This is a service / maintenance or supply contract in Grand Island, Nebraska. Contact the soliciting agency for additional information.
The primary purpose is the procurement of three (3) replacement Transformer-Rectifier (T/R) sets for the Joy-Western, hot-side electrostatic precipitator at Platte Generating Station. The supplied T/R sets must meet or exceed the original design parameters, have compatible dimensions with the original transformers, and not require modifications to connect to existing electrical, bus duct, or oil containment. The equipment must be of heavy-duty industrial-grade design, suitable for use in a power plant operating environment, constructed to withstand rain, snow, sleet, hail, and temperature fluctuations below 0°F and above 100°F. The T/R sets must be fluid-immersed type OA suitable for outdoor installation, exposed to various climates. All external welds, coatings, and tank construction, insulation, and lifting requirements are specified. The contractor shall ensure the supplied T/R sets work with the existing current limiting reactor and complete a full factory functional test with documentation before shipping. Delivery of the fully assembled, oil-filled T/R sets must be made within 365 days of contract execution. A minimum one-year warranty covering parts and labor is required. Bidders must submit three references, an itemized cost estimate, explanations of deviations, installation and startup manual, estimated delivery, hardware specifications, drawings, and sample test and startup reports. Bids are evaluated primarily on itemized price, schedule, quality, economy, contractor experience, and adherence to specification. The contractor must comply with specified insurance requirements, fair labor standards, unemployment fund contributions, and nondiscrimination requirements. All bids must be submitted using the required forms; bid security of 5% is mandatory. Successful bidders must furnish performance and payment bonds each in the full amount of the contract price within the specified time. The Owner reserves the right to accept or reject any or all bids.
Post-Bid
Power Plant
$500,000.00
Public - City
Service, Maintenance and Supply
Plans and Specifications are not available for this project. If that changes, they will be made available here.
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
January 22, 2026
March 8, 2026
To Be Determined, Grand Island, NE
Related To This Project
Grand Island, NE
Bid Date: Feb 03 2026
Grand Island, NE
Bid Date: Feb 03 2026
Grand Island, NE
Bid Date: Feb 17 2026
Grand Island, NE
Bid Date: Feb 04 2026
Grand Island, NE
Bid Date: Feb 04 2026
Grand Island, NE
Bid Date: Feb 04 2026
Grand Island, NE
Bid Date: Jan 21 2026
Grand Island, NE
--
Grand Island, NE
Bid Date: Feb 03 2026
Grand Island, NE
Bid Date: Feb 10 2026
Grand Island, NE
Bid Date: Feb 10 2026
Grand Island, NE
Bid Date: Jan 22 2026
Grand Island, NE
Bid Date: Jan 13 2026
Grand Island, NE
Bid Date: Jan 13 2026
Grand Island, NE
Bid Date: Jan 13 2026
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.