Site work, paving and new construction of a mixed-use development in Monterey, California. Design plans call for the construction of a 67,000-square-foot transportation facility; for site work for a road / highway; for paving for a road / highway; and fire / police facility.
As of August 7, 2024, this project is in design. There is a tentative plan for solicitation for an RFP for a general contractor to go out in late November 2024 with bids due January 2025. A timeline for construction has yet to be announced. The original solicitation is preserved below for reference. New Passenger Terminal Facility (Project) that includes associated landside support facilities at the Monterey Regional Airport (MRY or Airport). The Airport seeks a design team (Design Team or Consultant) under a single, responsible lead Architect who will be responsible for the delivery of the design of the Project. Unless expressly stated otherwise, experience and qualifications shall be evaluated based upon the combined experience and qualifications of the Proposer's Team. The selection of the Consultant will follow the Federal Aviation Administration's (FAA) Advisory Circular 150/5100-14 (latest edition), ARCHITECTURAL, ENGINEERING, AND PLANNING CONSULTANT SERVICES FOR AIRPORT GRANT PROJECTS A statement of your firm's interest and qualifications regarding these projects is herein solicited. The SOQ should include detailed information regarding the consultant's interest, qualifications, and current relative experience with the following tasks: The new Terminal project is a component of the overall Safety Enhancement Program (SEP) program. The design will include the proposed Terminal building and landside improvements. The Airport has planned for the relocation of the existing Aircraft Rescue and Fire Fighting Facility (ARFF), and the new Terminal Apron pavement components of the SEP, to be constructed and complete prior to the new Terminal construction. The new Passenger Terminal Building has been programmed/planned as a two-level concourse with a gross building areaexcluding the PPBsof approximately 65,000 square feet. A terminal space planning analyses was performed in 2021 to determine the right size of the building and equate the planned size to the cost of development for purposes of evaluating the financial feasibility The new terminal facility is planned to be the modest space requirements and will accommodate five (5) PBB gates with the remaining ramp area designated as future expansion and Remain-Over-Night (RON) gates, and to provide an "Optimum" level of service (LOS) and guest experience in accordance with the International Air Transport Association (IATA) standards. Please note that this is for a Request for Qualifications; a detailed cost proposal is not being requested at this time. The Airport assumes no obligation in the solicitation of this general statement of interest and qualifications and all costs shall be borne by the interested consultants. The Airport intends to shortlist and then select a Design Team who will provide the design vision, innovation and ingenuity for the design of a new relocated airport terminal, based upon the planning concepts of the SEP. The Monterey Peninsula Airport District encourages qualified Disadvantaged Business Enterprises to respond to this solicitation and to participate in these projects Federal requirements: a. Access to records and re ports. (reference: 49 cfr part 18.36(I), 49 cfr part 18.42) b. Buy american preference. (reference: 49 usc 50101) c. Airport and airway improve ment act of 1982, section 520 (reference: 49 u.S.C. 47123) d. Civil rights general. (refer ence: 49 usc 47123) e. Civil rights title vi assuran ces. F. Disadvantaged business en terprise. (reference: 49 cfr part 26) g. Energy conservation require ments. Source: 49 cfr part 18.36(I)(13) h. Federal fair labor stand ards act (federal minimum wage) (reference: 29 usc 201, et seq.) I. Occupational safety and health act of 1970 (reference 20 cfr part 1910) j. Right to inventions (refer ence 49 cfr part 18.36(I)(8)) k. Trade restriction (reference: 49 cfr part 30) l. Veteran's preference (refer ence: 49 usc 47112(c)) m. Seismic safety n. Copeland "Anti-kickback" act (reference: 49 cfr 18.36(I)(4), 29 cfr parts 3 & 5) o. Certification of offerer/bidder regarding de barment p. Davis bacon requirements. (reference: 49 cfr 18.36(I)(5)) q. Texting while driving. (refer ence: executive order 13513) r. Affirmative action require ment. (reference: 41 cfr part 60-4, executive order 11246) s. Equal opportunity clause and specifications. (reference 41 cfr 60-1.4, executive order 1 1246) t. Nonsegregated facilities re quirement. (reference: 41 cfr 60-1.8) u. Recovered material. (refer ence: 40 cfr part 247) v. Termination of contract. (reference: 49 cfr 18.36(I)(2)) w. Debarment and suspension (non-procurement). (refer ence: 2 cfr part 180 (subpart c), 2 cfr part 1200, dot order 4200.5 dot suspension & debarment procedures & ineligibility) x. Contract workhours and safety standards act re quirements. (reference: 49 cfr 18.36(I)(6)) y. Lobbying and influencing fed eral employees. . (reference: 49 cfr part 20, appendix a) z. Breach of contract terms. (reference 49 cfr part 18.36(I)(1)) aa. Clean air and water pollu tion control. (reference: 49 cfr 18.36(I)(12)) bb. Drug free workplace The method of Contractor Selection has not been Determined at this time.
Design
Transportation Terminals
$65,000,000.00
Public - City
New Construction, Paving, Site Work
We’ve obtained documents for this project and are currently processing them.
Trades Specified
Division 00 - Lorem Ipsum
Find More Local Projects
Within 75 Miles of This Project
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Market Pricing Around
- All Starter Product functionality
- Access to all documents (plans, specifications, and addenda)
- Access to planning projects
- Access to contact information
- Ability to Export
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
February 3, 2025
200 Fred Kane Dr, Monterey, CA
Related To This Project
Monterey, CA
Bid Date: May 24 2022
Monterey, CA
Bid Date: Jul 19 2022
Monterey, CA
Bid Date: Jul 22 2022
Monterey, CA
Bid Date: Aug 18 2020
Monterey, CA
Bid Date: Jul 30 2019
Monterey, CA
--
Monterey, CA
Bid Date: Aug 16 2022
Monterey, CA
Bid Date: Jun 27 2022
Monterey, CA
Bid Date: Feb 14 2023
Monterey, CA
Bid Date: Jun 02 2022
Monterey, CA
Bid Date: Jun 03 2022
Monterey, CA
Bid Date: May 24 2022
Monterey, CA
Bid Date: Apr 14 2022
Recently Viewed
--
--
--
--
--
--
--
--
--
--
Try it free. The data you need to build the relationships you want.
Sign up now to get free company and project data. No payment required.
Get the right
data with Project Intelligence
Project Shared
with
example@example.com
Choose what you would like to do.
Seen enough? Want to see more? Subscribe on your own or talk to one of our sales reps.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.