Site work for a water / sewer project in Birmingham, Pennsylvania. Completed plans call for site work for a one-story above grade water / sewer project.
As of January 20, 2026, the project is awarded to John Claar Excavating, Inc - $134,993.00 Stelco, Inc. - $31,480.00 with total awarded amount of $166,473. Question Deadline 11/25/2025 All questions shall be submitted using Online. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered. A. The Work of Project is defined by the Contract Documents and consists of the following 1. Project generally includes, but is not limited to rehabilitation of an existing pump station and surrounding site. B. Type of Contract: 1. Project will be constructed under coordinated, concurrent multiple contracts. See Section 01 12 00 "Multiple Contract Summary" for a description of work included under each of the multiple contracts. Contracts for this Project include the following: a. Contract No. 2025-01: General Construction b. Contract No. 2025-02: Electrical Construction The Project includes the following Work Construction of stormwater infrastructure and associated site work. Replacement of existing standby generator and automatic transfer switch. Construction of a roofed pavilion to provide shelter over the existing control panel. Replacement of the concrete pads for the generator and propane tank. Installation of site lighting. Grouting of pipe penetrations of the wet well and force main discharge manhole followed by the lining of the wet well and force main discharge manhole with a polyurea liner. The Northern Blair County Regional Sewer Authority is requesting bids for the Roots Pump Station Rehabilitation Project. The scope of work includes construction of stormwater infrastructure and associated site work, replacement of the existing standby generator and automatic transfer switch, construction of a roofed pavilion to provide shelter over the existing control panel, replacement of the concrete pads for the generator and propane tank, installation of site lighting, grouting of pipe penetrations of the wet well and force main discharge manhole, followed by the lining of the wet well and force main discharge manhole with a polyurea liner. Separate bids will be received for General Construction and Electrical Construction contracts. Bidders should register with the designated website to receive all official notifications, addenda, and documents. Bid security in the form of a Certified Check or Bid Bond in an amount not less than 10% must be furnished with the bid. All questions about the bidding documents are to be submitted via PennBid. Bidders are required to submit an executed non-collusion affidavit and a Public Works Employment Verification Form. The Pennsylvania Prevailing Wage Act applies, and all bids shall be irrevocable for 60 days after the opening date. Discrimination on the basis of gender, race, color, creed, sex, age, physical disability, or national origin is prohibited. Bid Result General Construction John Claar Excavating, Inc. $ 134,993 Electrical Construction Stelco, Inc $ 31,480.
Award
Water / Sewer
$166,473.00
Public - County
Site Work
Trades Specified
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
Find More Local Projects
Within 75 Miles of This Project
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
December 2, 2025
January 1, 2026
Roots Pump Station Ski Gap Road, Birmingham, PA
Related To This Project
Birmingham, PA
Bid Date: Mar 13 2025
Birmingham, PA
Bid Date: Jan 30 2025
Birmingham, PA
Bid Date: Sep 06 2022
Birmingham, PA
--
Philadelphia, PA
Bid Date: Nov 24 2025
Akron, PA
Bid Date: Nov 18 2025
Highspire, PA
Bid Date: Dec 04 2025
Oil City, PA
Bid Date: Nov 12 2025
Howard, PA
Bid Date: Nov 19 2025
Smethport, PA
Bid Date: Nov 25 2025
Philadelphia, PA
Bid Date: Jun 15 2026
Quarryville, PA
Bid Date: Dec 04 2025
Charleroi, PA
Bid Date: Nov 21 2025
Philadelphia, PA
--
Preview Active Commercial Construction Projects Like This One
Get preview access now—no credit card required.