034, and connection to the existing Influent Channel constructed under the CP-2 contract; 5. Install chambers for combined sewage and stormwater Conveyance structures along Nevins Street; 6. Install retaining walls. Concrete fill and benching within the influent channel, screening channel, tank cells and other concrete below grade structures constructed under the CP-2 contract; 7. Remediate and reuse/dispose of contaminated excavated soil, and dewatering water associated with the conveyance construction; 8. Grade and construct landscaping work on top of tank; 9. Convert existing Regulator R-25 to a flow through chamber and replacement of former RH-033 CSO outfall with new combined sewer conveyance; 10. Convert existing Regulator R-24 to a flow through chamber, construction of a new Regulator R-24 and replacement of portions of the existing CSO Outfall RH-038 in Degraw Street; 11. Modify Regulators R-23 and R-22 in Sackett and President Streets; 12. Maintain combined and stormwater flow during construction; 13. Protect and relocate of existing utilities; 14. Install street lighting, signage, pavement restoration, markings, sidewalk and site restoration; 15. Restore interior and exterior building finishes, terracotta screen system and access doorways; 16. Restore brick finish facade on Con Edison blockhouse; 17. Install bending weirs, process screening, degritting, and pumping equipment, and associated piping; 18. Install material conveyance system including screenings conveyor and dumpster conveyors; 19. Install temporary electrical system for construction and soil/groundwater remediation systems; 20. Install three (3) 2500/2800 kilovolt-ampere (kVA), 26.4 kilovolt (kV), 277/480-volt (V) transformers, and three (3) 4000 A-rated fused network protectors to be provided and maintained by Con Edison (electric utility); 21. Install electrical power supply and distribution equipment; 22. Install Solar panels on roof top of CSO facility; 23. Install building and park lighting; and 24. Install digital display boards along building faces fronting Butler and Nevins Streets. Question Deadline date added as per Addendum 1 Last Day of Questions Monday, September 15th 2025

Post-Bid

Water / Sewer

$200,000.00

Public - City

Site Work

3

11

5

3

Subscribe For Documents

12 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
1,000
Active Projects
514
Bidding Soon
7,693
All Active Projects
0
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

September 26, 2025

July 1, 2026

Project location map

270 Nevins St, New York, NY


Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.