Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Saving Project...
Renovation of a water / sewer project in Bay Shore, New York. Completed plans call for the renovation of a water / sewer project.
As of February 21, 2024, the project has not yet been awarded. The project will be awarded in the next 1-2 months. Bonds the Successful Bidder Will Be Required to Furnish a Performance Bond and a Labor and Material Bond/payment Bond in the Statutory Form of Public Bonds Required by Sections 136 and 137 of the State Finance Law, Each for 100% of the Amount of the Contract. Existing Plant and Well #2 Must Remain Operational Until New Plant is Operational and Approved. Work Includes Coordination Between All Contracts, Daily Cleaning, Submittals, as-builts and Closeout. General Construction Contract D006147: Work Includes but Not Limited to Concrete Foundation and Floor Slab, Masonry Block Walls, Concrete Water Storage Tanks, Stairs, Roof, and All Interior and Exterior Finishes & Incidentals Including Doors, Windows Louvers Fans, Grating, Trench Drains, Selective Demolition, and Site Work. Work Also Includes Providing Temporary Utilities, Utility Mark-out, Construction Fencing, Erosion Control, Sheeting and Bracing Excavation, Final Cleaning, Restoration, Assist With P and E Contract on Programming Controls, Start-up and Testing of All Equipment. Alternate 1 Work Includes Demolition of Existing Plant, Tanks, Drainage Structures, Rough and Final Site Grading, Plantings, and New Asphalt Driveway. Each Bid Must Be Prepared and Submitted in Accordance With the Instructions to Bidders and Must Be Accompanied by a Scanned Bid Security in the Form of a Certified Check, Bank Check, or Bid Bond in the Amount of: General Construction Contract: D006147 $70,766.00 (Seventy Thousand, Seven Hundred Sixty-six Dollars and Zero Cents); Electrical Contract: D006149 $37,505.00 (Thirty-seven Thousand, Five Hundred Five Dollars and Zero Cents); Plumbing Contract: D006148 $76,724.00 (Seventy- Six Thousand, Seven Hundred Twenty-four Dollars and Zero Cents). Minority and Women-owned Business Enterprise Participation Goals (Mwbe). The Following Goals for Mwbe Participation on This Project Have Been Established at: Minority Owned Business Enterprise (Mbe) Women Owned Business Enterprise (Wbe). Gc Contract: D006147 Mbe: 5% Wbe: 25%. E Contract: D006149 Mbe: 10% Wbe: 20%. P Contract: D006148 Mbe: 16% Wbe: 14%. Service-disabled Veteran Owned Business (Sdvob) Goals. The Following Goals for Sdvob Participation on This Project Have Been Established at: Service-disabled Veteran Owned Business. Gc Contract: D006147 Sdvob: 6%. E Contract: D006149 Sdvob: 4%. P Contract: D006148 Sdvob: 4%. Public Building Law 8(6) Pursuant to Public Building Law 8(6), The Completion Date for This Project is 365 Days After Agreement Has Been Approved by the Nys Comptroller's Office. Project Specific Liquidated Damages (Refer to Article 14.10 of the General Conditions). In the Event the Contractor Fails to Complete All the Work on Time, the Contractor Agrees to Pay the Office Liquidated Damages in the Amount Referenced in Article 14.10 of the General Conditions. For Administrative Related Questions, Utilize the Contact Noted Below: Ms. Margaret Ziminski, Mr. Nicholaus Nestasia, Ms. Tiffany Willms 631-321-3544 Liengineeringcontracts@parks.ny.gov. Please Note That Contacting. All Requests for Information (Rfis) Are Due by: 10:00 Am on Friday, December 29, 2023. Rfis Received After This Due Date and Time Will Not Be Processed. *The value for this project is based on a financial range. The value is listed as the highest possible cost from the range provided by a stakeholder or official project document. Estimated Range: $1,263,168.00 -$1,708,992.00 The Captree State Park Water Treatment Plant consists of two (2) wells each with an authorized capacity of 400 gallons per minute (GPM). Both the wells are drilled into the Magothy Aquifer. The treatment process at this facility includes filtration vessels to address elevated levels of iron followed by sodium hypochlorite treatment for disinfection and sodium hydroxide treatment for pH adjustment. The purpose of this project is to construct a new iron removal treatment system to replace the aging treatment system at this facility. Abbreviated Summary of General Construction Work Covered by Contract Documents (Contract G - D006147) 1. Furnish all labor, equipment, materials, tools, means, methods, and incidentals necessary to complete the Work as required by the Contract Documents for this Construction Contract. Each Contractor shall coordinate, through the Owner/Engineer, the work of their contract with the work by others. 2. Maintain operational the existing treatment building, system, storage tanks and Well No. 2 until such time as the new treatment system is operational and approved by SCDHS. 3. Coordinate with engineer and SCDHS for startup and obtaining approval to operate new treatment system to system. 4. This following abbreviated summary is provided in order to briefly describe the work covered by the Contract Documents for this Construction Contract. It is not all inclusive of the work under the Contract. 5. The work includes, but is not limited to, the following: a. Preliminary site work including site utility mark-out, erection of safety fencing, erosion control facilities, installation of stabilization pads, asphalt removals, sheeting, bracing, excavation, earth movement, sub-grade preparation, removal of excess and/or unsuitable excavated material, and import of suitable material, as necessary to install and construct all the work defined within the Contract Documents. b. Remove and legally dispose of existing items scheduled for demolition (including, but not limited to: existing Well No. 3 building, concrete pads, asphalt pavement required for work of base bid, and clearing of trees and brush as required). c. Site work including drainage structures, drainage piping, rough and final grading, backfilling and compacting excavations resulting from site removals, concrete sidewalk. d. Scope of Alternate Item 1, including demolition of existing iron treatment building, demolition of existing iron treatment equipment, demolition of existing underground water storage tanks, demolition of existing drainage structure, demolition of existing fuel tank, clearing of trees and brush as required, rough and final grading of demolished existing iron treatment building and water storage tanks area, full removal of existing driveway asphalt pavement, new driveway asphalt pavement and base, new asphalt pavement and base for trenched areas outside of curb line, and plantings. e. Furnish and supply temporary facilities. f. Construction of the new treatment building including a concrete foundation and floor slab, masonry block walls, concrete water storage tank, stairs, roof and all interior and exterior finishes & incidentals including but not limited to: doors, windows, louvers, fans, grating, trench drain systems, etc. g. Coordinate locations and installation of pipe or conduit penetrations and sleeves (provided by Contract P or E) in new floor slabs, foundation and masonry walls with Contract P or E. h. Coordinate locations of and perform installation of conduit penetrations in all existing floor slabs, foundation and masonry walls with Contract E. i. Coordinate locations of iron treatment vessels and vessel saddles with Contract P, prior to placement of foundations and installation of CMU wall. j. Painting of interior concrete block and other finishes. k. Final restoration of areas disturbed by all other contract work. l. Daily and Final cleaning. m. Project closeout submittals. 6. All other work shown and specified within the Contract Documents for Contract G.
Bid Results
Water / Sewer
$1,313,534.00
Public - State/Provincial
Renovation
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
January 18, 2024
March 18, 2024
3500 Ocean Pkwy, Bay Shore, NY
Related To This Project
Bay Shore, NY
Bid Date: Jan 31 2024
Bay Shore, NY
Bid Date: Feb 05 2024
Bay Shore, NY
Bid Date: Mar 05 2024
Bay Shore, NY
Bid Date: Jul 09 2024
Bay Shore, NY
Bid Date: Mar 15 2018
Bay Shore, NY
Bid Date: Jul 18 2024
Bay Shore, NY
Bid Date: Aug 01 2024
Bay Shore, NY
Bid Date: Jan 18 2024
Bay Shore, NY
Bid Date: Jan 18 2024
Bay Shore, NY
Bid Date: Jan 18 2024
Bay Shore, NY
Bid Date: Nov 03 2023
Bay Shore, NY
Bid Date: Oct 30 2023
Bay Shore, NY
Bid Date: Sep 29 2023
Bay Shore, NY
Bid Date: Oct 03 2023
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The best commercial construction data available. Period.
Sign up now to get instant access to project search, five projects and five companies, free.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.