Privately Funded
Bidding Soon
Documents Available
Publicly Funded
Addenda Available
Post-Bid
Published August 21, 2025 at 8:00 PM
Updated August 22, 2025
Site work for a water / sewer project in Safety Harbor, Florida. Conceptual plans call for site work for a water / sewer project.
25-0601-ITB-C Philippe Park Wastewater Collection System Improvements (PID 000341G) The construction of shell aggregate must conform to the requirements of Section 204 and 285 of the FDOT Specifications, as amended herein. The work specified under this Section consists of the construction of shell on prepared subgrade, in conformity with the lines, grades, notes and typical cross sections shown in the Plans, and as directed by the Engineer. The construction of Shell must conform to the requirements of this Section, or, in lieu thereof, such requirements as may be established by the Engineer during construction. The Engineer must have full authority to modify the provisions of this Section as deemed necessary, in his opinion, to meet field conditions and requirements. Material for Shell must consist only of Shell and such additive materials as may be approved by the Engineer for the purpose of facilitating construction and achieving the desired characteristics of the finished in-place product. The use of water for this purpose is considered incidental to work performed and will not be paid for separately, regardless if the contract includes a Water for Dust Control pay item. Material which shows a significant tendency toward adverse chemical or physical change on exposure to moisture will not be acceptable. The material must be free of any Ferrous Metals. The specific mechanical and physical properties of Shell and any additive materials permitted in the construction of Shell under this contract must be determined on the basis of test results as the work progresses. The finished in-place product must provide at least an LBR of 100 or greater. Placement and Spreading of Material The material must be transported to the point where it is to be used, over Shell previously placed where possible, and dumped at the end of the preceding spread. Hauling over the subgrade, or dumping on the subgrade for further placement operations, will be permitted only when, in the opinion of the Engineer, such procedures will not adversely affect the integrity of the completed base and subgrade. Spreading must be accomplished by mechanical spreaders capable of producing an even distribution of the Shell. Spreading by other means must be permitted only where and as directed by the Engineer. The minimum thickness of the Shell constructed under this contract must be as specified for the project. Compacting and Finishing Requirements After spreading is completed the shell must be uniformly compacted, with water being added as required, to a density of not less than ninety eight (98%) of the maximum density as determined by AASHTO T- 180. During final compaction operations, if the blading of any areas is necessary to obtain the true grade and cross section, the compacting operations must be completed prior to the performance of density tests on the finished base. Water associated with the use of this material is considered incidental to work performed and will not be paid for separately, regardless if the contract includes a Water for Dust Control pay item. Correction of Defects All defects in materials and construction must be corrected by the Contractor, at the Contractor's expense, and to the satisfaction of the Engineer, as the work progresses. Testing The County must be responsible for all testing performed in connection with the construction of the Shell under this contract. The work consists of furnishing all labor, equipment, and materials for installation of a new PVC riser pipe and cleanout at the ROW line (or other location as directed by the Engineer) on existing sewer lateral. The existing sewer lateral material may be PVC, Vitrified Clay, or DIP pipe. The unit price shall include all costs necessary to install riser pipe and cleanout including mobilization, maintenance of traffic, survey layout (based upon property monuments established by others), material, polyethylene wrap on ductile iron pipe, fittings, pipe cutting, wye unit on main, installation of riser pipe and cleanout, pavement cutting, trenching, dewatering for excavations up to 6-ft deep, sheeting for excavations up to 6-ft deep, bracing, utility crossings, barricades, clearing of the right-of-way, protection of property, backfilling, field layout, restoration, sodding, etc. The pay item shall include cleanout installation up to ten (10) feet in depth. The work consists of all labor, equipment, investigative digging, and materials for repair of an existing connection into manhole wall or to install a new connection. All core drills shall be of sufficient diameter to accommodate pipe connection. Manhole connections may be either gravity sewer or sewer force main. All connections shall include a water stop or boot connection. Payment shall also include core drills, masonry or concrete patching, fiberglass and interior surface patching, shoring, dewatering for excavations up to 6-ft deep, backfill, refill, compaction operations, compaction testing or re-testing, and traffic control. All sewer force main connections shall include installation of a drop bowl, paid for under MANHOLE INSIDE DROP CONNETION pay item. The work does not include excavation or surface restoration which, if required, will be paid for, or is part of the work, under other Contract Pay Items. The work consists of installing long and short side 3/4 ", 1", 1-1/2", and 2" service assemblies for potable and reclaimed water mains. Additional service tubing pipe for short services over 40 feet and long services over 100 feet in length shall be paid for under a separate pay item. Any required service casings for long side services shall be included in the pay item for long service assemblies. 3/4" and 1" service connections shall be made with a CC threaded corporation stop mounted on a service saddle. 1-1/2" and 2" service connections shall be made with an IPS threaded ball corporation stop mounted on a service saddle. The unit bid price shall include installing saddles, corporation stops, ball corporations; color coded potable water service tubing, HDPE or SCH 80 service casing by directional bore (for long service assemblies only), color coded tracer wire, potable or reclaimed water service box, tubing inserts, curb stops, handles on reclaimed service curb stops, meter couplings, meter gaskets, brass nipples, brass bushings, SCH 80 plugs; connections to existing and proposed meters, excavation, backfill, bracing, sheeting, shoring, dewatering, clearing, grubbing, stripping, and trenching; launching pits and receiving pits; bedding and backfill; disposal of soil; surface grading, pressure testing and cleaning; erosion protection and control; and all other related and necessary incidental materials, work and equipment required to construct a complete, operable potable or reclaimed water service assembly as shown in the standard details. The work consists of furnishing all labor, equipment and materials to install additional potable or reclaimed water service tubing with tracer wire that exceed the limits of other pay items. The unit bid price shall include installing color coded HDPE potable or reclaimed water service tubing, color coded tracer wire, tubing inserts, service couplings, excavation, backfill, bracing, sheeting, shoring, dewatering, clearing, grubbing, stripping, and trenching; bedding and backfill; disposal of soil; surface grading, pressure testing and cleaning; erosion protection and control; and all other related and necessary incidental materials, work and equipment required to construct a complete, operable potable or reclaimed water service line. The work consists of furnishing all labor, equipment and materials for disconnecting existing potable or reclaimed water service, relocating and resetting existing meter and backflow device, replacement of meter box, connection to existing pipe or tubing, and reconnecting the meter. Additional service tubing required shall be paid under other pay items. This unit bid price shall include: all materials, labor and tools, necessary for the proper installation of the service, including but not limited to: excavation, removal and control of groundwater and surface water; backfill, bedding materials, disposal of spoil, surface grading, connections to the main, curb stops, meter box, meter couplings, meter gaskets, tapping saddles, tap, testing; and all other related and necessary incidental materials, work and equipment required to construct a complete, operable potable or reclaimed water service as shown in the standard details. The work consists of furnishing and installing underground sewer mains using the horizontal directional drilling (HDD) method of installation. This work shall include all services, equipment, materials, labor, installation of two 14 gauge minimum tracer wires, tracer wire testing, appurtenances, DI/HDPE mechanical joint adapters, pipe and joint restraints for connections to fittings, materials above or below ground along pipeline alignment; joints and jointing materials, bentonite clay slurry seal, launching and receiving pits, exploratory pits; bracing, bedding and backfill, disposal of spoil; pressure testing; pigging, flushing, cleaning erosion protection and control, surface grading, and all other related and necessary materials for the complete and proper installation, testing, and restoration of underground sewer mains The work consists of furnishing all labor, equipment and materials for installing pipe as shown on the plans or directed by the Engineer. All ductile iron pipe shall have polyethylene encasement. The unit price shall include all costs necessary to install the pipe including mobilization, maintenance of traffic, survey layout (based upon property monuments established by others), clearing and grubbing, excavation, sheeting/shoring for excavation up to 6-ft deep, bracing, dewatering for excavations up to 6-ft deep, structural fill, material, polyethylene wrap on ductile iron pipe, testing, pavement cutting, trenching, utility crossings, barricades, clearing of the right-of-way, protection of property, backfilling, field layout, etc. Restoration will be paid for under separate pay items. Work performed for Point Repairs of gravity sewer pipes will be paid for under separate pay items. The work consists of furnishing all labor, equipment and materials and installing sanitary force main pipe by the open-cut method in accordance with the specifications. The unit price shall include all costs necessary to install the pipe up to 6 feet in depth, including: survey layout (based upon property monuments established by others); protection of property; protection of existing utilities, mailboxes and service connections; erosion protection (silt fence, hay bales, floating turbidity barriers, or other means, as required); materials, pavement cutting, extra pipe fitting material including joints/jointing material/restraints; shoring, sheeting for excavations up to 6-ft deep; bracing; utility crossings; barricades; clearing; grubbing and stripping of the right-of-way; trenching, bedding and backfilling; pigging; flushing and cleaning; pressure testing. Fittings shall be included in the cost of 2" pipe. Dual tracer wire and tracer wire testing shall be included in the price for PVC pipe items. Polyethylene encasement shall be included in the bid price for DI pipe items. Restoration will be paid for under separate pay items. Additional payment will be made for extra depth installation over six feet. Well point dewatering is an authorized pay item only when the installation is below 6 feet in depth and site conditions warrant; all dewatering up to 6 feet in depth is included in this pay item. The work consists of furnishing all labor, equipment and materials for installing ductile iron fittings not included in other items. All fitting shall include and be installed with joint restraints. The unit price includes furnishing and installing all fittings and materials above or below ground along the pipeline alignment; joints, joint restrainers, and jointing materials; bracing, shoring, and sheeting; dewatering, clearing, grubbing, and stripping; trenching, bedding and backfill; constructing the specified protection and adjusting of existing above ground and underground utilities and service connections; disposal of spoil; color coded polyethylene encasement; pressure testing; erosion protection and control, and all other related and necessary materials, work and equipment required to construct a complete, operable pipeline. The cost of furnishing and installing joint restraints shall be included in the unit price for Ductile Iron Fittings. The work consists of installing air release assemblies on sanitary sewer force mains. The unit bid price shall include installing the air release assembly, testing, excavation, backfill, bracing, shoring, sheeting for excavations up to 6-ft deep, dewatering for excavations up to 6-ft deep, surface grading, erosion protection and control, furnishing and installing tap saddle, tap, corporation stop, ball corporation, curb stop, automatic air release valve, enclosure, testing, miscellaneous brass nipples and fittings, and incidental items required to install a new assembly as shown on the standard detail. All assemblies shall include tracer wire access, drainage gravel and miscellaneous nipples and fittings as shown in the standard details, filter fabric, valve identification tags, paint reference stripe on curb, painting of valve cover and meter boxes. The work consists of furnishing all labor, equipment and materials for installing a valve not included in other items. The unit bid price includes furnishing and installing valves, valve boxes and covers, color coded polyethylene encasement, tracer wire access, filter fabric, valve identification tags, paint reference stripe on curb, painting of valve cover, concrete valve box pad, extension stems, joint restraints, pressure testing, excavation, backfill, dewatering for excavations up to 6-ft deep, sheeting for excavations up to 6-ft deep, shoring, surface grading and incidental construction associated with these items. Pinellas County is planning improvements to the wastewater collection system in Philippe Park located in Safety Harbor, Pinellas County, Florida. The improvements include four (4) new lift stations and approximately 2,800 lineal feet (LF) of 4-inch diameter force main. The majority of the force main is planned to be installed by open trench methods; however, horizontal direction drill (HDD) installation is planned from Station 10+25 to Station 14+50 (refer to Sheet 18 of 30% Plans). The pipe sections installed via open trench methods will consist of Polyvinyl Chloride (PVC), while the pipe sections installed via HDD will be High Density Polyethylene (HDPE). The planned invert depth of the force main will be less than 5 feet below ground surface (bgs). The proposed lift station wet wells are approximately 4 feet in diameter and will extend to a depth of 10 feet bgs. Measurement and payment of this pay item is based on the actual number of gate valves (M.J. or flanged) and boxes with concrete slabs installed in accordance with the Drawings and Specifications. The work shall include all labor, equipment and materials, coatings, testing, and any required incidentals necessary to completely install the valves. The unit bid price includes furnishing and installing valves, valve boxes and covers, color coded polyethylene encasement, protective coatings, tracer wire access, filter fabric, valve identification tags, paint reference stripe on curb, painting of valve cover, concrete valve box pad, extension stems, pressure testing, excavation, backfill, dewatering, sheeting, shoring, surface grading, demolition, removal, and disposal of any existing equipment if not a new installation and incidental construction associated with these items. Measurement and payment of this pay item is based on the actual number of check valves (flanged) installed in accordance with the Drawings and Specifications. The work shall include all labor, equipment and materials, coatings, testing, and any required incidentals necessary to completely install the valves. The unit bid price includes furnishing and installing check valves, protective coatings, pressure testing, dewatering, demolition, removal, and disposal of any existing equipment if not a new installation and incidental construction associated with these items. The work consists of furnishing all labor, equipment, materials and supervision necessary for the installation of stainless steel fittings and restraints. No coatings are required. Restraints for stainless steel fittings and flange pipe shall include stainless steel bolts, nuts, lock washers and gaskets. The unit price shall contain all costs necessary to procure the fittings with flanges, install the fittings, disposal of removed fittings, joint restraints (SS bolts, nuts and lock washers and gasket), property protection, pressure testing, and all other related and necessary materials required to install fittings in accordance with the Contract Documents. The work consists of furnishing all labor, equipment, materials and supervision necessary for the removal of existing riser and through pipes to value vault if required and the installation or replacement with stainless steel riser and through pipes (pump discharge connection to check valve in valve vault). The unit price shall contain all costs necessary to procure the pipe, install the pipe as required for the proper fit and to meet the field measured conditions, cutting the pipe, disposal of removed pipe, 1/2" welded threaded boss (IPS) for each pressure gauge connections in valve vault, core and seal boots, right- of-way clearing, trench safety, furnishing and installing pipe bedding, utility crossings, property protection, pressure testing, and all other related and necessary materials required to construct a complete and operable pipeline in accordance with the Contract Documents. Stainless steel pipe flanges will be paid for under another Pay Item and is not included in the work for this Pay Item. The work consists of furnishing all labor, equipment, materials and supervision necessary for the installation of 1/2" stainless steel pressure gauge ports. The unit price shall contain all costs necessary to procure and install the material, %" IPS direct drill and tap on ductile iron pipe, drilled through boss on stainless steel pipe, V2" X4" stainless steel IPS nipple, Vi' stainless steel ball valve and V2" SCH 80 PVC plug, and all other related and necessary materials required to install stainless steel pressure gauge connections in accordance with the Contract Documents. Stainless steel threaded boss and welding to the pipe will be paid for under another Pay Item and is not included in the work for this Pay Item. The work consists of furnishing all labor, equipment, materials and supervision necessary for the installation of adjustable pipe saddle supports with stainless steel pipe and base. The unit price shall contain all costs necessary to procure the saddles, install the saddles, disposal of removed saddles, grouting of base, protective coatings (not including Corrosion Control coatings), property protection, and all other related and necessary materials required to install pipe saddles in accordance with the Contract Documents. Scope of Work 7.1. OBJECTIVE/JUSTIFICATION Work in this project includes the installation of a new wastewater collection system consisting of approximately 2,800 linear feet of force main and four wastewater pumping stations in Philippe Park that will replace four onsite septic collection systems. The new system will connect to the City of Safety Harbor's wastewater collection system through the existing Lift Station No. 614. In addition, approximately 50 linear feet of the Lift Station No. 614 force main will be replaced at both the Lift Station and the discharge manhole. Additionally, this project is partially funded with grant funds from the Florida Department of Environmental Protection. Please see Appendix 4 Special Notices for grant requirements under this contract. 7.2. BACKGROUND The County requested a project to review the existing aging sanitary sewer infrastructure within Philippe Park. The current septic system is at risk of failure which requires significant additional regular maintenance. As stewards of public resources, rehabilitation and transformation of the existing sanitary system aims to eliminate ongoing risk of wastewater contamination into the groundwater system as well as the environmentally sensitive portion of upper Old Tampa Bay. Efforts undertaken in this project will align with the County's desire to identify and address existing infrastructure as potential opportunities for environmental and fiscal stewardship by increasing infrastructure resiliency and protect or improve environmentally sensitive areas.
Project Abandoned
Water / Sewer
$3,470,000.00
Public - County
Site Work
We’ve obtained documents for this project and are currently processing them.
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
August 21, 2025
October 24, 2025
2525 Philippe Park Dr, Safety Harbor, FL
Related To This Project
Safety Harbor, FL
Bid Date: Sep 03 2025
Safety Harbor, FL
Bid Date: Dec 01 2025
Safety Harbor, FL
Bid Date: Nov 18 2025
Safety Harbor, FL
Bid Date: Aug 26 2025
Safety Harbor, FL
--
Safety Harbor, FL
Bid Date: May 05 2025
Safety Harbor, FL
Bid Date: Mar 11 2025
Safety Harbor, FL
--
Safety Harbor, FL
--
Safety Harbor, FL
--
Safety Harbor, FL
--
Safety Harbor, FL
--
Safety Harbor, FL
--
Safety Harbor, FL
--
Bid Smarter, Not Harder
Spend more time doing the job than looking for it. ConstructConnect has the industry's most complete project data to help you find, bid, and win. Now.
Sign up to get free access, instantly.
