Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Published April 17, 2023 at 8:00 PM
Updated October 1, 2024
Renovation of a water / sewer project in Sunnyvale, California. Completed plans call for the renovation of a water / sewer project.
Project No: 9265A10, PW22-17, UY-21-07 As of April 17, 2023, this project is under construction. Construction began early in 2023 and is expected to last a few years. All trades have been let. The City of Sunnyvale is seeking statements of pre-qualifications from licensed Electrical Subcontractors interested in providing a sub-bid on the UY-21-07 - Sunnyvale Cleanwater Program Secondary Treatment and Dewatering Project and/or UY-21-04 - Sunnyvale Cleanwater Program Existing Plant Rehab Project ("Projects") at the City's Water Pollution Control Plant (WPCP). All Prospective Electrical Subcontractors interested in providing a sub-bid on the above mentioned Public Works Projects at the City's Water Pollution Control Plant (WPCP) must be pre-qualified prior to submitting a sub-bid (Prospective Sub-Bidders) on either of those projects. The City will include a list of pre-qualified electrical contractors in the Prime Contract Bidding documents indicating that the Prime Contractor shall only solicit electrical sub-bids from the listed pre-qualified The Engineer's Opinion of Probable Construction Cost is approximately $200M (Total Project Construction Cost). The Engineer's Opinion of Probable Construction Cost for the electrical scope of work is approximately $30M (Total Project Construction Cost). The Engineer's Opinion of Probable Construction Cost is approximately $45M (Total Project Construction Cost) The Engineer's Opinion of Probable Construction Cost for the electrical scope of work is approximately $25M (Total Project Construction Cost). Deadline for Subcontractor's Questions December 10, 2021 Construction is anticipated to be completed by June 2026. Minority-Owned, Woman-Owned, and Small Business Enterprises are encouraged to respond to this solicitation. The purpose of the Secondary Treatment and Dewatering Project is to improve various components of the treatment process to meet anticipated future regulatory requirements. This project will build conventional activated sludge facilities, which will be the main method to provide secondary treatment. The existing ponds, air flotation tanks, and fixed growth reactors will remain in service to augment the new facilities during periods of high flow. Thickening and dewatering facilities will be constructed to handle the additional biosolids generated. Solids-handling equipment will be housed in a new building and the ventilated air will be treated by an odor control system. The project work includes the following items: 1. Demolition of the existing 63-inch storm drain pipes. 2. Construction of the new Bioreactors. 3. Construction of the new Blower Building. 4. Construction of the new Secondary Clarifiers. 5. Construction of the new RAS/WAS Pump Station. 6. Construction of the new Thickening/Dewatering Building. 7. Construction of the new Digested Sludge Storage Tank. 8. Construction of the new Thickened Sludge Blend Tank. 9. Construction of the new DEMON Sidestream Treatment. 10.Construction of the improvements to the existing DS supernatant pump station. 11.Construction of the new Standby Generator and Fuel Tank. 12.Additions and modifications to the WPCP paving, grading, and drainage systems. 13.Additions and modifications to the WPCP yard piping system. 14.Construction of a new utility trench. 15.Electrical system improvements, including replacement of the 12.47kV service from PG&E. 16.Instrumentation and control system improvements. The estimated cost for this Work is between: $250M.
Under Construction
Water / Sewer
$277,872,751.00
Public - City
Renovation
Trades Specified
Division 00 - Lorem Ipsum
Division 01 - General Requirements
Division 03 - Concrete
Division 04 - Masonry
Division 05 - Metals
Division 06 - Wood, Plastics, and Composites
Division 07 - Thermal and Moisture Protection
Division 08 - Openings
Division 09 - Finishes
Division 10 - Specialties
Division 11 - Equipment
Division 12 - Furnishings
Division 13 - Special Construction
Division 14 - Conveying Equipment
Division 21 - Fire Suppression
Division 22 - Plumbing
Division 23 - Heating Ventilating and Air Conditioning
Division 26 - Electrical
Division 27 - Communications
Division 28 - Electronic Safety and Security
Division 31 - Earthwork
Division 33 - Utilities
Division 34 - Transportation
Division 40 - Process Interconnections
Division 41 - Material Processing and Handling Equipment
Division 43 - Process Gas and Liquid Handling, Purification and Storage Equipment
Division 44 - Pollution Control Equipment
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
August 24, 2022
April 3, 2023

Multiple Locations, Sunnyvale, CA
Related To This Project
Sunnyvale, CA
--
Sunnyvale, CA
Bid Date: Mar 02 2023
Sunnyvale, CA
--
Sunnyvale, CA
Bid Date: Nov 01 2022
Sunnyvale, CA
--
Sunnyvale, CA
Bid Date: Oct 05 2022
Sunnyvale, CA
Bid Date: Nov 09 2022
Sunnyvale, CA
--
Sunnyvale, CA
Bid Date: Oct 19 2022
Sunnyvale, CA
Bid Date: Nov 16 2022
Sunnyvale, CA
Bid Date: Oct 13 2022
Poway, CA
Bid Date: Nov 18 2022
Lancaster, CA
Bid Date: Oct 18 2022
Claremont, CA
Bid Date: Oct 18 2022
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Cut Costs, Not Corners.
Get ahead of project risks by targeting the right work early. With detailed construction data at your fingertips, you can pursue jobs that match your margins—and walk away from those that don’t.
Sign up now to get free company and project data. No payment required.
.webp)
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
.webp)
Upgrade now for industry‑leading commercial construction data.
You've reached the free-view limit.
Thousands of projects are added every week - don't miss out. Explore the best product options for your business and subscribe today.
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.