Site work for a civil project in Naples, Florida. Completed plans call for site work for a water / sewer project.
As of July 2024, this project is under construction. This project consists of constructing two new horizontal biologically active pressure filters (BAF) with associated backwash water supply pump, backwash air scour blower, air supply system, lake transfer pump replacement and piping modifications, new underground and above ground piping, fittings, pipe connections, pipe supports, backwash drain pipe and outfall, valves, flow control valves, electrical improvements, electrical switchgear and duct banks, motor controls centers, instrumentation and controls, control panels, communication, miscellaneous sitework, demolition of the existing transfer pump and associated VFDs, demolition of existing motor control centers, demolition of the transformers, demolition of the existing transfer pump disconnects, demolition of the existing underground and above piping. The design of the BAF system allows for future expansion: two additional filters. All new equipment will be installed on a reinforced concrete slab at minimum one foot above the FEMA base floor elevation or as indicated on the drawings. This project is located at the City's Source Water Facility at 7130 N. Collier Blvd, Naples, FL 34114. This project is being bid as a lump sum contract. The contractor is responsible for obtaining the required Collier County permits. The City has obtained the Florida Department of Environmental Protection permit. Owner will reimburse Contractor for County permit fees paid. Question Deadline 10/12/2023 at 5:00 PM ET Answers & Addendum 10/10/2023 5:00 PM Please direct questions to Angela Johenning, Purchasing and Fiscal Analyst at: ajohenning@cityofmarcoisland.com; or (239) 389-5011; or 50 Bald Eagle Drive, Marco Island, Florida 34145. Bid Bond, in an amount not less than 5% of the bidders maximum possible award The undersigned further agrees to substantially complete all work covered by this Proposal within 635 consecutive calendar days, and to fully complete all work in its entirety, including final acceptance, within 665 calendar days from and including the Commencement Date
Under Construction
Water / Sewer
$9,932,000.00
Public - City
Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
November 16, 2023
December 4, 2023
7130 Collier Blvd, Naples, FL
Related To This Project
Naples, FL
Bid Date: Jun 27 2024
Naples, FL
Bid Date: Aug 09 2023
Naples, FL
Bid Date: Oct 23 2023
Naples, FL
Bid Date: Sep 08 2023
Naples, FL
Bid Date: Dec 16 2021
Naples, FL
--
Naples, FL
Bid Date: Jan 28 2021
Naples, FL
--
Naples, FL
Bid Date: Nov 03 2023
Naples, FL
Bid Date: Oct 18 2023
Naples, FL
Bid Date: Sep 08 2023
Naples, FL
Bid Date: Oct 29 2021
Naples, FL
Bid Date: Oct 12 2021
Naples, FL
Bid Date: Sep 20 2023
Naples, FL
Bid Date: Sep 14 2023
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.