Site work for a bridge / tunnel in Oregon, Ohio. Completed plans call for site work for a bridge / tunnel.

As of April 10, 2025, project was awarded to Miller Brothers Construction, Inc., awarded amount is $897,717.76. The work on this project consists of the rehabilitation of the existing bridge on the Toledo-Lucas County Port Authority Facility 3 Access Road over the Bayshore power plant (First Energy) discharge channel. The contractor will be responsible for furnishing all labor, supervision, permits, equipment, shop drawings, tools, services, testing, and incidentals required to complete the work required by the bid documents, project technical specifications, project construction drawings and contract documents. The contractor will also be responsible for covering the cost of all materials except for the structures pre-purchased from Valmont and bearing pads and plates pre-purchased from others, as well as receiving the items when delivered and for all installation costs. The engineer's estimate for the base bid is approximately $1.2 million. Bids that are in excess of 10% above the engineer's estimate would be considered non-responsive. This project may be awarded by the Toledo-Lucas County Port Authority at its sole discretion. The Port Authority reserves the right to reject any or all bids, and to waive any technicalities as it may deem best for their interest. The Port Authority also reserves the right to add or subtract from quantities shown in the proposal. Electronic Proposals must be submitted on the form(s) included in online and shall be accompanied by a certified check or an acceptable Proposal Bond with satisfactory surety specifying the Toledo-Lucas County Port Authority as the obligee, in the sum of not less than ten percent (10%) of the total proposal amount. Question Deadline 03/11/2025 at 10:00 AM ET

Award

Bridges / Tunnels

$897,717.00

Public - City

Site Work

12

3

68

5

Subscribe For Documents

30 Record(s)

Subscribe for All Details

Trades Specified

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet

Find More Local Projects

Within 75 Miles of This Project
330
Active Projects
173
Bidding Soon
2,386
All Active Projects
0
Updated Recently

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

March 18, 2025

May 19, 2025

Project location map

Multiple Locations, Oregon, OH

Fuel growth with access to the bidding project info your business needs.

Full details, including key contact information, important dates, plans and specifications, on over 500,000 Projects including 5000 updated daily available to subscribers.