BLOCK PAGE!!!
Get Full Details

Privately Funded

Bidding Soon

Documents Available

Publicly Funded

Addenda Available

Post-Bid

Published November 20, 2025 at 7:00 PM

Updated November 21, 2025

Site work for a water / sewer project in Winnipeg, Manitoba. Working plans call for site work for a water / sewer project.

At WEWPCC, the Work to be done under the Contract shall consist of isolating one (1) of the three (3) sludge holding tanks at a time in coordination with plant staff such that the other two (2) tanks may be used as normal, and then for each tank, one at a time, the work includes: (a) Scaffolding and formwork as required to perform the work below. (b) Selective demolition of surface concrete within the tank. (c) Cleaning the tank. (d) Replacing the process pipe penetrations of the tank and adding new 200mm penetrations to be used for temporary tank ventilation requirements during construction. (e) Structural upgrades and concrete and rebar installation and replacement. (f) Instrumentation replacement. (g) Surface preparation of the tank interior and pipe penetrations, and application of a protective liner by a certified applicator. (h) Curing controls for concrete repairs and liner according to manufacturer's requirements, (i) For the middle tank, replacement of steel mud baskets in the truck bay floor drain and installation of a new stainless steel pipe (complete with hangers) connection through the wall of the tank to a rainwater leader drain pipe leading to a sump pit below. (j) Surface preparation and application of a fast-curing polyurethane cement floor coat on the top face (truck driving surface) of the top slab of the tanks such that the delay in truck loading does not cause tanks to over-fill. This must be coordinated with plant staff. This shall be done all at once rather than on a per-tank basis. (k) Coordination with the Contract Administrator, Plant Staff, and Wintec (sludge trucking contractor) as required. (l) Implementation of confined space safety controls and protocols for working within the sludge tanks. (m) Being responsible for the site safety program and accommodating inspections by the Contract Administrator. (n) Redline as-built markups. (a) The tank top slab has been delineated into three rehabilitation sections as shown on the drawings. Strategic rehabilitation sequencing of tanks must be followed. The tank top slab is structurally compromised, and access is currently restricted. Therefore, no equipment will be permitted on the existing slab throughout construction. (b) Scaffolding, shoring, and formwork as required to perform the work below. (c) Selective demolition of concrete tanks according to the contract drawings. (d) Demolition of the masonry block room above the tanks on the north east corner of the main floor (only south and west walls need to be demolished as long as roof is adequately supported) and salvaging the equipment within for continued use, coordinating new location of equipment with Contract Administrator and plant staff. (e) Salvaging other equipment and instrumentation on and in the tank top slab for re- installation including the level sensing instrumentation and transmitters, the Magikist Hot Water Pressure Washer with all ancillary equipment, and the exhaust fan and ducts at the north west corner on the main floor. (f) Cleaning the concrete sludge holding tanks. (g) Replacing the process pipe penetrations and ventilation duct penetrations of the tanks. (h) Replacement hatches and removal of ladders. (i) Structural upgrades and concrete and rebar installation and replacement according to contract drawings. (j) Surface preparation of the tank interior and pipe penetrations, and application of a protective liner by a certified applicator. (k) Curing controls for concrete and liner according to manufacturer's requirements, (l) Coordination with the Contract Administrator, Plant Staff, and Wintec (sludge trucking contractor) as required. (m) Implementation of confined space controls and protocols for working within the sludge tanks. (n) Re-construction and installation of masonry room above the sludge holding tanks and re- installation of all equipment within it. (o) Re-installation of salvaged equipment above the tanks and instrumentation within the tanks, including level sensing instrumentation and transmitters, the Magikist Hot Water Pressure Washer with all ancillary equipment, and the exhaust fan and ducts at the north west corner on the main floor. (p) Being responsible for the site safety program and accommodating inspections by the Contract Administrator. (q) Mechanical HVAC upgrades according to contract drawings. These upgrades may be completed separately from sludge holding tank rehabilitation work. (r) Surface preparation and application of a polyurethane cement floor coat on the top face of the top slab of the tanks. This shall be done all at once rather than on a per-tank basis, (s) Special Conditions: (i) Contractor must take precautions to control debris and demolish tanks top slab in such a way as to mitigate risks to the tanks, pipework, or transfer pumps connected to the base of the tanks. (ii) Construction sequence on drawing 1-0102-SGAD-DD53 must be followed to avoid compromising structural integrity of the tanks and surround building structural systems. (iii) Interior tank walls are compromised. Contractor must install a protective barrier on Tank 2 north wall during Tank 2 and Tank 3 rehabilitation to prevent water jetting or other rehabilitation work until after Tank 1 is taken out of service. (t) Redline as-built markups. TIMELINE: A tender for construction resulted in no award. Low bid received was $12,070,000. Updates will be made upon rebid, expected December 2025/January 2026. Project may be split into 2 projects.

Final Planning

Water / Sewer

$15,000,000.00

Public - City

Site Work

We’ve obtained documents for this project and are currently processing them.

Subscribe For Documents

7 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
87
Active Projects
41
Bidding Soon
539
All Active Projects
0
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

July 30, 2025

April 27, 2026

Project location map

Multiple Locations, Winnipeg, MB

Related To This Project


Recently Viewed

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.