Demolition, site work and addition to a water / sewer project in Palm Coast, Florida. Completed plans call for the addition of a water / sewer project; and for site work for a water / sewer project.
The existing Palm Coast WWTF No. 1 is a conventional activated sludge (oxidation-ditch) domestic wastewater plant with a permitted Annual Average Daily Flow (AADF) capacity of 6.83 million gallons per day (MGD) and operates under the Florida Department of Environmental Protection (FDEP) Permit No. FL0116009. The WWTF No.1 expansion will add 4.0 MGD, ADDF treatment capacity using a 5-stage Barenpho treatment process to achieve advanced wastewater treatment (AWT). The existing oxidation ditches will be upgraded to achieve AWT but the scope of this RFP doesn't include the upgrade. CPH Consulting, LLC (Engineer) has been engaged by the City to deliver engineering services for the design and permitting phases of the WWTF No.1 expansion. Wharton-Smith, Inc (Contractor) has been chosen by the City as the general contractor, utilizing the Construction Manager at Risk (CMAR) method. The expansion will add a 4.0 MGD, AADF capacity treatment process by the following units to meet the AWT requirements: 1. Influent pump station 2. Headworks - grit removal and screen equipment 3. Odor control system 4. Flow equalization(EQ) tank with aeration and mixing equipment 5. EQ pumping systems 6. Anerobic tanks 7. Pre-Anoxic tanks 8. Aeration tanks (oxic tanks) 9. Post-Anoxic tanks 10. Reaeration tanks 11. Blower Systems, diffuser systems and DO control system for the oxic zones and reaeration zones 12. Mixing equipment for all anaerobic, fermentation and anoxic tanks 13. Return activated sludge pumps and internal recycle pumps 14. Clarifiers 15. Sludge holding tanks 16. Disk filters 17. Chlorine Contact Chambers (CCC) 18. Reclaimed water transfer pumps 19. Chemical feed systems including alum, Micro-C, sodium hypochlorite, polymer and other chemical storage and feed systems 20. Any other needed improvements for the WWTF No.1 upgrade and expansion Questions Due Date: May 22nd 2025, 2:00 PM EDT
Award
Water / Sewer
$6,000,000.00
Public - City
Addition, Demolition, Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
June 5, 2025
August 4, 2025
Multiple Locations, Palm Coast, FL
Related To This Project
Palm Coast, FL
--
Palm Coast, FL
Bid Date: May 15 2025
Palm Coast, FL
Bid Date: Aug 29 2019
Palm Coast, FL
Bid Date: Jun 13 2025
Palm Coast, FL
Bid Date: Jun 05 2025
Palm Coast, FL
Bid Date: Jul 07 2025
Palm Coast, FL
Bid Date: Jun 24 2025
Palm Coast, FL
Bid Date: Jun 26 2025
Palm Coast, FL
Bid Date: May 23 2025
Palm Coast, FL
Bid Date: May 09 2025
Palm Coast, FL
Bid Date: Apr 11 2025
Palm Coast, FL
Bid Date: May 09 2025
Palm Coast, FL
Bid Date: Oct 14 2020
Palm Coast, FL
Bid Date: Apr 10 2025
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.